A. J. Paretta Contracting Co. v. United States

109 Ct. Cl. 324, 1947 U.S. Ct. Cl. LEXIS 53, 1947 WL 5076
CourtUnited States Court of Claims
DecidedOctober 6, 1947
DocketNo. 46395
StatusPublished
Cited by2 cases

This text of 109 Ct. Cl. 324 (A. J. Paretta Contracting Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. J. Paretta Contracting Co. v. United States, 109 Ct. Cl. 324, 1947 U.S. Ct. Cl. LEXIS 53, 1947 WL 5076 (cc 1947).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiff sues for the increased wages it was required to pay on a contract with defendant for the construction of a part of a housing project at Massena, New York, and for the cost of repairing certain piers and footings which were damaged by frost.

Its claim for increased wages are for those paid carpenters and common laborers employed on the project. The circumstances under which the increases were paid to the carpenters differ somewhat from those under which the increase was paid to common laborers. We shall discuss first the increased wages paid the carpenters.

1. The Davis-Bacon Act (Act of March 3, 1931, 46 Stat. 1494, as amended by the Act of August 30,1935,49 Stat. 1011, title 40, U. S. C., sections 276a to 276a-6), provides that the specifications for every contract for public buildings or public works should contain a provision setting out the minimum wages to be paid mechanics and laborers and that this minimum should be the wages determined by the Secretary of Labor to be the prevailing wages therefor in the community in which the work was to be done.

On August 10,1942, the Secretary of Labor had determined that the prevailing wage for carpenters for the locality in [346]*346which Massena, New York, is located was $1.25 and the prevailing wage for laborers was 65 cents. The contract in this case was executed on December 2, 1942, and it, accordingly, in the specifications, required plaintiff to pay not less than these wages.

Previous to the execution of the instant contract plaintiff and defendant had entered into a contract on June 9, 1942, for the construction of another part of this housing project. This contract contained the same provisions as to wages as that contained in the instant contract, but plaintiff had been compelled to pay carpenters under the former contract $1.35 an hour. The two contracts covered units in the same housing project, and the carpenters refused to work, for less than $1.35 on the second unit of the project.

Before the instant contract had been executed on December 2,1942, the Stabilization Act of October 2,1942 ( 56 Stat. 765, 767), had been enacted and the President had issued Executive Order 9250, which provided that there should be no increase or decrease in wages without the approval of the National War Labor Board and which prohibited this Board from increasing wages above those prevailing on September 15, 1942, unless necessary to correct inequalities, etc. Inasmuch as the Secretary of Labor had determined that the prevailing wage for carpenters on August 10,1942, was $1.25 plaintiff was thus prohibited by the Stabilization Act and this Executive Order from paying the wages of $1.35 demanded by the carpenters. However, it did so nevertheless up until February 23, 1943. On that date it notified the carpenters' union that in view of the Executive Order it could not pay more than $1.25. The carpenters refused to work for these wages and as a result no carpenter work was done on the project from February 23, 1943, until June 4, 1943.

The carpenters union undertook to get the Wage Adjustment Board, a subsidiary of the National War Labor Board, to authorize an increase in the wage rates, but plaintiff refused to participate in these proceedings, partly for the reason that considerable delay would be encountered before action could be secured from this Board. Instead, it appealed to the Federal Public Housing Authority to settle [347]*347the problem. Plaintiff’s representatives had a conference with the Assistant Director of the Labor Relations Division of the Federal Public Housing Authority in Washington. This official agreed that he would undertake to get the Secretary of Labor to amend the determination of August 10, 1942, fixing the prevailing wages for carpenters at $1.25, if plaintiff would agree that this modification of the previous determination would involve no increased cost to the Government. The Assistant Director understood plaintiff to agree to this, and he, accordingly, took them to the office of the Assistant Solicitor of the Wage Determination Section of the Department of Labor. The Assistant Solicitor also understood plaintiff to agree that a modification of the determination of August 10, 1942, would involve no increase to the Government and, with this understanding, he induced the Secretary of Labor to modify the determination of August 10, 1942, by declaring that the prevailing wage on that date was $1.35 instead of $1.25.

Plaintiff denies that its representatives made any such agreement. The record indicates that they did not expressly do so, but it also indicates that by their conduct and whatever they may have said and by what they left unsaid, they gave these two officials the impression that they would make no claim against the Government for the difference between the $1.25 rate and the $1.35 rate. '

In addition to denying that they made any such agreement, plaintiff says that, irrespective of whether they did so or not, they are entitled to the increase because the determination of the Secretary of Labor was made pursuant to the Secretary’s official duty and was a determination made necessary by the facts and that it was not one induced by any promise they may have made, and, therefore, they are not bound by the promise, if made.

Legally, plaintiff may be correct, whatever may be said of the morality of their conduct, but we do not think the case turns on any agreement they may have made.

The Davis-Bacon Act required that the contract should contain a provision that the contractor should pay not less than the minimum wage fixed in the contract, which should be that wage which had been determined by the Secretary of [348]*348Labor to be the prevailing wage in the community. The Secretary of Labor had determined that $1.25 was the prevailing wage, and the contract contained a provision requiring the contractor to pay not less than this wage. The provisions of the contract were in exact accordance with the facts and with the law. But the contractor says that the Secretary of Labor had made a mistake in this determination of the prevailing wage and that having contracted upon the basis of the determination as made, it is entitled to recover the excess amount it was required to pay.

"We do not think this position can be maintained in view of the provisions of paragraphs c and d of article 6 of the Special Conditions of the Specifications. Paragraph c contemplates that there may be a change in the determination of the prevailing wage as made by the Secretary of Labor prior to the execution of the contract, and it provides that the contractor shall pay not less than the wages which the Secretary of Labor may from time to time determine as the prevailing wage. This section reads:

The determinations of the Secretary of Labor shall be deemed to establish the minimum wages which may be paid to the designated laborers and mechanics * * *

Inasmuch as the minimum wage specified to be paid in paragraph a of article 6 was based upon the last determination of the Secretary of Labor prior to the execution of the contract, the only purpose of paragraph c was to require the contractor to pay any minimum wage that might be determined by the Secretary of Labor after the execution of the contract. This would seem to cover any later determination, whether it was brought about by changed conditions or by a mistake in the previous determination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morrison-Hardeman-Perini-Leavell v. The United States
392 F.2d 988 (Court of Claims, 1968)
Ross Engineering Co. v. United States
127 F. Supp. 580 (Court of Claims, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
109 Ct. Cl. 324, 1947 U.S. Ct. Cl. LEXIS 53, 1947 WL 5076, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-j-paretta-contracting-co-v-united-states-cc-1947.