A-1 General Contracting, Inc. v. River Market Commodities, Inc.

212 A.D.2d 897, 622 N.Y.S.2d 378, 1995 N.Y. App. Div. LEXIS 1410
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 9, 1995
StatusPublished
Cited by14 cases

This text of 212 A.D.2d 897 (A-1 General Contracting, Inc. v. River Market Commodities, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A-1 General Contracting, Inc. v. River Market Commodities, Inc., 212 A.D.2d 897, 622 N.Y.S.2d 378, 1995 N.Y. App. Div. LEXIS 1410 (N.Y. Ct. App. 1995).

Opinion

Casey, J.

Appeal from a judgment of the Supreme Court (Lomanto, J.), entered November 22, 1993 in Fulton County, upon a decision of the court in favor of plaintiffs.

The parties entered into an agreement whereby plaintiff A-l General Contracting, Inc. (hereinafter plaintiff) was to demolish a former meat packing plant in the City of Utica, Oneida County, which consisted of an abandoned structure and a large smokestack. The demolition was to include the removal of all debris, and necessary backfilling and grading. Defendant agreed to pay $90,000 for the demolition work. The parties contemplated periodic partial payments or advances during the course of the work. After plaintiff began the demolition work, including the implosion of the chimney, a dispute arose as to whether plaintiff was entitled to a partial payment. Defendant refused to pay until plaintiff did more work; plaintiff refused to do more work until defendant made a partial payment. The parties’ intransigence inevitably led to the courtroom where, in separate actions, each party claimed that the other breached the contract. After a nonjury tried, Supreme Court concluded that defendant not only breached the contract, but also acted willfully and maliciously, which had the intended effect of making plaintiff’s performance of its contractual obligations impossible. Plaintiff’s damages were assessed at $80,000, which represented the full amount of the contract price less the one $10,000 partial payment made by defendant. Defendant appeals from the judgment entered on Supreme Court’s decision.

Based upon our review of the record, we agree with Supreme Court that defendant breached the contract, but we find no evidence in the record to support the court’s finding on the issue of impossibility. In the exercise of our factfinding authority in this nonjury case (see, e.g., Kandrach v State of New York, 188 AD2d 910, 912-913), we conclude that the judgment should be modified to reduce the amount of damages to $45,500 for the reasons set forth below.

In response to defendant’s request for bids on the demolition project, plaintiff submitted a proposal to perform the demolí[898]*898tion for $90,000, which defendant accepted. The proposal contained no detail regarding plaintiffs obligations or how payment was to be made by defendant. The parties subsequently executed a contract which details the work to be performed by plaintiff. Regarding payment, the contract contains a provision which recognized plaintiffs need for funds during the course of the demolition work, and as a result defendant agreed "to advance to [plaintiff], upon request, on account of the monies to become due upon completion of this contract such reasonable sums as in the judgment of [defendant] may balance the work performed by [plaintiff] to the date of such request, allowing the retention, at all times, of sufficient funds to cover the unfinished work remaining to fulfill the terms of this agreement”.

Prior to the execution of the contract, plaintiff Kenneth F. Roser (plaintiffs president) and defendant’s attorney apparently discussed a specific payment schedule. In the belief that an agreement had been achieved during the discussions, Roser drafted a letter setting forth a payment schedule which required six $10,000 payments upon completion of specified stages of the demolition work and a final $30,000 payment upon completion of all work. Upon receipt of the typewritten letter, defendant’s attorney added to five of the $10,000 payments handwritten notations which required removal of debris in addition to the demolition work specified in the letter. Supreme Court concluded that the letter could be used to clarify or define the ambiguous payment provision in the contract, and agreed with plaintiff that the handwritten notations should be ignored. We disagree. We find that the letter establishes the lack of an agreement regarding a specific payment schedule. As evidenced by the typewritten portion of the letter, plaintiff sought a payment schedule with specific terms. As evidenced by the handwritten notations added by defendant’s attorney, defendant sought a payment schedule with different terms. There clearly was no meeting of the minds regarding the terms of a specific payment schedule, a conclusion buttressed by the parties’ subsequent execution of the contract which contained the vague provision regarding payment and did not refer to the earlier letter. We conclude, therefore, that the letter is irrelevant for the purpose of determining which party breached the contract.

