AAG Glass, LLC v. Laminados de Aller, S.A., VetroTool S.A., Roberto Puga Garcia, and Manuel Puga Diaz

CourtDistrict Court, D. Delaware
DecidedJuly 8, 2026
Docket1:21-cv-00638
StatusUnknown

This text of AAG Glass, LLC v. Laminados de Aller, S.A., VetroTool S.A., Roberto Puga Garcia, and Manuel Puga Diaz (AAG Glass, LLC v. Laminados de Aller, S.A., VetroTool S.A., Roberto Puga Garcia, and Manuel Puga Diaz) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AAG Glass, LLC v. Laminados de Aller, S.A., VetroTool S.A., Roberto Puga Garcia, and Manuel Puga Diaz, (D. Del. 2026).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF DELAWARE AAG GLASS, LLC, ) ) Plaintiff, ) ) V. ) C.A. No. 1:21-cv-00638-SRF ) LAMINADOS DE ALLER, S.A., ) VETROTOOL 8.A., ROBERTO PUGA ) GARCIA, and MANUEL PUGA DIAZ, ) ) Defendants. ) Scott D. Cousins, Lewis BRISBOIS BISGAARD & SMITH LLP, Wilmington DE; Aaron M Bernay, Frost BROWN TopD LLP, Cincinnati OH. Attorneys for Plaintiff

MEMORANDUM OPINION

July 8, 2026 Wilmington, Delaware

Hox rte JUDGE!: Pending before the court is the Motion of the Plaintiff for a Judgment by Default pursuant to Federal Rule of Civil Procedure 55(b)(2), against Defendants Laminados De Aller, S.A.,* VetroTool S.A., Roberto Puga Diaz and Manuel Puga Garcia, collectively “Defendants.” (D.I. 141) For the reasons which follow, Plaintiff’s motion is GRANTED. ?

I. JURISDICTION Federal jurisdiction in this case is based upon diversity of citizenship. 28 U.S.C § 1332(a)(2). Plaintiff is a Delaware limited liability company with its principal place of business in Batavia, Ohio. (D.I. 1 at 95) Defendants, Laminados de Aller, S.A. and VertroTool S.A. are foreign public limited liability companies each with their principal place of business in Asturias, Spain. (/d at ff 8-9.) Defendants, Roberto Puga Garcia and Manuel Puga Diaz are individuals residing in Oviedo, Spain. (/d at {§ 10-11.) The damages claimed exceed the $75,000 jurisdictional requirement. 28 U.S.C § 1332(b); Ud. at { 23.)

' On May 10, 2022, the parties consented to the jurisdiction of the Magistrate Judge to conduct all proceedings and order the entry of a final judgment in accordance with 28 U.S.C. § 646(c) and Fed. R. Civ. P. 73. (D.I. 38) 2 Defendant is a Spanish sociedad anonima (public limited liability company) (D.I. 141 at 7 8) 3 The associated affidavits and exhibits are found at D.I. 142, D.I. 143, D.I. 144, D.I. 145, DL. 154, D.I. 155, D.I. 156.

Il. BACKGROUND

A. Factual Background Plaintiff AAG Glass, LLC, (“Plaintiff”) filed this breach of contract action on April 30, 2021, against Defendants Laminados de Aller, S.A. (“Laminados”), VetroTool, S.A. (“VetroTool”), Robert Puga Garcia (“Garcia”) and Manuel Puga Diaz (“Diaz”) (collectively “Defendants”). (D.I. 1) Plaintiff is a Delaware limited liability company that makes automotive windshield glass at a factory in Ohio. (D.I. 1 at § 1) Laminados is a Spanish manufacturer of industrial equipment that produces furnaces for making automotive glass. (/d. at 2) VetroTool is a corporate affiliate of Laminados who, allegedly, supplied part of the equipment to Laminados. (/d. at { 6) Garcia and Diaz are owners of Laminados and VetroTool, and Garcia was the primary contact between AAG and Laminados during the parties’ relationship. (/d.)

On or about August 22, 2018, Plaintiff and Laminados entered into an agreement (the “Agreement”) whereby Laminados would sell, ship and install a complete production line for manufacturing automotive windshields. (/d. at JJ 13, 16-17, Ex. 1) The production line was to be ready for shipment by April 5, 2019, and expected to fulfill orders by July 19, 2019. Ud.) The Agreement was guaranteed by Vetrotool, Garcia and Diaz (the “Guaranty”). (/d. at { 6; Ex. 2) All three guarantor parties signed the Guaranty on the same date as the Agreement. (/d.)

