A & C Electric Co. v. Meade Electric Co. (In Re a & C Electric Co.)

211 B.R. 268, 38 Collier Bankr. Cas. 2d 686, 1997 Bankr. LEXIS 470, 1997 WL 391819
CourtUnited States Bankruptcy Court, N.D. Illinois
DecidedApril 11, 1997
Docket19-00434
StatusPublished
Cited by7 cases

This text of 211 B.R. 268 (A & C Electric Co. v. Meade Electric Co. (In Re a & C Electric Co.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A & C Electric Co. v. Meade Electric Co. (In Re a & C Electric Co.), 211 B.R. 268, 38 Collier Bankr. Cas. 2d 686, 1997 Bankr. LEXIS 470, 1997 WL 391819 (Ill. 1997).

Opinion

MEMORANDUM OPINION

JACK B. SCHMETTERER, Bankruptcy Judge.

This adversary proceeding relates to the case filed by A and C Electric Company, Inc. (“A & C”) under Chapter 11 of the Bankruptcy Code, 11 U.S.C. § 101 et seq., on August 15, 1995 (“Petition Date”), in which A & C’s plan has been confirmed. This adversary proceeding was commenced on August 20, 1996, by A & C against defendant Meade Electric Company, Inc. (“Meade”). It seeks judgment requiring Meade to turn over to A & C the balance of certain proceeds that Meade has in its possession and to which Meade asserts a right of recoupment. Plaintiff sued for $181,345.81, plus interest, computed as the net of its claim for $193,000 less $11,650.19 tendered by Defendant to it. Plaintiff seeks a declaration that Meade’s asserted recoupment rights were discharged or limited under the confirmed Plan and claims that the $193,000 is a fund belonging to it. The parties have cross-moved for summary judgment. For reasons stated below, Plaintiffs motion is denied and Defendant is found to be entitled to assert recoupment, but the undetermined issue of the amount it can claim prevents entry of judgment at this time.

Undisputed Facts

The following undisputed facts emerge from the pleadings and summary judgment filings under Local Bankruptcy Rule 402.M and N:

1. A & C is an Illinois corporation engaged in the business of electrical contracting, with its principal place of business at 2049 Greens Court, Hoffman Estates, Illinois.

2. Meade is an Illinois corporation engaged in the business of electrical contracting, with its principal place of business at 710 Quail Ridge Drive, Westmont, Illinois.

3. On or about February 24, 1994, A & C entered into a subcontract (“Subcontract”) with Meade for the performance by A & C of certain electrical construction work on the United States Postal Service facility in Chicago, Illinois (“PO Project”). Meade was a subcontractor of the general contractor, which was a joint venture consisting of The George Hyman Construction Co. and Power Contracting & Engineering Corp. (“General Contractor”). The PO Project is owned by the United States Postal Service (“Owner”).

4. While performing the Subcontract, A & C performed certain' work and incurred certain costs which A & C asserts were outside of the work required by it under the Subcontract. Accordingly, it submitted a claim (“Extras Claim”) for such work and costs to Meade. Meade in turn submitted the Extras Claim with its mark-up to the General Contractor which in turn submitted it to the Owner. At the time the Extras Claim was submitted, the General Contractor and/or the Owner disputed Meade’s right to payment therefor.

5. By letters dated June 26, 1995 and July 13, 1995, A & C notified Meade that it was having financial difficulties and that unless an agreement was reached to provide financial accommodations to A & C by July *271 14,1995, A & C would not be able to complete its obligations under the Subcontract.

6. By letter dated August 8, 1995, Meade informed A & C that Meade would pay certain vendors of A & C but would not otherwise assist A & C.

7. On August 15, 1995, A & C filed a voluntary petition for relief under Chapter 11 of the Bankruptcy Code. Prior to the filing, A & C ceased work on the PO Project and did not complete its obligations under the Subcontract.

8. On August 18,1995, Meade informed A & C that A & C was in default under the Subcontract and that if the defaults were not cured within three days, Meade would complete A & C’s work with its own manpower. A & C was also informed that Meade would use the unpaid balance of the Subcontract funds to complete A & C’s work. Lastly, A & C was notified that any excess funds would be remitted to A & C and that Meade would require A & C to satisfy any shortfall.

9. By letters dated August 29, 1995, September 8, 1995 and September 15, 1995, Meade informed A & C of the status of Meade’s completion of A & C’s obligations under the Subcontract. Invoices for Meade’s services were also sent to A & C.

10. On January 5, 1996 and May 6, 1996, monthly statements of the hours spent by Meade completing A & C’s obligations under the Subcontract were transmitted to A & C with back-up.

11. On March 22,1996, Meade filed in the related bankruptcy case its proof of claim in the amount of $227,925, as an unsecured non-priority claim for the total of expenses incurred to that date and its estimate of the cost to be incurred in the future to complete A & C’s portion of the PO Project.

12. On the summary attached to its proof of claim, Meade set forth that the basis for the claim was back charges to A & C for Meade to complete and correct A & C’s work on the PO Project.

13. On or about April 21, 1996, Meade completed performance of A & C’s portion of the PO Project.

14. During the pendency of the bankruptcy, representatives of A & C participated in a meeting with representatives of the General Contractor, the Owner and Meade regarding the payment of the Extras Claim, among other things.

15. Meade now claims in its motion papers that the total cost of completing and correcting A & C’s work on the PO Project was actually $234,783.96.

16. The Subcontract provided, in paragraph 3(d):

Contractor [Meade] may withhold amounts otherwise due under this Subcontract or any other agreement between the parties to cover Contractor’s reasonable estimate of any costs or liability contractor has incurred or may incur for which Subcontractor [A & C] may be responsible under this Subcontract or any other agreement between the parties. Appropriate adjustments to withholdings shall be made when the exact amounts owed are determined.

17. The Subcontract provided, in paragraph 9(a):

In case of termination for default, Subcontractor shall not be entitled to receive any further payment until the work shall be fully completed and accepted by the Owner and payment in full made by the Owner. At such time, if the unpaid balance of the price to be paid shall exceed the expense incurred by Contractor including overhead and profit, such excess shall be paid by Contractor to Subcontractor. If such amount shall exceed such unpaid balance, the Subcontractor shall pay Contractor the difference on demand.

18. On January 31, 1996, A & C filed its proposed Plan of reorganization.

19. On February 29, 1996, the court entered an order approving the adequacy of A & C’s disclosure statement, fixing the time for filing acceptances or rejections to the Plan and directing that the Plan, disclosure statement and a ballot be served on creditors and other parties in interest.

20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Eggers
432 B.R. 577 (W.D. Texas, 2010)
ORIUS CORP. v. Qwest Corp.
373 B.R. 555 (N.D. Illinois, 2007)
PPM Finance, Inc. v. Norandal USA, Inc.
297 F. Supp. 2d 1072 (N.D. Illinois, 2004)
In Re Black
280 B.R. 680 (N.D. Alabama, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
211 B.R. 268, 38 Collier Bankr. Cas. 2d 686, 1997 Bankr. LEXIS 470, 1997 WL 391819, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-c-electric-co-v-meade-electric-co-in-re-a-c-electric-co-ilnb-1997.