A. & L. McKnight v. PUC

CourtCommonwealth Court of Pennsylvania
DecidedMarch 20, 2024
Docket1253 C.D. 2019
StatusPublished

This text of A. & L. McKnight v. PUC (A. & L. McKnight v. PUC) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. & L. McKnight v. PUC, (Pa. Ct. App. 2024).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Alexia and Lawrence McKnight, : Petitioners : : v. : : Public Utility Commission, : No. 1253 C.D. 2019 Respondent : Submitted: January 5, 2024

BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge HONORABLE CHRISTINE FIZZANO CANNON, Judge HONORABLE LORI A. DUMAS, Judge

OPINION BY JUDGE FIZZANO CANNON FILED: March 20, 2024

Alexia and Lawrence McKnight (McKnights), pro se, filed a petition for review (Petition) of a final order (Final Order) of the Pennsylvania Public Utility Commission (PUC) dated August 8, 2019, requiring the McKnights to accept installation of an advance metering infrastructure electric meter, or smart meter, at their residence. Disposition of the Petition was stayed pending our Supreme Court’s decision in a group of consolidated appeals addressing substantially similar issues. The Supreme Court filed that decision in 2022. See Povacz v. Pa. Pub. Util. Comm’n, 280 A.3d 975 (Pa. 2022). Thereafter, the parties in this case were directed to file additional briefs but requested and were granted leave to refrain from doing so. This case is therefore ready for this Court’s review on the original briefs. Upon review, we conclude that our Supreme Court’s decision in Povacz has disposed of most issues the McKnights have raised before us and that the remaining issues are waived and/or lack merit. Accordingly, we affirm the Final Order. I. Background The Act of October 15, 2008, P.L. 1592, No. 129 (Act 129) amended the Public Utility Code1 to require that electric distribution companies (EDCs) furnish smart meters to their customers. See Section 2807(f) of the Public Utility Code, 66 Pa.C.S. § 2807(f). Pursuant to Act 129, the PUC issued an order in 2009 directing EDCs to install smart meters according to a depreciation schedule not to exceed 15 years in duration. The McKnights filed a formal complaint with the PUC regarding the installation of a smart meter at their residence by their EDC, PECO Energy Company (PECO).2 Like a number of other PECO customers, the McKnights expressed concerns about adverse health effects of exposure to radiofrequency (RF) fields or electromagnetic fields (EMFs)3 from smart meters. PECO refused any disability accommodation to allow the McKnights to use an analog meter instead of a smart meter. Following evidentiary hearings in 2018, an administrative law judge (ALJ) issued an initial decision to which both PECO and the McKnights filed exceptions. In its opinion (Opinion) accompanying the Final Order, the PUC addressed each of the McKnights’ exceptions to the ALJ’s decision. First, the PUC concluded that the McKnights were required to prove by a preponderance of the evidence that PECO caused the health effects alleged in the complaint and thereby violated a provision of the Public Utility Code, a PUC regulation or order, or a PUC-approved tariff. The PUC also observed that an ALJ’s

1 66 Pa.C.S. §§ 101-3316. 2 PECO is an intervenor in this proceeding. 3 These two terms were used interchangeably before the PUC.

2 decision must be supported by substantial evidence. The PUC rejected the McKnights’ assertions of alternate burdens of proof and determined that the ALJ had applied the correct burdens in ruling on their complaint. The PUC opined that the mere existence of a body of inconclusive scientific evidence suggesting a connection between RFs from smart meters and alleged harm to human health cannot satisfy the requisite burden of demonstrating, by a preponderance of the evidence, a conclusive causal connection between RFs and existing or future harm to human health. The PUC acknowledged that Section 1501 of the Public Utility Code, 66 Pa.C.S. § 1501, which requires EDCs to provide safe and reasonable electric service,4 may be violated where a complainant can prove adverse health effects from RFs. However, the PUC declined to alter the established burden of proof in the absence of scientific consensus on the effects of exposure to RFs. In a related determination, the PUC rejected the McKnights’ argument that they had met their burden of proof by demonstrating both potential harm from the smart meter and a temporal connection between the installation of the smart meter and the appearance of their alleged physical symptoms. After summarizing both sides’ evidence, the PUC noted the ALJ’s finding that Alexia McKnight had

4 Section 1501 of the Public Utility Code provides:

Every public utility shall furnish and maintain adequate, efficient, safe, and reasonable service and facilities, and shall make all such repairs, changes, alterations, substitutions, extensions, and improvements in or to such service and facilities as shall be necessary or proper for the accommodation, convenience, and safety of its patrons, employees, and the public.

