A. H. Sollinger Construction Co. v. Illinois Building Authority

283 N.E.2d 508, 5 Ill. App. 3d 554, 1972 Ill. App. LEXIS 2750
CourtAppellate Court of Illinois
DecidedMay 24, 1972
Docket71-125
StatusPublished
Cited by9 cases

This text of 283 N.E.2d 508 (A. H. Sollinger Construction Co. v. Illinois Building Authority) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. H. Sollinger Construction Co. v. Illinois Building Authority, 283 N.E.2d 508, 5 Ill. App. 3d 554, 1972 Ill. App. LEXIS 2750 (Ill. Ct. App. 1972).

Opinion

Mr. JUSTICE ALLOY

delivered the opinion of the court:

Plaintiffs, who entered into a. joint venture to act as general contractor for the construction of a building now housing the Appellate Court of Illinois, Second District, brought this action in the Circuit Court of Kane County seeking to recover money allegedly due them under the venture. Their complaint, presenting multiple and alternative theories of recovery, named as defendants the Illinois Building Authority, owner of the building; Lundeen, Hilfinger & Asbury, the architects; and Classic Tile Company, a subcontractor which had laid the brick surface of front and rear courtyards. Trial was by jury and plaintiffs here appeal from an order directing a verdict for Classic Tile at the close of all the evidence, and from a judgment entered on a jury verdict in favor of the Authority and the architects.

The building was accepted by the Authority as substantially completed in August, 1966, subject only to a specific list of items, including the courtyards, to be completed, corrected or repaired. At the same time, final payment of $35,000.00 on the contract price was withheld pending the satisfactory completion of the items on the fist and the resolution of claims that had been made by subcontractors and material-men. Before final settlement was accomplished difficulties arose with the brick surface covering the courtyards. Subsequent to the winter of 1966-1967 it was noted that in many diverse areas the mortar in the joints between the bricks had deteriorated, chipped and fallen out, leaving holes. The Authority notified the architects and the plaintiffs, and the latter, in turn, unsuccessfully sought to have Classic Tile return to correct the work.

Further deterioration occurred during the winter of 1967-1968, and when plaintiffs had done nothing other than to remove the loose mortar, the Authority, after due notification to plaintiffs, and, as permitted under the terms of the contract, employed Western Waterproofing Company, at a cost of $12,225.00, to repair the defective areas. After Western had been employed, and in accordance with the general contract, plaintiffs were notified that they would be “back charged” for the cost of the repair work against the balance due under the contract. The present action followed. In this appeal, plaintiffs principally contend that the trial court erred in directing a verdict for Classic Tile and that the verdict in favor of the Authority and the architects was against the manifest weight of the evidence.

We deem it expedient to first consider the contentions advanced with respect to Classic Tile and the architects, which contentions bring into focus the allegations of plaintiffs’ complaint and the proof introduced to sustain them. Count II of the complaint, directed against Classic Tile, alleged, in pertinent part, that the subcontractor had not performed the paving of the courtyard in a workmanlike manner, or in accordance with the specifications in the subcontract; that the fault and responsibility for the defects was that of Classic Tile; and that under the terms of the subcontract Classic Tile was required to indemnify plaintiffs for the back charge incurred because of the former’s defective work.

Count III, pleading a cause of action against the architects, alleged, in substance, that the architects had a duty to specify a mortar mix capable of withstanding the elements to which the courtyards would be exposed; that they negligently and carelessly selected a mortar mix which was inadequate for the purpose intended; that they negligently and carelessly failed to prescribe the use of vapor barriers or other devices or techniques which would have prevented the deterioration of the mortar joints; and that as a result of such wrongful conduct plaintiffs had suffered damages in the amount of $50,000.00. The respective answers of the defendants denied the foregoing allegations. Classic Tile also alleged, as an affirmative defense, that it had objected to the use of the mortar mix specified but had been more or less coerced into using it by representatives of the plaintiffs and the architects.

