A to Z Plumbing & Heating, Inc. v. City of Ashland

CourtCourt of Appeals of Wisconsin
DecidedMay 28, 2025
Docket2023AP000386
StatusUnpublished

This text of A to Z Plumbing & Heating, Inc. v. City of Ashland (A to Z Plumbing & Heating, Inc. v. City of Ashland) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A to Z Plumbing & Heating, Inc. v. City of Ashland, (Wis. Ct. App. 2025).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. May 28, 2025 A party may file with the Supreme Court a Samuel A. Christensen petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2023AP386 Cir. Ct. No. 2021SC250

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT III

A TO Z PLUMBING & HEATING, INC.,

PLAINTIFF-APPELLANT,

V.

CITY OF ASHLAND,

DEFENDANT-RESPONDENT.

APPEAL from a judgment of the circuit court for Ashland County: ANTHONY J. STELLA, JR., Judge. Affirmed and cause remanded with directions.

¶1 GILL, J.1 A to Z Plumbing & Heating, Inc. (“A to Z”), appeals the circuit court’s grant of summary judgment to the City of Ashland in this small claims action. A to Z, by its president, Zygmund Jablonski Jr., argues that the court erred

1 This appeal is decided by one judge pursuant to WIS. STAT. § 752.31(2) (2023-24). All references to the Wisconsin Statutes are to the 2023-24 version. No. 2023AP386

by concluding that after the corporation completed the contract for installation of an HVAC system, the City did not breach its contract with A to Z when the City hired another contractor to repair that system.2 We affirm.

¶2 Additionally, the City has filed a motion for sanctions under WIS. STAT. RULE 809.25(3), asserting that this appeal is frivolous in its entirety and seeking to recover the costs, court fees, and attorney fees it incurred on appeal. We agree with the City that A to Z’s appeal is frivolous in its entirety. Accordingly, we grant the City’s motion for sanctions and remand the matter to the circuit court to determine the amount of costs, fees, and reasonable attorney fees that the City is entitled to recover.

BACKGROUND

¶3 On August 13, 2020, the City entered into a contract with A to Z whereby A to Z agreed to replace the HVAC system in the Bretting Community Center in exchange for $199,664.3 The contract stated that A to Z would begin on August 13, 2020, and that the work would be substantially completed by December 31, 2020. The work consisted of removing “three existing gas fired air handling units”; installing “three new hot water coil air handling units” and

2 We note that “the Wisconsin Supreme Court has unequivocally stated that under Wisconsin rules and statutes, only lawyers can appear on behalf of or perform legal services for corporations in legal actions in Wisconsin courts.” Carmain v. Affiliated Cap. Corp., 2002 WI App 271, ¶19, 258 Wis. 2d 378, 654 N.W.2d 265. However, “[t]he only exception” to this rule is for “actions filed in small claims court.” Jadair Inc. v. United States Fire Ins. Co., 209 Wis. 2d 187, 202, 562 N.W.2d 401 (1997). Because A to Z’s complaint was filed in small claims court, Jablonski is permitted to “appear on behalf of or perform legal services” for A to Z in this matter. 3 Throughout the performance of this contract, multiple change orders were needed and mutually agreed upon. These change orders resulted in an additional cost of $2,216 to the City, bringing the total contract sum to $201,880.

2 No. 2023AP386

“associated ductwork, piping, control work and electrical”; and installing cooling coils, two new condensing units, and a new hot water boiler system.

¶4 A to Z did not substantially complete the above work by the December 31, 2020 deadline. After A to Z requested and was granted multiple extensions to complete the project, installation of the HVAC system was completed on June 23, 2021.

¶5 On June 29, 2021, the HVAC system installed by A to Z stopped working. Shortly thereafter, the City hired another contractor to repair the HVAC system. On July 3, 2021, A to Z sent a letter to the City, indicating that it would be “filing claims” against the City for “additional costs and delays” that were caused by the COVID-19 pandemic under the theory of the “[d]octrine of [i]mpracticability.” The letter stated that this decision was based on “[r]ecent events,” which the City interprets on appeal as meaning its hiring of another contractor to repair the HVAC system.

