A. G. Rushlight & Co. v. Johnson

139 P.2d 280, 18 Wash. 2d 383
CourtWashington Supreme Court
DecidedJuly 2, 1943
DocketNo. 28965.
StatusPublished
Cited by4 cases

This text of 139 P.2d 280 (A. G. Rushlight & Co. v. Johnson) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. G. Rushlight & Co. v. Johnson, 139 P.2d 280, 18 Wash. 2d 383 (Wash. 1943).

Opinion

Grady, J.

This action was brought by A. G. Rush-light & Company, a corporation, against George Johnson, J. O. Johnson, and Albin Johnson, copartners doing business under the firm name and style of Western Construction Company, to recover damages for breach of contract. The case was tried before the court and a jury, and a verdict for the plaintiff was returned. The court denied a motion of the defendants for judgment notwithstanding the verdict of the jury, but granted their alternative motion for a new trial on the specific ground that an error had been committed by the court in giving instruction No. 15. The plaintiff has appealed from the order granting a new trial, and the defendants have taken a cross-appeal from the order denying their motion for a judgment notwithstanding the verdict.

The basis of the complaint is that respondents had entered into a contract with the United States govern *385 ment to construct a warehouse in the city of Seattle, and, on July 12, 1941, in connection with the performance of the main contract, awarded a subcontract to appellant to install all plumbing, heating, and sprinkler systems, sewer work, and temporary toilets for workmen; that, shortly after the subcontract was executed, the respondents wrongfully repudiated the subcontract and refused to permit further performance by the appellant, which caused it to suffer damages.

The answer of the respondents admitted their co-partnership status, the existence of their contract with the United States government, the entry into the subcontract with the appellant, and denied generally all of the other allegations of the complaint. The respondents then set up a “first, separate and affirmative defense,” in which they plead in detail that appellant had breached its subcontract with them, in that it failed, neglected, and refused to furnish them the bond required under the subcontract or to install the temporary toilet facilities for workmen as provided for in the subcontract; and, for these reasons, they had declared the subcontract breached, forfeited, and terminated.

The reply of the appellant alleged that the bond referred to in the answer was given by it to the respondents before any attempt was made by them to terminate the subcontract; that, prior to the giving of the bond, the time had been extended by the respondents, and the bond was furnished within such time; also, that no notice had been given by the respondents to appellant at any time prior to the repudiation of the subcontract that the temporary toilet facilities were needed, or that the subcontract would be terminated if such facilities were not installed; and that the respondents had not erected a building or prepared a place in which the toilet facilities could be installed.

We have made a somewhat extended reference to the pleadings, as they have an important bearing upon *386 the action of the trial court in granting a new trial because of the giving of instruction No. 15, relating to the burden of proof. The factual situation which the jury had a right to adopt, and which we deem sufficient to consider the questions raised on the appeal and cross-appeal, is as follows:

The subcontract contained the following provisions:-

“Section 3. The Subcontractor and the Contractor' agree that the materials, labor, equipment, supplies,-' and tools to be furnished and work to be done by the Subcontractor are as follows:
“Having carefully examined the plans and specifications and Addenda 1, 2 and 3, as well as the premises, the Subcontractor agrees to furnish all material and' labor in the installation of all plumbing, heating, sprinkler systems, sewer work and temporary toilets for workmen. All in accordance with plans and specifications and to the satisfaction of the engineer-in-charge. . . .
“Section 4. The Subcontractor agrees to complete the several portions and the whole of the work herein sublet by the time or times following: Work to commence as soon as the project is ready and to be carried on with sufficient force so as not to delay the general-progress of the work. Should the said Subcontractor neglect to carry on his work with sufficient force and thereby cause delay on the project, the General Contractor reserves the right after giving forty-eight hours’ written notice to take over the contract and complete the same, charging the expense thereof to the said Subcontractor; . . .
“Section 12. Unless it is expressly waived herein, the Subcontractor agrees that he will within five days from date herein provide the Contractor with a bond in a Surety Company in form and contents acceptable to the Contractor, conditioned for the faithful performance of this contract in all of its particulars.”

When the parties discussed the prepared subcontract, the appellant requested that the provision for the giving of the bond be waived. The respondent with whom the matter was discussed objected to this, but he agreed that they would pay one half of the bond premium.' *387 The appellant requested the respondent to take up the matter of the waiving of the bond with his brothers. The respondent then suggested that the question of the bond be left until the first of the week, when respondents would let appellant know if the bond would be waived. There was then appended to the subcontract the following provision, which both parties signed:

“It is hereby understood and agreed that in the event a subcontract bond is required, Western Construction Co. and A. G. Rushlight & Co. will each pay one-half the amount of premium in payment of bond, notwithstanding sec. 12 of subcontract agreement, which is hereby modified as above as to payment of premium.”

This was on Saturday, July 12th. On July 15th, respondents wrote a letter to appellant, addressed to its office in Portland, Oregon, informing it that they had decided to ask that a bond be furnished in accordance with section twelve of the subcontract. On the same day, the respondents got in communication with Mr. Rushlight in Seattle by telephone and informed him that they would require the bond, and read a copy of the letter to him. The respondents also, in this telephone conversation, requested that appellant put in the temporary plumbing, explaining that their contractee was insistent on its being installed. In neither the letter nor the telephone conversation did the respondents tender or offer to pay one half of the bond premium.

On July 18th, the respondents wrote another letter to appellant, demanding that the bond be given and stating that they wanted it within the five-day period provided for in the subcontract, or even sooner, but adding that, as three days had already passed, it could not be expected sooner. In this letter they stated they were ready and willing to pay one half of the amount of the bond premium. The letter was received at the Portland office of the appellant on July 19th.

On the morning of July 22nd, the respondents again *388 mailed a letter to appellant, informing it that they had elected to terminate the subcontract; the reasons given for its termination were failure to give bond and failure to put in temporary plumbing. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valeo Intellectual Property, Inc. v. Data Depth Corp.
368 F. Supp. 2d 1121 (W.D. Washington, 2005)
Pritchett v. City of Seattle
335 P.2d 31 (Washington Supreme Court, 1959)
Lamoreaux v. Fosket
273 P.2d 795 (Washington Supreme Court, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
139 P.2d 280, 18 Wash. 2d 383, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-g-rushlight-co-v-johnson-wash-1943.