A & G Coal Corporation v. Commonwealth of Kentucky, Energy and Environment Cabinet

Court of Appeals of Kentucky·Decided February 29, 2024·No. 2022 CA 000493·Unknown

Opinion

RENDERED: MARCH 1, 2024; 10:00 A.M.

NOT TO BE PUBLISHED

Commonwealth of Kentucky

Court of Appeals

NO. 2022-CA-0493-MR

AND

NO. 2022-CA-0505-MR

A & G COAL CORPORATION; BEECH CREEK COAL KENTUCKY CORPORATION; FOUR STAR RESOURCES, LLC; INFINITY ENERGY, INC.; KENTUCKY FUEL CORPORATION; SEQUOIA ENERGY, LLC; VIRGINIA FUEL CORPORATION; JAMES C. JUSTICE, II; AND JAMES C. JUSTICE, III APPELLANTS/CROSS-APPELLEES

APPEAL AND CROSS-APPEAL FROM FRANKLIN CIRCUIT COURT v. HONORABLE THOMAS D. WINGATE, JUDGE ACTION NO. 15-CI-01125

COMMONWEALTH OF KENTUCKY, ENERGY AND ENVIRONMENT CABINET APPELLEE/CROSS-APPELLANT

OPINION

AFFIRMING

** ** ** ** **

BEFORE: CETRULO, JONES, AND TAYLOR, JUDGES.

TAYLOR, JUDGE: A & G Coal Corporation; Beech Creek Coal Kentucky Corporation; Four Star Resources, LLC; Infinity Energy, Inc.; Kentucky Fuel Corporation; Sequoia Energy, LLC; Virginia Fuel Corporation; James C. Justice, II; and James C. Justice, III (hereinafter collectively referred to as appellants) bring Appeal No. 2022-CA-0493-MR from a November 9, 2021, Order of the Franklin Circuit Court, as amended by Order entered April 18, 2022, enforcing a Settlement Agreement entered into with the Commonwealth of Kentucky, Energy and Environment Cabinet (Cabinet), on April 30, 2019 and incorporated into an Agreed Judgment entered on October 21, 2019. The Cabinet has filed a Cross-Appeal from the same Orders in Cross-Appeal No. 2022-CA-0505-MR, contesting the circuit court’s amendment of the interest rate on the outstanding sum owed by appellants as set out in the Settlement Agreement and Agreed Judgment. For the reasons stated, we affirm both appeals.

I. APPEAL NO. 2022-CA-0493-MR BACKGROUND

On August 15, 2014, the parties entered into an Agreed Order (2014 Agreed Order) with the Cabinet that required appellants to timely complete certain reclamation activities on coal mining permits contained in the 2014 Agreed Order

by September 1, 2015.1 Incorporated into the 2014 Agreed Order was an admission by appellants that they had breached twelve previous agreed orders relating to many of the violations and penalties at issue in the 2014 Agreed Order. The 2014 Agreed Order provided for bonding requirements and permitting actions. Notably, it was stipulated that the appellants owed the Cabinet $4,498,995 – an amount the parties agreed fairly represented the combined value of several civil penalties the Cabinet could have otherwise assessed against appellants under Kentucky law. Further, the 2014 Agreed Order stipulated that if appellants strictly complied with and satisfied all of the order’s terms by September 1, 2015,2 appellants would only owe the Cabinet $1.5 million. In the event appellants failed to do so, however, whatever remained of the $4,498,995 would be due as of that date and would begin to accrue interest from September 1, 2015.

On October 23, 2015, the Cabinet initiated the underlying action in Franklin Circuit Court to enforce the 2014 Agreed Order. In its complaint, the Cabinet alleged appellants failed to comply with the terms of the 2014 Agreed

1 The 2014 Agreed Order was entered in an administrative proceeding before the Energy and Environment Cabinet (Cabinet) on August 15, 2014, and signed by Leonard K. Peters, as Secretary of the Cabinet. 2 Paragraph 51 of the 2014 Agreed Order provided: “Time is of the essence in the implementation of this Agreed Order by the Petitioners and the terms of this Agreed Order are to be strictly construed so as to achieve prompt and complete abatement of violations and payment of civil penalties.” Paragraph 56 provided that “Failure to complete all remedial measures by September 1, 2015, unless under extension granted . . . , shall result in the imposition of the [various breach remedies] without hearing or notification of breach.”

Order. After nearly four years of litigation and at least four mediations that followed, the parties then entered into a Settlement Agreement effective April 30, 2019, (2019 Settlement Agreement). The terms of the 2019 Settlement Agreement required appellants to pay the principal balance remaining from the 2014 Agreed Order ($2,998,995). Among other terms, it also required appellants to complete reclamation activities at five different sites by specified times and to post a letter of credit with the Cabinet to secure the payment of the principal balance owed.