Defendants failed to meet every material deadline in their Agreement. (7d. at 1 18) At the outset, Defendants were to provide a project timeline and heater design layout within 30 days of entering the Agreement, both of which arrived incomplete and late. 7d.) Furthermore, Defendants failed to ship their production in April 2019, and when it arrived in July of that year, the fabrication of each piece of equipment was not complete. (/d. at § 19) Given the significant delays in production and concerns about Defendants’ solvency, Plaintiff amended the Agreement

twice and advanced funds to Defendants so the Agreement could be completed. (/d. at { 20- 21)* Ultimately, Defendants neither delivered a complete production line nor installed it at Plaintiff's factory in Ohio. (/d. at § 22) Thus, Plaintiff made significant expenditures to manufacture, produce, ship, program, and install the production line Defendants had promised.” (/d.) As such, the production line Plaintiff was promised was not able to produce merchantable products until September 15, 2020, causing Plaintiff to lose out on several contract awards. (Id. at J] 18, 23) Plaintiff requests total damages of $3,909,238.61 plus attorneys’ fees and costs in the amount of $571,311.34. (DI. 154 at 4, D.I. 156 at 9) B. Procedural Background The parties’ Agreement contained alternative dispute resolution procedures in which the parties were to submit claims to the American Arbitration Association (“AAA”) of Wilmington, Delaware, which Plaintiff initiated. (D.I. 1-1 at § 21; D.I. 1 at ¥15) On November 6, 2020, before filing suit, Plaintiff sent Defendants a demand letter but Defendants did not respond to it. (DI. 1915 at DI. 141 at 6 (quoting Lauch Aff. at § 18)) On December 16, 2020, Plaintiff filed a request for mediation with the AAA. (/d.) Although Laminados initially agreed to mediate the dispute and the AAA appointed a mediator, Laminados subsequently refused to participate in the mediation process. Consequently, the dispute remained unresolved. (Id.) Therefore, Plaintiff initiated the present action on April 30, 2021. (/d.)

4 The first amendment to the Agreement was in August 2019, where Plaintiff modified its payment schedule which effectively advanced funds to Defendants. (D.I. 1 at { 20). Two months later, Plaintiff amended the Agreement again and advanced € 100,000 to Defendants to complete fabrication of the production line which was still a work in progress. (D.L. at 5 Plaintiff incurred expenses to take the components Defendants delivered and convert them into a functioning production line, including: $300,000 to air freight unfinished parts from Spain to Ohio, $ 600,000 to program its furnace and pre-processing lines, $ 700,000 to install the furnace’s electrical cabinets, and over $60,000 in safety fencing. (D.I. 1 at § 21)

The docket reflects that the Defendants were represented by counsel and participated in the litigation through December 30, 2022, when their original counsel’s motion to withdraw was granted. (D.I. 53) Defendants retained new counsel and participated in the litigation, including the pretrial conference. (D.I. 74) A jury trial was set to begin on July 22, 2024, (D.I. 72; D1. 86), but on July 19, 2024, the court was notified of a potential settlement and the trial date was vacated. (D.I. 103) On September 30, 2024, Plaintiff and three of the four Defendants agreed to a final settlement agreement, stipulation of dismissal, and form of judgment. (D.I. 111) Plaintiff received executed copies on October 25, 2024, from all Defendants except Diaz. (D.I. 111) In response, Plaintiff moved to enforce the settlement agreement against Diaz. (D.I. 119) On January 29, 2025, Defendants’ second set of counsel was granted leave to withdraw. (D.I. 127) On that same date, the court denied Plaintiff’s motion for enforcement of the settlement agreement against Diaz. The court ordered the parties to submit a joint status report on or before March 17, 2025, that included whether any Defendants other than Diaz may be terminated from the case and what remained to be litigated in the case regarding Diaz. (D.I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hicks v. Guinness
269 U.S. 71 (Supreme Court, 1925)
Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Comdyne I, Inc. v. Corbin
908 F.2d 1142 (Third Circuit, 1990)
Economy Folding Box Corp. v. Anchor Frozen Foods Corp.
515 F.3d 718 (Seventh Circuit, 2008)
Honaker v. Farmers Mutual Insurance Company
313 A.2d 900 (Superior Court of Delaware, 1973)
Joe Hand Promotions, Inc. v. Yakubets
3 F. Supp. 3d 261 (E.D. Pennsylvania, 2014)
Pedrick v. Roten
70 F. Supp. 3d 638 (D. Delaware, 2014)
Hritz v. Woma Corp.
732 F.2d 1178 (Third Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
AAG Glass, LLC v. Laminados de Aller, S.A., VetroTool S.A., Roberto Puga Garcia, and Manuel Puga Diaz, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aag-glass-llc-v-laminados-de-aller-sa-vetrotool-sa-roberto-puga-ded-2026.