819d LLC v. Pcg Construction Group, LLC

CourtDistrict Court, District of Columbia
DecidedFebruary 2, 2021
DocketCivil Action No. 2019-0080
StatusPublished

This text of 819d LLC v. Pcg Construction Group, LLC (819d LLC v. Pcg Construction Group, LLC) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
819d LLC v. Pcg Construction Group, LLC, (D.D.C. 2021).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

819D LLC,

Plaintiff,

v. Case No. 1:19-cv-00080 (TNM)

POTOMAC CONSTRUCTION GROUP, LLC,

Defendant.

MEMORANDUM ORDER

Plaintiff 819D LLC (“819D”) moved for default judgment against Defendant Potomac

Construction Group, LLC (“Potomac”). The Court granted the motion as to Potomac’s liability,

but declined to award damages because 819D did not provide sufficient evidence. 819D files a

supplemental statement seeking to prove these damages. Based on the evidence, the Court will

grant 819D $339,384.13 in compensatory damages.

I.

The Court need only briefly recount the facts, which are set out fully in the prior decision.

See 819D LLC v. Potomac Constr. Grp., LLC, No. 1:19-cv-00080 (TNM), 2020 WL 5518215

(D.D.C. Sept. 14, 2020) (“819D I”). 819D sued Potomac for failure to perform their contract to

renovate condominiums in Washington, D.C. Id. at *1. 819D alleged that Potomac failed to complete its work on the condominiums, falsely represented that it secured a performance bond

required for the work, and failed to use payments from 819D to properly pay subcontractors. Id.

Potomac never responded to the complaint. Id. So 819D sought default judgment against

Potomac under Federal Rule of Civil Procedure 55. Id. at *2.

The Court partially granted 819D’s default judgment motion. The Court found the

allegations sufficient to establish Potomac’s liability for all counts except punitive damages. Id.

at *2–3. But the Court denied without prejudice the damages sought because 819D failed to

provide “sufficient information for the Court to make the necessary determination on the amount

of damages owed.” Id. at *4 (cleaned up). The Court allowed 819D to supplement its motion

with “another submission proving its entitlement to the requested amount of compensatory

damages.” Id. at *5.

819D timely filed its supplemental submission on damages. See Pl.’s Suppl. Statement in

Supp. Default J. Damages (“Pl.’s Statement”), ECF No. 31.

II.

For default judgments, courts make an “independent determination of the sum to be

awarded.” Int’l Painters & Allied Trades Indus. Pension Fund v. R.W. Amrine Drywall Co., 239

F. Supp. 2d 26, 30 (D.D.C. 2002). The moving party “must prove its entitlement to the amount

of monetary damages requested using detailed affidavits or documentary evidence on which the

court may rely.” Boland v. Providence Constr. Corp., 304 F.R.D. 31, 36 (D.D.C. 2014) (cleaned

up). And it must prove “these damages to a reasonable certainty.” Boland v. Elite Terrazzo

Flooring, 763 F. Supp. 2d 64, 68 (D.D.C. 2011).

2 III.

819D seeks these damages: $36,993.27 for costs incurred to perform work assigned to

Potomac, Pl.’s Statement at 1; $56,004.17, which represents the sum Potomac requested for

premium payments on the performance bond it never obtained, id. at 2; $308,395.52 in payments

to Potomac based on fraudulent subcontractor lien releases, id. at 3; $365,016.00 to recover the

statutory warranty bond that the District of Columbia will not release, id.; $372,975.36, which

represents Potomac’s profits on the condominiums project, id. at 3–4; and $27,465.00 in

attorney’s fees and costs, id. at 4. 1 The Court will partially award these damages.

First, 819D claims $36,993.27 in damages “to have work performed that should have

been done by [Potomac] at no cost under its warranty obligations” and “to pay [Potomac] for

work that [Potomac] would not perform without payment.” Id. at 1–2; see also Aff. Supp.

Default J. (“Rubin Aff.”) ¶ 9, ECF No. 31-1 (“819D incurred damages in the amount of

$36,993.27 to pay for the cost to perform contract that [Potomac] had left incomplete and correct

defective contract work installed by [Potomac].”). Such damages are recoverable here because

they “arise directly from the breach itself.” Mercer Mgmt. Consulting, Inc. v. Wilde, 920 F.