Paragraph 7 of the 2019 Settlement Agreement further provided that if appellants “fully satisfied all of the obligations set forth in this Settlement Agreement within all of the time frames specified in this Settlement Agreement as confirmed by the [Cabinet], the [Cabinet] shall acknowledge that the principal balance of the $2,998,995 civil penalty plus interest accrued thereon owed by the [appellants] to the [Cabinet] pursuant to the August 15, 2014 Agreed Order has been fully satisfied.” In the event appellants failed to do so, Paragraph 10 provided, in sum, that appellants would immediately be in default, and that the Cabinet would be entitled to the relief and remedies otherwise provided pursuant to the 2014 Agreed Order.

Subsequently, the parties jointly sought and were granted an Agreed Judgment entered by the circuit court on October 21, 2019. Importantly, for purposes of this appeal, the Agreed Judgment incorporated therein the terms of the

2019 Settlement Agreement and the 2014 Agreed Order. On September 27, 2021, the Cabinet moved the circuit court to declare appellants in default of the 2019 Settlement Agreement, and to enforce the Agreed Judgment of October 21, 2019. Appellants did not dispute that they had failed to complete all the reclamation activities at the five different sites by the deadlines specified in the 2019 Settlement Agreement. Nevertheless, they argued they should not be found in default because, as they asserted, the COVID-19 pandemic made it “impractical” for them to perform the required work. And, due to that purported impracticality, appellants argued the circuit court was required to exercise its equitable authority to provide them a six-month extension regarding their obligations. Ultimately, the circuit court rejected appellants’ arguments and entered an Order enforcing the October 21, 2019, Agreed Judgment in favor of the Cabinet. This appeal followed.

STANDARD OF REVIEW

As noted, this appeal looks to the enforcement of the Agreed Judgment entered into by the parties on October 21, 2019, that incorporated the terms of the parties’ 2019 Settlement Agreement as well as relevant terms of the 2014 Agreed Order. The circuit court concluded that appellants failed to comply with the 2019 Settlement Agreement. Accordingly, our review in this appeal necessarily looks to the interpretation and construction of the terms of the 2019 Settlement Agreement, which is well-established under Kentucky jurisprudence to

be questions of law for this Court. See Cinelli v. Ward, 997 S.W.2d 474, 476 (Ky. App. 1998). Accordingly, our review is de novo. Id.; see also Nelson v. Ecklar, 588 S.W.3d 872, 878 (Ky. App. 2019).

ANALYSIS

The primary arguments raised by appellants in this appeal are: (1)

appellants’ substantially complied with most of their obligations under the 2019 Settlement Agreement; (2) their failure to complete all the reclamation activities at the five different sites by the deadlines specified in the 2019 Settlement Agreement should have been excused under the doctrine of “impracticability”; and (3) the circuit court should have equitably modified their agreed-upon deadlines in the 2019 Settlement Agreement to provide them a six-month extension, rather than declaring them in breach.

Free access — add to your briefcase to read the full text and ask questions with AI

A & G Coal Corporation v. Commonwealth of Kentucky, Energy and Environment Cabinet, (Ky. Ct. App. 2024).

A & G Coal Corporation v. Commonwealth of Kentucky, Energy and Environment Cabinet (A & G Coal Corporation v. Commonwealth of Kentucky, Energy and Environment Cabinet) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Reliable Mechanical, Inc. v. Naylor Industrial Services, Inc.
125 S.W.3d 856 (Court of Appeals of Kentucky, 2004)
E'Town Shopping Center, Inc. v. Lexington Finance Co.
436 S.W.2d 267 (Court of Appeals of Kentucky (pre-1976), 1969)
Cinelli v. Ward
997 S.W.2d 474 (Court of Appeals of Kentucky, 1998)
Hopkins v. Ratliff
957 S.W.2d 300 (Court of Appeals of Kentucky, 1997)
Mid-Continent Petroleum Corp. v. Barrett
181 S.W.2d 60 (Court of Appeals of Kentucky (pre-1976), 1944)
Fidelity Deposit Co. of Maryland v. Jones
75 S.W.2d 1057 (Court of Appeals of Kentucky (pre-1976), 1934)
Frazier v. Collins
187 S.W.2d 816 (Court of Appeals of Kentucky (pre-1976), 1945)
Sword, Special Deputy Banking Com'r v. Scott
169 S.W.2d 825 (Court of Appeals of Kentucky (pre-1976), 1943)
Uncle George Orphans Home, Inc. v. Landrum
551 S.W.2d 582 (Court of Appeals of Kentucky, 1977)
Goetz v. Asset Acceptance, LLC
513 S.W.3d 342 (Court of Appeals of Kentucky, 2016)
Jackson Hosp. Corp. v. United Clinics of Ky., LLC
545 S.W.3d 327 (Court of Appeals of Kentucky, 2018)