Abbyad v. Mathes Group

671 So. 2d 958, 1996 WL 112977
CourtLouisiana Court of Appeal
DecidedMarch 14, 1996
Docket95-CA-1543
StatusPublished
Cited by3 cases

This text of 671 So. 2d 958 (Abbyad v. Mathes Group) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abbyad v. Mathes Group, 671 So. 2d 958, 1996 WL 112977 (La. Ct. App. 1996).

Opinion

671 So.2d 958 (1996)

Charles ABBYAD and Jill Abbyad d/b/a The Chimes Cottages
v.
The MATHES GROUP, a Professional Architectural Corporation, and Jeffrey Thomas Avegno, Inc.

No. 95-CA-1543.

Court of Appeal of Louisiana, Fourth Circuit.

March 14, 1996.

*959 House, Golden, Kingsmill & Riess, W. Richard House, Jr., Randal R. Cangelosi, New Orleans, for Plaintiffs-Appellants Charles Abbyad and Jill Abbyad d/b/a The Chimes Cottages.

William E. Wright, Jr., Deutsch, Kerrigan & Stiles, New Orleans, for Defendant-Appellant The Mathes Group, a Professional Architectural Corporation.

Before KLEES, BYRNES and MURRAY, JJ.

KLEES, Judge.

Plaintiffs, Charles and Jill Abbyad ["the Abbyads"], initiated this suit against The Mathes Group ["Mathes"] and Jeffrey Thomas Avegno, Inc. ["JTA"], alleging that the defendants were negligent in rendering certain architectural and engineering services during the renovation and expansion of plaintiffs' home, which they also operated as a bed and breakfast. Mathes reconvened seeking *960 unpaid fees the Abbyads allegedly owed for the architectural services performed.

In November 1994, following a five-day trial, the jury found Mathes to be 70% at fault, the plaintiffs to be 25% at fault, and the plaintiffs' contractor, Gill Gagnon (not a party to the suit) to be 5% at fault. The jury did not assign any percentage of fault to JTA. Additionally, the jury found plaintiffs had incurred $95,000 in pecuniary damages, and declined to award plaintiffs any amount for mental anguish. Finally, the jury found that plaintiffs owed Mathes $4,000 for architectural services rendered.

On February 7, 1995, the trial court rendered judgment in accordance with the jury findings, awarding plaintiffs $62,500 plus interest and costs. Both Mathes and the Abbyads have appealed this decision. Each side contends that the jury's findings with regard to the allocation of comparative fault and the amount of damages are clearly erroneous. After reviewing the record, we find no manifest error in the jury's conclusion.

FACTS

In April of 1991, the Abbyads met with several architects of Mathes to discuss additions the Abbyads wanted to make to the Chimes Cottages, a bed and breakfast operated by them at their residence, which consisted of a one-story, five-room house and a detached two-room cottage. At this meeting, the Abbyads expressed their desire to add a second floor to the main house plus attic space which could be converted into bedrooms and a bathroom for their children. On the advice of Charles Montgomery, one of the Mathes architects, the Abbyads decided to include in the project two five-foot wings, one on each side of the house, to make it appear more symmetric. The Abbyads stated that their budget for the project was about $125,000. Although Mathes initially wanted a percentage of the cost to perform full architectural services on the project, it was eventually agreed that Mathes would be paid approximately $2,500 to $3,000 to design the additions, draw all the plans and obtain the necessary permits. The Abbyads indicated that they did not need full architectural services, which would include contract administration, presumably because they had already hired a general contractor named Gill Gagnon to oversee the project. Mr. Gagnon was present at the initial meeting between the Mathes architects and the Abbyads. Mathes hired co-defendant JTA, an engineering corporation, to assist with the structural engineering aspects of the project.

As the project progressed, two problems were encountered that plaintiffs claim made it necessary in August of 1991 for them to abandon the project as originally envisioned, demolish the first floor structure, and start over. About August 2, 1991, after the house had been raised and a new foundation had been poured, the Abbyads' framer discovered a "notched joist" condition, which had to be corrected before the work could progress. Mr. Abbyad contacted Mathes, who sent out someone to investigate. Mathes' proposed solution was to install "joint hangers," which suggestion was incorporated into a new set of plans submitted August 24, 1991.

On or about August 26, 1991, after the roof had been removed from the house, a more significant problem occurred when the Abbyads learned that the second floor and attic space could not be added without replacing the existing 2 × 4 studs in the walls of the first floor with 2 × 6 foot studs, which were required to obtain a city permit. At this point the Abbyads decided that the project as originally envisioned was not feasible, and within two days they had the house demolished.

The lawsuit filed by the Abbyads against Mathes and JTA was based on the allegation that the defendants were negligent in failing to discover and make known to them at an earlier time these two conditions, the notched joists and the need for 2 × 6 foot studs. Plaintiffs allege particularly that the lack of 2 × 6 foot studs made it impossible for the first floor to support the planned addition, and that had they been made aware of this fact, they would have never commenced the project.

Liability

Mathes contends on appeal that the jury's allocation of 70% of the fault to Mathes is too high; conversely, plaintiffs contend that the jury should have assigned 100% of the fault *961 to Mathes and/or JTA. Plaintiffs argue that the jury erred not only in assigning 25% fault to the Abbyads, but also in assigning 5% to Gill Gagnon, a non-party, and in assigning none to JTA. After reviewing the record, we find no manifest error in the jury's determination of fault.

The record clearly contains sufficient evidence to support the jury's finding of 70% fault on the part of Mathes. The Abbyads were told by architect Mark Gates of Mathes in April of 1991 that the existing structure of the house would support a second story and attic. Between April 26, 1991 and June 29, 1991, neither Mathes nor JTA ever conducted any measurement of the wall studs. On June 3rd, Mathes applied to the city for a permit to raise the Abbyad's house, which permit was issued on June 5th. The Abbyads began raising the house. On June 29th, Mr. Thomas of JTA submitted foundation drawings and at the same time sent Mark Gates of Mathes a note saying "we still need to determine bearing wall studs". According to Mr. Abbyad, Gates examined the wall studs in early July and at that time indicated to Mr. Abbyad that as long as the studs were "true" two-by-fours, they would be sufficient to support the second story addition. This advice was proven at trial to be a clear violation of the New Orleans Building Code. The need for 2 × 6 foot studs was first indicated in a set of plans submitted to the city permit office on July 15th, but plaintiffs contended they were not made aware of this fact until late August. Plaintiffs' expert, Stephen Craig Ratley, testified that by waiting so long to measure the wall studs, Gates breached the standard of care required of an architect.

In view of this evidence, we find the jury's assignment of 70% to Mathes to be reasonable. It was also reasonable for the jury to find no fault on the part of JTA, as the record is devoid of any evidence which indicates that JTA's conduct fell below that required of the engineering profession. In response to Mathes' arguments, we also find the jury's decision to apportion 25% of the fault to the Abbyads to be reasonable in light of the record. Although Mr. Abbyad testified that he felt he had to demolish his house because it was no longer feasible to continue as planned, the record does not fully support this.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Snow Manufacturing Co. v. Snowizard Holdings, Inc.
921 F. Supp. 2d 527 (E.D. Louisiana, 2013)
Roberson v. Al's Pest Control Service, Inc.
713 So. 2d 641 (Louisiana Court of Appeal, 1998)
Dual Drilling Co. v. MILLS EQUIPMENT INVS., INC.
705 So. 2d 1246 (Louisiana Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
671 So. 2d 958, 1996 WL 112977, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abbyad-v-mathes-group-lactapp-1996.