The principal witnesses for plaintiffs were Dean F. Hilfinger, one of the architects who was called as an adverse witness; Albert H. Sollinger, president of one of the construction companies which had entered into the joint venture; and Robert F. Duggan, president of the other joint venturer, whose company supervised the actual construction. Classic Tile and the architects presented no proof whatsoever, while the Authority introduced only certain exhibits and the testimony of David R. McNulty, is regional construction director.

From the record, it appears that the design for the exterior courtyards called for vertical brick walls and brick surfaces and, relative thereto, the architects specified: “* * * all masonry work shall be laid in lime and cement mortar composed of one part Portland cement, two parts lime and seven parts sand * * * In lieu of the lime cement mortar above specified, the contractor shall be permitted to use Medusa, Universal or approved equal prepared mortar.” We note that it appears from the record that the prepared mortars are mixed with sand and water at the construction site in proportions as directed by the manufacturer. The base of the courtyards was a four and one-half inch concrete slab poured over gravel, and the method for installing the brick surface was that a bed of mortar would be placed on the top of the concrete slab, that bricks and half bricks would be set in the mortar bed, and that the space between the bricks would then be filled in, or topped, with mortar to form a joint. When the desired result is achieved, the mortar in the topping unites with the mortar in the bed to form a solid masonry bond. In regard to tire latter step in the process, the architects specified that the topping in the mortar joints should be installed to a thickness, or width, of one-half inch.

It should here be noted that brick masons and tile setters, two separate crafts, use different methods in finishing mortar joints. The former use a tool to compress mortar into the space between the bricks and to level it off even with the top of the bricks, making what is called a “tooled joint.” Tile setters, on the other hand, use burlap or some similar material to rub the joint, thus creating some pressure on the mortar in the joint and cleaning excess mortar from the surface. This method produces what is termed a “rubbed joint.” According to the two witnesses who testified on the subject, a tooled joint is greatly superior to a rubbed joint.

The vertical walls in the courtyards were erected by a mason subcontractor, who used Medusa. April Tile Company was originally engaged to lay the brick surfaces, but, for reasons not shown in the record, April Tile was replaced by Classic Tile. It appears that tile companies, rather than brick masons, were engaged to lay the surfaces due to jurisdictional rules of the labor unions involved. Just who made the selection of Medusa under the options given in the specifications was never made entirely clear, but it was, in any event, being used for the exterior courtyard work when Classic Tile came into the picture. There was testimony that Classic Tile “objected” to Medusa and “preferred not to use it” for the surface work, but that it did so at the insistence of representatives of the plaintiffs and the architects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ainsworth Corp. v. Cenco Inc.
511 N.E.2d 1149 (Appellate Court of Illinois, 1987)
Thomas v. Northington
479 N.E.2d 976 (Appellate Court of Illinois, 1985)
Moehle v. Chrysler Motors Corp.
426 N.E.2d 1099 (Appellate Court of Illinois, 1981)
Intaglio Service Corp. v. J. L. Williams & Co.
420 N.E.2d 634 (Appellate Court of Illinois, 1981)
Tom Olesker's Exciting World of Fashion, Inc. v. Dun & Bradstreet, Inc.
390 N.E.2d 60 (Appellate Court of Illinois, 1979)
Saldana v. Wirtz Cartage Co.
370 N.E.2d 1131 (Appellate Court of Illinois, 1977)
Roddy v. Chicago & Northwestern Railroad
363 N.E.2d 65 (Appellate Court of Illinois, 1977)
Morrison v. Community Unit School District No. 1
358 N.E.2d 389 (Appellate Court of Illinois, 1976)
Klavine v. Hair
331 N.E.2d 355 (Appellate Court of Illinois, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
283 N.E.2d 508, 5 Ill. App. 3d 554, 1972 Ill. App. LEXIS 2750, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-h-sollinger-construction-co-v-illinois-building-authority-illappct-1972.