A.A.R.R. Co. v. . Johnson

31 N.E. 903, 134 N.Y. 375, 1892 N.Y. LEXIS 1526
CourtNew York Court of Appeals
DecidedOctober 1, 1892
StatusPublished
Cited by4 cases

This text of 31 N.E. 903 (A.A.R.R. Co. v. . Johnson) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A.A.R.R. Co. v. . Johnson, 31 N.E. 903, 134 N.Y. 375, 1892 N.Y. LEXIS 1526 (N.Y. 1892).

Opinion

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 377

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 378 The plaintiff by the instrument of April 6, 1886, leased to the defendants for the term of its corporate existence the right to use an existing street railroad of about one mile in length, and agreed to perfect its chartered rights to extend the railroad about four miles further, and to confer such rights upon the defendants, who agreed to act under such perfected rights and to complete the extension, and as *Page 379 completed the lease was to attach to it; and the defendants agreed to operate both the old and the extension as a cable railroad. The rent reserved to the plaintiffs was to be at the rate of fourteen per centum of the gross earnings of the railroad and without any guaranty of the amount until October 1, 1886; but from and after that date the defendants guaranteed that the rent should not be less than $15,000 per annum. This action is to recover the guaranteed rent from February 1, 1887, to October 1, 1887. The defendants' answer in substance is that the guaranty was dependent upon the performance by the plaintiff of the conditions precedent, which were necessary to enable the defendants to complete the contemplated extension, and that these were not performed by the plaintiff, and thus the guaranty never became operative.

By the agreement, which for convenience may be called a lease, the plaintiff agreed to obtain the consents of the local authorities and property holders, which by statute, Ch. 252, Laws 1884, § 3, were necessary to perfect its right to construct the extension, "so as to allow the work of the second party to proceed without hindrance." The defendants agreed that "the said railroad shall be completed and the cars run thereon from Broadway to Fulton ferry on or before November 15, 1886." This required the completion of about one and one-half miles of the proposed extension. But the plaintiff did not procure the requisite consents until in October, 1886, and thus the defendants could not "proceed without hindrance," but were prevented from proceeding at all until after the day fixed for the guaranteed rent to begin.

It was provided in the lease that "in case the party of the first part shall be unable to procure the requisite consents for the construction of a cable road within sixty days from the execution of this agreement, and shall give notice of such failure in writing to the party of the second part, this lease and agreement shall, at the option of the said party of the second part, cease and determine," but the plaintiff, notwithstanding its failure, gave no notice thereof to the defendants.

By this delay the defendants suffered the loss of the season *Page 380 most suitable for the work of construction. They commenced it, however, in October, 1886, and prosecuted it with diligence. Beyond Broadway the most considerable part of the remainder of the proposed extension lay in Central avenue. The defendants commenced the work of construction upon this avenue in February, 1887. The Broadway Railroad Company of Brooklyn, assuming to act under the authority granted to it by Ch. 461, Laws of 1860, had already commenced the construction of a railroad upon the same avenue.

The trial court found that its consent was necessary to allow the work of the defendants to "proceed without hindrance," and that that consent was refused. Three several actions were commenced in the Supreme Court; one by this plaintiff against the Broadway Railroad Company, one in the interest of this plaintiff against the same defendant, and the third in the interest of the said Broadway company against this plaintiff, all involving the plaintiff's right to construct its railroad in Central avenue. The result was that about July 1, 1887, this plaintiff was enjoined by the court from proceeding with the construction of the railroad therein. This injunction was effective to prevent the defendants from completing the railroad. Meantime, the defendants had assigned the lease to the Brooklyn Cable Company, a corporation organized, professedly, pursuant to the terms of the lease to take such assignment. The plaintiff alleges that the assignment is invalid because the corporation has not the paid-up capital required by the lease in case of an assignment, but we do not think it necessary to pursue this question. The defendants and their assignee had spent large sums of money in the construction of the extension of the railroad.

About July 20, 1887, shortly after the injunction, the Brooklyn Cable Company notified the plaintiff that it would hold the lease as broken by the non-performance of its conditions to be performed by the plaintiff, and that it was ready to surrender to the plaintiff all the property it had received under the agreement, upon being reimbursed for its expenditures in complying with the contract. The plaintiff paid no attention *Page 381 to this notice. The trial court found that the portions of the route contemplated by the lease, upon which the defendants and their assignee were unable to construct and operate a railroad, were material and substantial parts thereof, and the failure of the plaintiff to procure the requisite consents prevented such construction and operation.

The plaintiff claims that it leased to defendants a railroad in being, and delivered possession of it to them, and also made certain covenants to promote the building and operation of its extension by the defendants; that the lease is complete, and plaintiff's default, if any, in regard to the extension, is no defense to the action for rent, and can only avail the defendants as a counterclaim, and this they have not pleaded.

The defendants claim that the lease was executory — at least as to the guaranteed amount; that the covenants of the lease were in this respect mutual and dependent, and that the certain amount of rent was guaranteed because the plaintiff's covenants, if performed, would have given to the defendants an opportunity to complete the railroad early enough to enable them to try to earn the rent they guaranteed to pay; and that the breach of the covenants on the part of the plaintiff resulted in the non-creation of that part of the railroad whose contemplated earnings were a substantial part of the consideration for the defendants' guaranty of a fixed amount of rent; also that the delivery of the perfected right to construct the extension was never fully made.

We think the judgment must be affirmed.

The lease recited that the agreements expressed in it were "for and in consideration of the mutual covenants and agreements herein contained, and by each of said parties to be observed and performed."

The lease was two fold in its character; the plaintiff demised to the defendants an existing railroad, and reserved a percentage of its gross earnings as rent. It also assumed to demise its franchise and right to operate an additional line of railroad. We assume, without deciding, that the lease was valid. (Woodruff v. Erie Railway Co., 93 N.Y. 609.) The defendants *Page 382 were ready and willing to treat it as valid. But the additional line of railroad had no existence, and the plaintiff's right to construct it was incomplete, and would remain so until it should procure the requisite consents of the property owners and city authorities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alderson v. Republican-Courier Co.
221 P. 544 (Montana Supreme Court, 1923)
Kinney v. Eckenberger
145 P. 665 (Oregon Supreme Court, 1915)
People Ex Rel. Warschauer v. . Dalton
53 N.E. 1113 (New York Court of Appeals, 1899)
Johnson v. Atlantic Avenue Railroad
27 N.Y.S. 584 (New York Supreme Court, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
31 N.E. 903, 134 N.Y. 375, 1892 N.Y. LEXIS 1526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aarr-co-v-johnson-ny-1892.