A-Z Electrical Engineering Inc v. James Jenkins

Michigan Court of Appeals·Decided July 23, 2026·No. 374949·Unpublished

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

A-Z ELECTRICAL ENGINEERING, INC, UNPUBLISHED July 23, 2026 Plaintiff-Appellee, 9:00 AM

v No. 374949 Wayne Circuit Court JAMES JENKINS and JENKINS LC No. 23-001535-CB CONSTRUCTION, INC,

Defendants-Appellants.

Before: MARIANI, P.J., and O’BRIEN and WALLACE, JJ.

PER CURIAM.

This case arises out of a payment dispute between defendants, James Jenkins and Jenkins Construction, Inc (Jenkins Construction), and plaintiff, A-Z Electrical Engineering, Inc, the company defendants hired to perform electrical work. After former counsel for defendants was suspended from the practice of law, the trial court repeatedly, over the course of almost a year, communicated to defendants that they needed to retain new counsel. Defendants essentially ignored the trial court and sent a corporate representative to represent them at trial, despite the fact that he was not an attorney. As a result, the trial court found defendants in default and entered a default judgment in favor of plaintiff for the sum certain that had been determined to be at issue in the court’s pretrial order. On appeal, defendants argue that the trial court erred by: entering the default, failing to conduct a separate hearing on damages, and denying their motion to set aside the default judgment. We affirm.

I. FACTUAL AND PROCEDURAL HISTORY

In 2023, plaintiff filed a four-count complaint against defendants alleging breach of contract, account stated, unjust enrichment, and fraudulent misrepresentation, all arising out of agreements for two separate electrical production and service projects in 2019. As alleged in the complaint, both projects consisted of work performed in Detroit, with project #1 pertaining to the Guardian Building and project #2 pertaining to the Eighth Precinct Building, with past due outstanding balances owed by defendants on both projects, including $5,664.52 for project #1 and $126,731.00 for project #2. Plaintiff further alleged that it ceased working on the projects in 2019

-1- at the instruction of defendants, at which time the above-referenced balances were owed. Regarding the account stated, plaintiff alleged that defendants received a credit account from plaintiff and that defendants failed to make payments as they became due. Plaintiff attached an affidavit verifying the account, which had a total unpaid balance of $132,395.52 (plaintiff also alleged to be owed post-judgment interest and contract interest capped at the rate of 13% from the date of the filing of the complaint, compounded annually). Regarding the breach of contract count, plaintiff alleged that it performed all of its obligations under a contract between the parties, that defendants breached the contract by failing to issue payment, and that it has suffered the same damages alleged in the first count. The third count of the complaint (unjust enrichment) alleged that it would be inequitable for defendants to be enriched by the work performed by plaintiff without issuing payment, while the fourth count (fraudulent misrepresentation) alleged that defendants intentionally misled plaintiff into believing that defendants would pay plaintiff for the balances that were due at the time defendants halted the two projects.

In April 2023, defendants answered the complaint, alleging that the actual amount owed by defendants, after accounting for setoffs and their counterclaim, was an amount less than the jurisdictional requirement of the circuit court; however, defendants’ pleading contained no counterclaim. While defendants admitted the existence of a contract between plaintiff and Jenkins Construction, they denied that James Jenkins had any contractual relationship with plaintiff and denied that he personally owed plaintiff any money. Defendants further denied that they ever requested or authorized any credit account from plaintiff and that it was the contract between plaintiff and Jenkins Construction that governed the relationship between those two parties. Likewise, defendants alleged that plaintiff had no claim for unjust enrichment or fraudulent misrepresentation, that James Jenkins had no relationship with plaintiff, and that the relationship between Jenkins Construction and plaintiff was governed by the contract.

On August 21, 2023, plaintiff served discovery requests on defendants that included various requests for admission pursuant to MCR 2.312, which essentially requested defendants to admit that the amount owed under the contract was $997,875.00, but that defendants only paid plaintiff $871.144.88.1 On October 17, 2023, plaintiff served defendants with notice that they had allegedly failed to respond to these requests for admission under MCR 2.312.

On November 13, 2023, plaintiff filed a motion requesting that the trial court either enter an order compelling defendants to answer overdue discovery requests or award reasonable attorney fees, costs, and sanctions pursuant to MCR 2.313(A)(5).

On October 8, 2024, the trial court conducted a status conference at which it instructed the parties that the matter would proceed to a bench trial on January 6, 2025, at 9:00 a.m. A written order to that effect was issued on October 11, 2024.

1 We note that the caption of the document failed to identify that it contained requests for admission, in violation of MCR 2.312(A), which provides: “The request must clearly identify in the caption and before each request that it is a Request for Admission.”

-2- On January 2, 2025, a final pretrial order was entered, attached to which were plaintiff’s proposed trial exhibits, including invoices sent to defendant, electrical permits pulled by plaintiff, and photographs from the jobsites.

On the morning of trial, James Jenkins did not appear, and no attorney appeared on behalf of either defendant.2 Counsel for plaintiff moved for entry of a default judgment in the amount of $69,030.02, which was the total amount of the outstanding invoices owed by defendants to plaintiff. The court allowed a non-attorney corporate representative of Jenkins Construction to speak on the record, who stated that defendant Jenkins Construction overpaid plaintiff, which was “why we were in court today.” Counsel for plaintiff then moved to strike the statement on the basis that the agent was not an attorney and could not speak for either defendant, but the court denied that motion.

The court then recounted the history of the case, which it described as “tortured,” based in part on former counsel for defendants having had challenges complying with discovery and facing issues pertaining to his licensure. The court indicated that it had multiple conferences with James Jenkins in which the court clearly indicated that he needed to retain an attorney to substitute for his former counsel, and that James Jenkins indicated he would either retain successor counsel or settle the case. Based on the record, the court found that no action had actually been taken by defendants. The court noted defendants’ failure to adequately cooperate with discovery, but ultimately stated it would grant a default judgment in favor of plaintiff and against defendants under 2.603(A)(1), based on defendants’ failure to appear at trial, despite proper service of notice of trial. The court denied plaintiff’s requests for attorney fees, but noted that such matters may be the subject of post-judgment proceedings.

On January 9, 2025, a default judgment was entered against defendants and in favor of plaintiff in the amount of $69,030.02.

Free access — add to your briefcase to read the full text and ask questions with AI

A-Z Electrical Engineering Inc v. James Jenkins, (Mich. Ct. App. 2026).

A-Z Electrical Engineering Inc v. James Jenkins (A-Z Electrical Engineering Inc v. James Jenkins) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Saffian v. Simmons
727 N.W.2d 132 (Michigan Supreme Court, 2007)
Alken-Ziegler, Inc. v. Waterbury Headers Corp.
600 N.W.2d 638 (Michigan Supreme Court, 1999)
Shawl v. SPENCE BROS., INC.
760 N.W.2d 674 (Michigan Court of Appeals, 2008)
Peters Production, Inc. v. Desnick Broadcasting Co.
429 N.W.2d 654 (Michigan Court of Appeals, 1988)
Detroit Bar Ass'n v. Union Guardian Trust Co.
281 N.W. 432 (Michigan Supreme Court, 1937)