66 Pa.C.S. § 1501; see also Povacz v. Pa. Pub. Util. Comm’n, 280 A.3d 975, 999-1000 (Pa. 2022) (quoting Section 1501).

3 begun experiencing a variety of symptoms5 after installation of the smart meter but that the McKnights had failed to prove by a preponderance of the evidence that the smart meter caused those symptoms. The PUC slightly modified a few of the ALJ’s findings but agreed with the ALJ’s determination that the McKnights had failed to overcome PECO’s rebuttal evidence. Specifically, they had presented no surrebuttal evidence and had failed to demonstrate a conclusive causal connection between RF emissions from the smart meter and Alexia McKnight’s alleged physical harm. The PUC likewise rejected the McKnights’ various arguments that the ALJ’s decision was against the weight of the evidence. The PUC also agreed with the ALJ’s conclusion that Section 1501 of the Public Utility Code does not require a safety accommodation to allow an electric customer to elect against installation of a smart meter. The PUC concluded that PECO sufficiently accommodated its customers by offering to work with them to relocate smart meters if requested and to offer several different new types of meters. In this regard, the PUC also reiterated that the McKnights failed to prove that any meter was harming their health. Accordingly, the PUC denied the McKnights’ exceptions to the ALJ’s decision, with some minor modifications not at issue here. The filing of the Petition in this Court followed.

5 Those symptoms included headaches, difficulty concentrating, fatigue, insomnia, and feeling an urgent need to escape. McKnights’ Br. at 8.

4 II. Issues The McKnights raise several issues6 for review by this Court.7 First, they assert that the PUC misrepresented “the proximal cause” of their complaint by adding a reference to RFs rather than the smart meter as the alleged cause of their symptoms. McKnights’ Br. at 2. Second, they insist that the PUC “arbitrarily and capriciously” altered the applicable burden of proof by requiring a “conclusive” connection between the smart meter and their alleged harm. Id. Third, they cryptically posit that they do not “hold [a] burden to show ‘conclusive science’ for all intermediate mechanisms in a case of specific cause without alternative possible explanation[.]” Id. Fourth, they contend that the PUC failed to properly consider Section 1501’s requirement of safe and reasonable service as applied to Act 129’s smart meter mandate. Id. Fifth, they maintain that the PUC lacked “medical authority” to order them to disregard their physician’s advice to avoid exposure to RFs. Id. Sixth, they suggest that mandating installation of a smart meter “where there is uncertainty about the safety represent[s] a violation of inherent human rights[.]” Id. Seventh, they argue that as pro se litigants “who lack legal assistance and opportunity for financial recompense to pay for legal counsel[,]” they were denied due process. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trizechahn Gateway LLC v. Titus
976 A.2d 474 (Supreme Court of Pennsylvania, 2009)
Rich v. Acrivos
815 A.2d 1106 (Superior Court of Pennsylvania, 2003)
Dilliplaine v. Lehigh Valley Trust Co.
322 A.2d 114 (Supreme Court of Pennsylvania, 1974)
In Re Fc III
2 A.3d 1201 (Supreme Court of Pennsylvania, 2010)
Romeo v. Pennsylvania Public Utility Commission
154 A.3d 422 (Commonwealth Court of Pennsylvania, 2017)
SugarHouse HSP Gaming, L.P. v. Pennsylvania Gaming Control Board
162 A.3d 353 (Supreme Court of Pennsylvania, 2017)
V.S. v. Department of Public Welfare
131 A.3d 523 (Commonwealth Court of Pennsylvania, 2015)
Hiko Energy, LLC v. Pa. Pub. Util. Comm'n
209 A.3d 246 (Supreme Court of Pennsylvania, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
A. & L. McKnight v. PUC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-l-mcknight-v-puc-pacommwct-2024.