Plaintiff contends that defendant breached the contract by refusing plaintiffs request for an additional advance of the money due under the contract. Defendant contends that no additional advance was required until further work was per[899]*899formed and, therefore, plaintiff breached the contract by refusing to perform. Resolution of the competing claims depends upon the interpretation and application of the contractual payment provision set forth above. The provision cannot be construed as giving defendant the unfettered right to decide if, when and how much money should be advanced to plaintiff, for a contract should not be interpreted in such a way as would leave one of its provisions substantially without force or effect (see, Tantleff v Truscelli, 110 AD2d 240, 245-246, affd 69 NY2d 769). We construe the provision as requiring that defendant act reasonably in exercising its judgment when an advance is requested, taking into account the amount of the work performed in relation to the total work contemplated. The issue, therefore, distills to whether there was a reasonable basis for defendant’s refusal to make the payment requested by plaintiff.

The testimony of Roser and a subcontractor who worked on the project, together with the photographic evidence, clearly establishes that plaintiff made substantial progress on the project. After moving equipment onto the site in November 1986, plaintiff made several written and numerous oral requests for an advance as the work progressed. Roser testified that defendant’s attorney agreed to deliver a $20,000 payment to the work site the day the smokestack was brought down with dynamite. The attorney was present at the sight and watched the blasting, which occurred at the end of February 1987, but he left without delivering the payment. Plaintiff thereafter received a $10,000 check in the mail and continued to work into July 1987 despite defendant’s failure to comply with plaintiff’s repeated requests for more money. Defendant suggested at trial that plaintiff breached the contract by using subcontractors and by failing to have adequate insurance, but during the relevant time period defendant never directed plaintiff to cease work. Instead, defendant’s attorney repeatedly urged plaintiff to continue the work and assured plaintiff that additional payments would be made when the work progressed. There is also evidence in the record to support Supreme Court’s finding of adequate insurance. Having received no payment other than $10,000, plaintiff stopped work in July 1987. According to Roser and the subcontractor, the project was 80% complete at that time.

We find that the evidence clearly establishes that defendant did not act reasonably in refusing to advance any more than approximately 11% of the contract price despite the substantial progress made by plaintiff. Defendant claims that its [900]*900refusal was justified by the presence of a large amount of debris on the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Radiation Oncology Servs. of Cent. N.Y., P.C. v. Our Lady of Lourdes Mem. Hosp., Inc.
2023 NY Slip Op 06019 (Appellate Division of the Supreme Court of New York, 2023)
Aerotek, Inc. v. Mept 757 Third Ave., LLC
2020 NY Slip Op 06377 (Appellate Division of the Supreme Court of New York, 2020)
Gapiii, Inc. v. Seal Industries, Inc.
789 S.E.2d 321 (Court of Appeals of Georgia, 2016)
Frank Brunckhorst Co., LLC v. JPKJ Realty, LLC
129 A.D.3d 1019 (Appellate Division of the Supreme Court of New York, 2015)
Catskill Modular Homes of Greene County, Inc. v. Hanson
87 A.D.3d 790 (Appellate Division of the Supreme Court of New York, 2011)
Ward v. Melis
28 A.D.3d 970 (Appellate Division of the Supreme Court of New York, 2006)
James E. McMurray Enterprises, Inc. v. Frohlich
309 A.D.2d 836 (Appellate Division of the Supreme Court of New York, 2003)
Hidden Meadows Development Co. v. Parmelee's Forest Products, Inc.
289 A.D.2d 642 (Appellate Division of the Supreme Court of New York, 2001)
Teramo & Co. v. O'Brien-Sheipe Funeral Home, Inc.
283 A.D.2d 635 (Appellate Division of the Supreme Court of New York, 2001)
In re the Arbitration between County of Chemung & Civil Service Employees Ass'n
277 A.D.2d 792 (Appellate Division of the Supreme Court of New York, 2000)
Matzen Construction, Inc. v. Schultz
257 A.D.2d 724 (Appellate Division of the Supreme Court of New York, 1999)
Eddy v. Champlain Milk Producers Cooperative, Inc.
231 A.D.2d 830 (Appellate Division of the Supreme Court of New York, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
212 A.D.2d 897, 622 N.Y.S.2d 378, 1995 N.Y. App. Div. LEXIS 1410, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-1-general-contracting-inc-v-river-market-commodities-inc-nyappdiv-1995.