Supp. 219, 238 (D.D.C. 1996) (cleaned up). 819D, however, only proves some of these

damages.

As support, 819D offers a list of payments made to third-party vendors, which provides

the date, third-party name, payment amount, and check number for most payments. 2 See Pl.’s

Statement Ex. 1, ECF No. 31-2. But the Court can only confirm some of these payments. Id.

Ex. 2, ECF No. 31-3. 819D submits no proof that it paid $29,971.04 to Potomac or $635.00 to

1 All page citations are to the page numbers that the CM/ECF system generates. 2 Other payments are listed as “Reimbursement” with no check number or have no designation. Pl.’s Statement Ex. 1, ECF No. 31-2. 3 S.P.D. Company, although both payments are included on the list. Id. Exs. 1, 2. Payments the

Court can confirm total $4,955.48. 3 Id. 819D can recover this sum. The Court, however,

declines to award the remaining amount based only on 819D’s internal list. 4 See Mercer Mgmt.

Consulting, 920 F. Supp. at 238 (“[A] plaintiff must provide a reasonable basis upon which

damages may be estimated.”).

Second, 819D asks for $50,285.00, which represents payments to Potomac based on its

false representations that it paid premiums on a performance bond for the condominiums project.

Pl.’s Statement at 2; see also Rubin Aff. ¶ 11. 819D also seeks $5,719.17 it paid in interest on a

loan used to pay Potomac. Id. The Court finds that these payments were “direct consequences”

of Potomac’s fraud and thus are recoverable. Naartex Consulting Corp. v. Watt, 722 F.2d 779,

793 (D.C. Cir. 1983). To support these damages, 819D submits Potomac’s application for

payment to 819D listing the $50,285.00 in purported premium payments. See Pl.’s Statement

Ex. 3 at 3, ECF No. 31-4; see also id. Ex. 4, ECF No. 31-5 (listing bond payment as $50,285.00).

819D confirms that it paid Potomac based on this application. Id. Ex. 5, ECF No. 31-6. And

819D provides the calculation for the interest it paid. Id. Ex. 6, ECF No. 31-7. Based on this

evidence, 819D can recoup the $56,004.17.

Third, 819D seeks to recover $308,395.52 it paid Potomac based on “forged and

fraudulent subcontractor lien releases.” Pl.’s Statement at 2–3; see also Rubin Aff. ¶ 13.

3 There is a discrepancy between the amount noted for Check 102 in the list of payments ($1,368.28) and the amount provided on the copy of Check 102 ($1,315.98). The Court uses the amount on the check to calculate the damages. 4 Indeed, some third-parties included on 819D’s list do not match the entity provided on the checks. Compare Pl.’s Statement Ex. 1 (listing Check 115 as payment to John Morris and Samantha Novick totaling $1,368.50), with id. Ex. 2 at 8 (Copy of Check 115 showing Canal View Holdings LLC as the entity to receive this amount). 4 Potomac would not have received the payments without these false representations. See Pl.’s

Statement Ex. 8 § 12, ECF No. 31-9. As evidence, 819D presents Potomac’s four payment

applications requesting: $128,212.42, $76,140.44, $96,507.50, and $29,971.04, respectively. 5

See id. Ex. 7, ECF No. 31-8. But 819D confirms payment for only the first three applications.

Id. at 7–10 (showing wire transfers and checks in the amounts requested in Potomac’s first three

applications).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mercer Management Consulting, Inc. v. Wilde
920 F. Supp. 219 (District of Columbia, 1996)
Boland v. ELITE TERRAZZO FLOORING, INC.
763 F. Supp. 2d 64 (District of Columbia, 2011)
Boland v. Providence Construction Corp.
304 F.R.D. 31 (District of Columbia, 2014)
Gag Enterprises, Inc. v. Rayford
312 F.R.D. 230 (District of Columbia, 2015)
Combs v. Coal & Mineral Management Services, Inc.
105 F.R.D. 472 (District of Columbia, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
819d LLC v. Pcg Construction Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/819d-llc-v-pcg-construction-group-llc-dcd-2021.