A. Griffis v. Albert Einstein Healthcare Network (WCAB)

CourtCommonwealth Court of Pennsylvania
DecidedMarch 15, 2024
Docket613 C.D. 2022
StatusUnpublished

This text of A. Griffis v. Albert Einstein Healthcare Network (WCAB) (A. Griffis v. Albert Einstein Healthcare Network (WCAB)) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. Griffis v. Albert Einstein Healthcare Network (WCAB), (Pa. Ct. App. 2024).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Anna Griffis, : Petitioner : : v. : No. 613 C.D. 2022 : Submitted: April 28, 2023 Albert Einstein Healthcare Network : (Workers’ Compensation Appeal : Board), : Respondent :

BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge HONORABLE CHRISTINE FIZZANO CANNON, Judge HONORABLE LORI A. DUMAS, Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY PRESIDENT JUDGE COHN JUBELIRER FILED: March 15, 2024

Anna Griffis (Claimant) petitions for review of a May 24, 2022 Order of the Workers’ Compensation Appeal Board (Board) that affirmed, as modified, a decision by a Workers’ Compensation Judge (WCJ) denying Claimant’s Penalty Petition. Claimant filed the Penalty Petition against Albert Einstein Healthcare Network (Employer), asserting Employer did not begin paying its share of the costs associated with a third-party recovery after recovering an accrued lien and failed to pay specific loss benefits. The WCJ concluded Claimant had not paid the accrued lien immediately and therefore Employer was entitled to recover the accrued lien by withholding $332.20 per week over the course of 545.99 weeks. Upon appeal, the Board concluded the WCJ transposed numbers in the amount of the accrued lien, resulting in a miscalculation of the period of suspension, and therefore modified the recovery period to 356.35 weeks, but otherwise affirmed the WCJ’s decision. Before this Court, Claimant asserts the WCJ erred in calculating the reimbursement of Employer’s net subrogation lien using pro rata attorney’s fees and costs rather than the full indemnity1 benefits. For the reasons that follow, we affirm.

I. BACKGROUND With respect to the issue presently before the Court, the WCJ found the following facts:2 1. . . . Claimant[] was injured in the course of her employment on April 28, 2009[,] while employed by . . . Employer. Her injuries were severe. She continues to be entitled to compensation for total disability. 2. Four years after the injury, [] Claimant settled a medical malpractice case in the total amount of $2.088 million . . . . 3. [] Claimant then refused to reimburse [] [Employer’s] already[-] substantial subrogation lien[,3] electing instead to challenge [] [Employer’s] right to subrogation. The [WCJ’s] Order of August [1], 2017[4] confirmed [] [E]mployer’s right to subrogation, but [] Claimant continued to refuse to reimburse the lien. 4. As a result of [] Claimant’s failure to reimburse the lien, [] Employer[,] as of October 3, 2017[,] stopped paying wage loss

1 Wage-loss benefits, indemnity benefits, and disability benefits are synonymous in workers’ compensation. See, e.g., CPV Mfg., Inc. v. Workers’ Comp. Appeal Bd. (McGovern), 805 A.2d 653, 658 (Pa. Cmwlth. 2002). 2 Claimant represents in her brief that “[t]he facts of this case are not in dispute, only the calculation of [] Employer’s reimbursement of the net subrogation lien.” (Claimant’s Brief (Br.) at 8.) We explained in great detail the factual and procedural history of this case in Griffis v. Workers’ Compensation Appeal Board (Albert Einstein Healthcare Network) (Pa. Cmwlth., Nos. 273 and 280 C.D. 2019, filed July 15, 2020) (Griffis I). 3 The subrogation lien represents the amount Claimant owes Employer from the time of her recovery of the third-party settlement until Employer learned of the settlement and ceased paying indemnity benefits, as the receipt of the third-party settlement on the part of Claimant represented a prepayment of future indemnity benefits. Griffis I, slip op. at 30-31. 4 The WCJ appears to have accidentally referred to the Order as being dated August 3; the relevant Order is dated August 1.

