Aaby v. States Marine Corporation

181 F.2d 383, 1950 U.S. App. LEXIS 3772
CourtCourt of Appeals for the Second Circuit
DecidedApril 12, 1950
Docket21541_1
StatusPublished
Cited by12 cases

This text of 181 F.2d 383 (Aaby v. States Marine Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aaby v. States Marine Corporation, 181 F.2d 383, 1950 U.S. App. LEXIS 3772 (2d Cir. 1950).

Opinion

CHASE, Circuit Judge.

This appeal is from an interlocutory decree for the owners of the Norwegian Diesel motorship “Tentó” which was entered after'/the .trial of a libel by them for damages resulting from the appellant’s repudiation of a twelve months’ time charter of the. ship. Delivery of the vessel by the owners .to the charterer was to take place under the charter at port of survey, at the owner’s option, by not later than 4 P.M., December 31, 1937. . From December 15 to about 3 P.M. on December 31, 1937, the vessel was laid up for repairs at Sandefjord, ‘Norway, but delivery was tendered there at about 3:30 P.M. on the required day. The’charterer’s surveyor inspected the vessel, found no defects and gave his certificate to that effect, and the master and the charterer’s agent signed a certificate of delivery at 3:30 P.M. The latter gave the master written orders to proceed to St. John, N.B., and the vessel sailed. At about 4 P.M., however, a steel shaft in the lubricating oil pump of one óf the vessel’s three auxiliary motors — she had two main motors — broke, owing either to a latent defect in the metal or to metal fatigue. The' vessel stopped at about 4:20 apparently not because the breaking of the shaft made her unnavigable but to determine the extent of. the damage. She then drifted; until about 7 P.M. when she anchored, and remained at anchor until about 6:30 P.M. on January 1, 1938. At that time, her anchorage being dangerous, she was assisted by. a tug to return to Siggrunn, Norway. Her engines had failed to start at 6:10 P.M., because insufficient starting air had been pumped up, but by about 9 P.M. they started, and were used in maneuvering to anchorage at Siggrunn. Repairs were commenced on the morning of January 2, were completed that night, and the vessel sailed at 2:10 A.M. on January 3, the total delay thus amounting to about two and one-half days.

On January 3, 1938, the charterer informed the owner’s agent at Oslo that it refused to accept delivery and that they should consider the charter party cancelled. When efforts to agree as to continuing the charter failed, the vessel was returned to the owners on January 8. Suit was begun by the owners in January, 1940, but, as a result of the war, the case did not come to trial until April 1947. The court below found that the vessel “was unsea-worthy as to the lubricating oil pump” at the time of delivery, but held that repudiation of the charter was not justified, on the alternative grounds that (1) “there is no suggestion that the break down in any way interfered with or frustrated the purposes of the charter, * * * ” 80 F.Supp. 328, at page 333, or that (2) delivery and acceptance of the vessel having taken place, the “warranty” of seaworthiness was supplanted by the breakdown clause in the charter, providing “That in the event of loss of time from * * * breakdown or damages to * * * machinery * * * the payment of hire shall cease for the time thereby lost, * * * ” Concededly, however, the charterer was entitled to relief from the payment of hire during the period of delay caused by the breakdown, and the decree permitted the determination and allowance of that in computing the damages.

We agree with the result reached by the district court. It is true that, from the fact that the shaft broke almost immediately after the delivery of the vessel it could properly be inferred that it was defective at the time of delivery. The Southwark, 191 U.S. 1, 13-14, 24 S.Ct. 1, 48 L.Ed. 65; Federal Forwarding Co. v. Lanasa, 4 Cir., 32 F.2d 154, 156-157; The Nomad, D.C.N.J., 3 F.Supp. 535; Scrutton on Charterparties and Bills of Lading (12th ed.) pp. 101-02. It is also true that the exercise of diligence to discover the defect or lack of knowledge of.it is im *385 material, the terms of the charter party or of a controlling statute not being to the contrary. Work v. Leathers, 97 U.S. 379, 24 L.Ed. 1012; The Caledonia, 157 U.S. 124, 15 S.Ct. 537, 39 L.Ed. 644; The Carib Prince, 170 U.S. 655, 18 S.Ct. 753, 42 L.Ed. 1181; Federal Forwarding Co. v. Lanasa, supra.

But this does not mean that there was necessarily a breach of the undertaking expressed here as “Vessel on her delivery to be tight, staunch, strong and in every way fitted for the service * * * ” Such an undertaking seems to be equivalent to what is generally called the “warranty” of seaworthiness that is implied in all contracts concerning vessels in the absence of an express and unambiguous stipulation to the contrary. See Luckenbach v. W. J. McCahan Sugar Ref. Co., 248 U.S. 139, 150, 39 S.Ct. 53, 63 L.Ed. 170, 1 A.L.R. 1522; The Josephine, 3 Cir., 49 F.2d 207, 209; Carver on the Carriage of Goods by Sea (7th ed.) § 144.

Not every defect needing repair or causing damage amounts to a breach of undertaking. Middleton & Co., (Canada), Ltd., v. Ocean Dominion S. S. Corp., 2 Cir., 137 F.2d 619, 622, certiorari denied 320 U.S. 802, 64 S.Ct. 432, 88 L.Ed. 484; The Sandfield, 2 Cir., 92 F. 663; Hedley v. Pinkey & Sons S. S. Co., (1894) A.C. 222. The evidence tends to show that the breaking of the shaft was of little importance with respect to the operation of the vessel, though it is apparent that the defect was not remediable at sea, or in a few minutes with the materials available on board. Even so, were we forced to take the view that any breach, no matter how petty, of the undertaking of seaworthiness operates “to entitle the injured party not only to sue for damages but also to refuse to continue performance,” see 4 Williston on Contracts § 1080, this case would demonstrate the harsh consequences of such a view. Perhaps the court below felt similarly, for it did not unqualifiedly hold that the “Tentó” was unseaworthy; rather, it held, that she was “unseaworthy as to the lubricating oil pump.”

Authoritative support for the view that any breach of the undertaking of seaworthiness permits repudiation has, however, not been found. The authorities reveal some confusion as to the meaning of the term “warranty,” as well as to the legal consequences of a breach of “warranty”; as to whether a ship-owner’s undertaking of seaworthiness is a “warranty,” and indeed even as to the reason for implying such an undertaking in contracts.

The general American view is that a “warranty” is a guaranty that a certain fact is true. See 4 Williston on Contracts § 1075. Thus, when an owner “warrants” that a certain situation exists, he promises that it does exist, and the obligation of the charterer is conditioned upon the existence of that situation. Davison v. Von Lingen, 113 U.S. 40, 5 S.Ct. 346, 28 L.Ed. 885.

By this definition, then, any breach of warranty permits rescission, 1 2as well as an action for damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
181 F.2d 383, 1950 U.S. App. LEXIS 3772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aaby-v-states-marine-corporation-ca2-1950.