A. Raymond Plumbing v. Eggers

CourtNebraska Court of Appeals
DecidedMarch 31, 2015
DocketA-14-106
StatusUnpublished

This text of A. Raymond Plumbing v. Eggers (A. Raymond Plumbing v. Eggers) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. Raymond Plumbing v. Eggers, (Neb. Ct. App. 2015).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

A. RAYMOND PLUMBING V. EGGERS

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

A. RAYMOND PLUMBING, INC., APPELLEE, V.

JAMES EGGERS, APPELLANT.

Filed March 31, 2015. No. A-14-106.

Appeal from the District Court for Douglas County: J. MICHAEL COFFEY, Judge, on appeal thereto from the County Court for Douglas County: MARCELA A. KEIM, Judge. Judgment of District Court affirmed. Theodore R. Boecker, Jr., of Boecker Law, P.C., L.L.O., for appellant. Martin A. Cannon, of Cannon Law Office, for appellee.

INBODY, PIRTLE, and BISHOP, Judges. PIRTLE, Judge. INTRODUCTION James Eggers received a judgment in the county court for Douglas County for damages in a breach of contract action. The district court for Douglas County affirmed the county court’s award of sanctions and costs, but remanded the matter to the county court for a retrial on the issue of damages. Eggers appeals the decision of the district court, and for the reasons that follow, we affirm. BACKGROUND James Eggers (Eggers) hired A. Raymond Plumbing (Raymond) to complete certain plumbing work in connection with the construction of a home. Raymond provided a bid to

-1- complete the custom work for a total of $19,124. After completing a portion of the plumbing work, Raymond invoiced Eggers for approximately ninety percent of the total bill and demanded payment before the company would proceed with any further work. Eggers rejected the demand because he found Raymond’s work was inadequate and Raymond had not completed ninety percent of the work. Eggers made a demand that Raymond complete the work set forth under the original bid, but Raymond did not return to the work site. Eggers sought performance from a substitute contractor, Backlund Plumbing. Backlund found some of the items were unfinished or were defectively installed by Raymond. Backlund corrected the defective plumbing and completed the work Raymond was contracted to do. Backlund billed Eggers for a total of $14,537. On August 29, 2011, Raymond filed a complaint in the county court for Douglas County against Eggers for breach of contract. Raymond’s complaint asserted that Eggers failed to pay for plumbing work at Eggers’ home in Omaha. On September 28, 2011, Eggers filed an answer and counterclaim asserting that he hired Raymond to perform construction work, but Raymond failed to complete the work in a good and workmanlike manner. Eggers asserted that he had to contract with a different company to correct the deficiencies in Raymond’s work, and he suffered damage due to the increased costs of completing the work. Raymond did not file an answer in response to the counterclaim. The county court set a trial date for May 23, 2012. Eggers timely complied with the county court’s orders regarding exhibits, witness lists, and other pretrial submissions. Raymond did not comply with the order. On May 23, 2012, both parties appeared with counsel for trial before the county court. Prior to the commencement of trial, Eggers filed a motion in limine based upon Raymond’s failure to comply with the pretrial order. The court noted Raymond had not timely responded to any of Eggers’ discovery requests, Raymond had not filed an answer to Eggers’ counterclaim, nor had Raymond timely complied with any of the court’s pre-trial orders. Raymond acknowledged the failure to respond, and made a motion to continue prior to trial. Raymond’s counsel stated that his practice got very busy with another case and he was unable to complete the necessary work for Raymond prior to trial. The court stated the trial would be continued over Eggers’ objection. On May 31, 2012, the court submitted a written order finding Raymond was in violation of the pretrial order and that Eggers had complied with the order. The county court stated that granting Eggers’ motion in limine would prohibit Raymond from proceeding on its claim, and would also bar Raymond from introducing any evidence to rebut the counterclaim. The county court denied Eggers’ motion in limine, continued the case to the next civil panel, set a date for a new pretrial hearing, and granted Eggers leave to file a motion for sanctions. The order set the case for trial on August 9, 2012. By the time of trial on August 9, Raymond still had not filed a reply to Eggers’ counterclaim, despite having received notice from the court that the reply was in default. The county court issued a pretrial order on August 17, 2012 setting the trial for September 12. On September 12, Raymond moved to file an answer to the counterclaim and the court denied the motion. The court found Raymond was in default and had not shown good cause to file a reply out of time, especially in light of the court’s prior admonition that there was no reply or

-2- answer on file. Raymond moved to voluntarily dismiss its complaint against Eggers, without prejudice, and the court granted Raymond’s motion over Eggers’ objection. At trial Eggers adduced evidence on his counterclaim. He testified that he made a cash partial payment toward the bid in the amount of $3,300. The parties agreed that Eggers would receive a 10 percent discount if he paid in cash, so he was to receive $3,360 as credit toward the final bill. The parties also bartered for guttering services which entitled Eggers to an additional $1,088 in credit. Eggers testified that he paid Backlund to complete the project. The county court did not allow Raymond’s counsel to cross-examine Eggers on the issue of damages or put on evidence regarding the issue of damages. On November 7, 2012, the county court issued an order finding it was undisputed that Raymond and Eggers entered into an agreement wherein Raymond was to perform plumbing services at a residential property owned by Eggers. The county court found Raymond defaulted on its contractual obligations and had not performed its responsibilities under the contract in a good and workmanlike manner. The court reviewed the testimony and exhibits offered regarding damages alleged in the counterclaim. The county court awarded damages in the amount of $14,537. The court further ordered Raymond to pay costs in the amount of $311.06, but declined Eggers’ request for attorney fees. The court ordered sanctions in the amount of $1,000 against Raymond’s counsel. Raymond filed a motion to alter or amend, or for new trial, and the county court denied the motion. Raymond appealed the county court’s order to the district court. The bill of exceptions was filed on February 15, 2013, and Raymond filed a statement of errors on February 26. Eggers filed a motion for summary affirmance because of Raymond’s failure to file a statement of errors within 10 days. The district court overruled the motion and issued an order on August 7, 2013, vacating the judgment of the county court. Eggers moved to alter the district court’s order and to request reconsideration and rehearing. On January 7, 2014 the district court issued an order amending the August 7, 2013 ruling. The district court affirmed the $1,000 sanction against Raymond’s counsel and the award of costs, but concluded the county court erred in its assessment of damages. The district court remanded the case for a retrial on the issue of damages. Eggers timely appealed the district court’s decision. ASSIGNMENTS OF ERROR Eggers asserts it was error for the district court to reverse the county court’s determination of damages, and for the district court to order a retrial on the issue of damages. STANDARD OF REVIEW A suit for damages arising from breach of contract presents an action at law. Stauffer v. Benson, 288 Neb. 683, 850 N.W.2d 759 (2014).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Centurion Stone of Neb. v. Whelan
835 N.W.2d 62 (Nebraska Supreme Court, 2013)
Stauffer v. Benson
288 Neb. 683 (Nebraska Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
A. Raymond Plumbing v. Eggers, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-raymond-plumbing-v-eggers-nebctapp-2015.