¶6 On August 31, 2021, the City approved its final payment to A to Z which was subsequently issued on September 3, 2021, to satisfy its total contractual obligation of $201,880. The City did not pay any of the “claims” filed by A to Z for the additional costs and delays.4 A to Z then filed a small claims complaint against the City, in which A to Z alleged that the City had breached its contract with A to Z by hiring another contractor on July 3, 2021. A to Z sought to obtain $10,000 to compensate it for “financial [and] reputational loss.”

4 A to Z does not argue on appeal that the City wrongfully declined to pay any of these additional claims.

3 No. 2023AP386

¶7 The City filed a motion for summary judgment, in which it alleged that there were no genuine issues as to any material facts and that it was entitled to judgment as a matter of law because it paid A to Z the full contract price and therefore did not breach the contract. Specifically, the City argued that its contract with A to Z created only one duty for the City—to pay the contract price—and that the City fulfilled this duty. The City also noted that its contract with A to Z did “not prohibit the City from hiring a contractor to work on the non-functioning air conditioning system, nor d[id] it require the City to notify A to Z in advance.”

¶8 A to Z opposed the City’s summary judgment motion and filed its own motion for summary judgment. A to Z argued that the City violated § 12.2.2.1 of the contract by hiring another contractor to repair the HVAC system, and that this violation caused A to Z to suffer reputational harm, including the loss of two other projects with the City.

¶9 The circuit court granted the City’s motion for summary judgment. It first found that the City “paid [A to Z] the full amount that [it] would have received under the contract had it been satisfactorily completed in full, even though the contract was not completed to the satisfaction of the [City].” The court then found that the section of the contract that A to Z claimed was breached merely gave the City a warranty for the work performed by A to Z. However, that section did “not give the warrantor a right to perform that work; rather, it impose[d] upon the warrantor the obligation to perform work at the option of the purchaser.” The court noted that “[t]he warrantor has no absolute right to perform the repairs on products that it has given a warranty for” and that to suggest otherwise is “absurd.”

¶10 The circuit court also considered whether A to Z was entitled to interest or a fee due to the City’s late final payment. The court noted that, under the

4 No. 2023AP386

terms of the contract, final payment was due 30 days “after the contractor fully performed the contract and a final certificate was issued by the architect OR subject to the approval of the City Council at a regularly established meeting date.” The court then noted that the contract was not fully performed within the timeframe established in the contract and that there was no evidence of when a final certificate was issued by the architect. The court found that the City waited to issue the final payment because it was waiting for a final invoice from A to Z and that the City issued its final payment six weeks after it received the final invoice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Pettit
492 N.W.2d 633 (Court of Appeals of Wisconsin, 1992)
Howell v. Denomie
2005 WI 81 (Wisconsin Supreme Court, 2005)
Baumeister v. Automated Products, Inc.
2004 WI 148 (Wisconsin Supreme Court, 2004)
Turner v. Taylor
2003 WI App 256 (Court of Appeals of Wisconsin, 2003)
Jadair Inc. v. United States Fire Insurance
562 N.W.2d 401 (Wisconsin Supreme Court, 1997)
Carmain v. Affiliated Capital Corp.
2002 WI App 271 (Court of Appeals of Wisconsin, 2002)
Larson v. Burmaster
2006 WI App 142 (Court of Appeals of Wisconsin, 2006)
Holz v. Busy Bees Contracting, Inc.
589 N.W.2d 633 (Court of Appeals of Wisconsin, 1998)
Louis Pagoudis v. Marcus Keidl
2023 WI 27 (Wisconsin Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
A to Z Plumbing & Heating, Inc. v. City of Ashland, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-to-z-plumbing-heating-inc-v-city-of-ashland-wisctapp-2025.