2 compensation benefits[,5] as it was [] Employer’s only means of recouping the substantial lien. 5. Consequently, Claimant filed a Penalty Petition on November 3, 2017[,] alleging that [] Employer violated the [Workers’ Compensation] Act [(Act[)6] by failing to pay its pro rata share of [Claimant’s] fees and expenses. 6. The May 10, 2018 [WCJ] Decision [] ordered [] Claimant to reimburse [] Employer for its lien and found that [] Employer was entitled to a full suspension of [] Claimant’s benefits until the lien was reimbursed. 7. [The May 10, 2018] Order [of the WCJ] was ultimately affirmed as modified by the [Board] and then on July 15, 2020[,] by the Commonwealth Court.[7] 8. [] Claimant has failed to offer any evidence or rational theory in support of the position that the lien has been reimbursed by [] Claimant. 9. Despite the very significant third-party recovery, [] [Employer’s] lien is not even close to being reimbursed. Because [] Claimant has failed to reimburse, [] Employer can recoup the amount due only by withholding the amount that would otherwise be due on a weekly basis. 10.[] Claimant has failed to prove a violation of the Act.

5 Where an employer is subrogated to a workers’ compensation claimant’s rights in a third- party tort settlement, the claimant is entitled to pro rata reimbursement of the fees and costs associated with procuring that settlement in the first instance. 21A SUMM. PA. JUR. 2d, EMPLOYMENT & LAB. RELS § 18:39 (2d ed.). Thus, in a scenario where the claimant pays the full subrogation lien up front, during the grace period in which the employer need not pay compensation because that compensation has essentially been “prepaid” by the remaining balance of recovery Claimant has in the settlement, the employer must still pay pro rata costs and fees. Id. This avoids the potential for unjust enrichment because the claimant has created a fund for the benefit of the employer at the claimant’s expense. Id. at § 18:41. 6 Act of June 2, 1915, P.L. 736, as amended, 77 P.S. §§ 1-1041.4, 2501-2710. 7 In Griffis I, this Court, while acknowledging it was a violation of the Act for Employer to unilaterally cease payment, affirmed the Board’s affirmance of the WCJ, who declined to impose penalties. “Because there was no error in suspending Claimant’s benefits until she repays Employer as set forth above, the WCJ did not abuse his discretion in declining to impose penalties despite finding a violation of the [] Act.” Id., slip op. at 34.

3 (WCJ Decision, 11/10/2021, Findings of Fact (FOF) ¶¶ 1-10.)8 To summarize, the relevant facts are that Claimant was injured during the course and scope of employment and received, inter alia, indemnity benefits from Employer. She later received a large settlement in her medical malpractice action against the doctors who treated her for the work injury. Employer established subrogation rights in the award, which resulted in: (i) Claimant owing a lump sum subrogation lien to Employer for past double payment of benefits, which she has refused to pay, and (ii) the remaining settlement funds (i.e., balance of recovery), deemed “prepayment” of indemnity benefits under the Act, serving as a credit Employer is entitled to take against payment of future indemnity benefits (i.e., creating a “grace period”). During the grace period, Employer was to pay Claimant its pro rata share of the costs and fees associated with recovering the medical malpractice settlement. Employer has not paid any pro rata costs and fees to Claimant since October 2017. The WCJ reasoned that Employer’s “only way to get reimbursed is to stop paying compensation due until the debt has been recovered” given Claimant’s choice not to immediately reimburse the existing lien. (Id. at 5.) The WCJ explained that if Claimant had immediately reimbursed the lien, Employer would have been obligated to pay fees and costs associated with the medical malpractice recovery of $332.20 per week, representing Employer’s share of the fees and costs of obtaining the third-party settlement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CPV Manufacturing, Inc. v. Workers' Compensation Appeal Board
805 A.2d 653 (Commonwealth Court of Pennsylvania, 2002)
Monessen, Inc. v. Workers' Compensation Appeal Board
875 A.2d 415 (Commonwealth Court of Pennsylvania, 2005)
Universal Am-Can, Ltd. v. Workers' Compensation Appeal Board
762 A.2d 328 (Supreme Court of Pennsylvania, 2000)
Mrkich v. Workers' Compensation Appeal Board
801 A.2d 668 (Commonwealth Court of Pennsylvania, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
A. Griffis v. Albert Einstein Healthcare Network (WCAB), Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-griffis-v-albert-einstein-healthcare-network-wcab-pacommwct-2024.