Opinion

Order, Supreme Court, New York County (Louise Gruner Gans, J.), entered on or about March 19, 2001, which denied petitioner’s application to discharge or reduce respondent’s mechanic’s lien, unanimously affirmed, without costs.

Pertinent provisions of the parties’ contract governing respondent’s renovation of petitioner’s apartment provide for a final payment “on the date the job is completed and signed [off] by [petitioner’s] Architect,” with any disputes as to the quality of the work and whether or not it has been completed to be resolved solely and finally by petitioner’s architect. Respondent filed a notice of mechanic’s lien for an amount approximating the final payment specified in the contract, which lien petitioner seeks to discharge on the ground that the final payment is not due since her architect never signed off on the job. The application was properly denied since it does not appear from the face of the lien that it is invalid “by reason of the character of the labor or materials furnished” (Lien Law § 19 [6]) or for any other reason set forth in section 19 (see, Matter of Supreme Plumbing Co. v Seadco Bldg. Corp., 224 App Div 844). Rather, the validity of the lien plainly turns on a dispute as to whether respondent has completed the work required by the contract, and, accordingly, must await trial of the foreclosure action (see, Care Sys. v Laramee, 155 AD2d 770, 771; Matter of Atlantic Cement Co. v St. Lawrence Cement Co., 22 AD2d 228). Nor should the lien be reduced on the basis of the contract clause providing damages for delay, which in petitioner’s view results in the lien being exaggerated. Although Lien Law § 39 provides that a willfully exaggerated lien is void, the issue of willful or fraudulent exaggeration is one that also ordinarily must be determined at the trial of the foreclosure action (see, Coppola Gen. Contr. Corp. v Noble House Constr., 224 AD2d 856). We have considered petitioner’s other arguments and find them unavailing. The best resolution of this matter is that there be a speedy trial, to which the parties committed themselves on oral agreement. Concur — Ellerin, J.P., Lerner, Rubin, Buckley and Friedman, JJ.

Free access — add to your briefcase to read the full text and ask questions with AI

Aaron v. Great Bay Contracting, Inc., 290 A.D.2d 326, 736 N.Y.S.2d 359, 2002 N.Y. App. Div. LEXIS 409 (N.Y. Ct. App. 2002).

290 A.D.2d 326 (Aaron v. Great Bay Contracting, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Matter of Broadway PT 1710 LLC v. Kingdom Assoc., Inc.
Appellate Division of the Supreme Court of New York, 2026
J.T. Magen & Co., Inc. v. Nissan N. Am., Inc.
2019 NY Slip Op 8784 (Appellate Division of the Supreme Court of New York, 2019)
Matter of Beebe v. Liebel
2019 NY Slip Op 337 (Appellate Division of the Supreme Court of New York, 2019)
Matter of Rigano v. Vibar Constr., Inc.
131 A.D.3d 1252 (Appellate Division of the Supreme Court of New York, 2015)
On the Level Enterprises, Inc. v. 49 East Houston LLC
100 A.D.3d 473 (Appellate Division of the Supreme Court of New York, 2012)
NDL Associates, Inc. v. Villanova Heights, Inc.
99 A.D.3d 450 (Appellate Division of the Supreme Court of New York, 2012)
Bryan's Quality Plus, LLC v. Dorime
80 A.D.3d 639 (Appellate Division of the Supreme Court of New York, 2011)
Northside Tower Realty, LLC v. Klin Construction Group, Inc.
73 A.D.3d 1072 (Appellate Division of the Supreme Court of New York, 2010)
Turbo Carpentry Corp. v. Brancadoro
21 A.D.3d 479 (Appellate Division of the Supreme Court of New York, 2005)
In re Lowe
4 A.D.3d 476 (Appellate Division of the Supreme Court of New York, 2004)
Executive Towers at Lido, LLC v. Metro Construction Services, Inc.
303 A.D.2d 545 (Appellate Division of the Supreme Court of New York, 2003)