8 O.S.H. Cas.(bna) 1785, 1980 O.S.H.D. (Cch) P 24,702 H. S. Holtze Construction Company v. F. Ray Marshall, Secretary of Labor, United States Department of Labor, and the Occupational Safety and Health Review Commission

627 F.2d 149
CourtCourt of Appeals for the Eighth Circuit
DecidedAugust 8, 1980
Docket79-1957
StatusPublished

This text of 627 F.2d 149 (8 O.S.H. Cas.(bna) 1785, 1980 O.S.H.D. (Cch) P 24,702 H. S. Holtze Construction Company v. F. Ray Marshall, Secretary of Labor, United States Department of Labor, and the Occupational Safety and Health Review Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
8 O.S.H. Cas.(bna) 1785, 1980 O.S.H.D. (Cch) P 24,702 H. S. Holtze Construction Company v. F. Ray Marshall, Secretary of Labor, United States Department of Labor, and the Occupational Safety and Health Review Commission, 627 F.2d 149 (8th Cir. 1980).

Opinion

627 F.2d 149

8 O.S.H. Cas.(BNA) 1785, 1980 O.S.H.D. (CCH) P 24,702
H. S. HOLTZE CONSTRUCTION COMPANY, Petitioner,
v.
F. Ray MARSHALL, Secretary of Labor, United States
Department of Labor, and the Occupational Safety
and Health Review Commission, Respondent.

No. 79-1957.

United States Court of Appeals,
Eighth Circuit.

Submitted June 10, 1980.
Decided Aug. 8, 1980.

I. John Rossi, Des Moines, Iowa, for petitioner.

John R. Bradley, Atty., U. S. Dept. of Labor, Washington, D. C., argued, Carin A. Clauss, Sol. of Labor, Benjamin W. Mintz, Associate Sol., Washington, D. C., on brief, for Occupational Safety and Health.

Allen H. Feldman, Counsel, and John A. Bryson, Acting Asst. Counsel, Washington, D. C., for App. Litigation.

Before ROSS, Circuit Judge, GIBSON, Senior Circuit Judge, and HANSON, District Judge.*

ROSS, Circuit Judge.

This action arises under the Occupational Safety and Health Act of 1970 (Act), 29 U.S.C. § 651 et seq. Petitioner, H. S. Holtze Construction Company (Holtze), is a contractor who at all times relevant to this action was engaged in the construction of three-story buildings in an apartment complex. On October 30, and 31, 1975, a compliance officer of the Occupational Safety and Health Administration inspected this worksite and noted three Holtze employees working on a third floor level of one of the buildings. They were assembling wall sections which were to be erected as the exterior walls for the third floor. The building measured 171 feet by 48 feet and the third floor level was 191/2 feet above the ground.

The employees assembled the wall sections by nailing two by four studs into plates and then stapling celotex and plywood sheets to the studs to provide for exterior coverage of each section. All the materials needed in constructing the wall sections were precut on the ground and raised by a forklift to the third floor for assembling. After the wall sections were assembled, they were pushed out to the edge of the floor, raised into place and nailed into the floor. Two by fours were then angled from these exterior walls to the interior floor to provide temporary bracing for the wall. Before any further work was done on this level, the exterior walls were fully secured by enough interior walls for adequate bracing.

At the time of the inspection, the edge of the floor was unguarded in the area in which the employees worked. The employees would approach the edge of the floor when they were removing lumber from the forklift, nailing the base of the exterior wall sections to the studding, and erecting each wall section. On the basis that Holtze failed to provide fall protection for its employees working on opensided floors, Holtze received a citation alleging that it had committed a serious violation of section 5(a)(2) of the Act, 29 U.S.C. § 654(a)(2) for failure to comply with 29 C.F.R. § 1926.500(d)(1).1

Because Holtze contested the citation, a hearing was held on March 16, 1976, before the Occupational Safety and Health Review Commission's Administrative Law Judge (ALJ). For issues relevant to this appeal, the judge vacated subitem (a) which read "(Third level floor, building B-2, Southeast corner) Open-sided floor 19 feet 6 inches from ground." The ALJ accepted Holtze's argument that the wall, when erected, provided protection equivalent to that of the standard railing, finding that:

The work involved in the building of temporary guardrails in obedience to 29 CFR 1926.500(d)(1), and the subsequent removal of such rails, would, by itself, take more time than the assembling and erection of the exterior walls, thereby increasing the total time spent by respondent's employees at or near the floor edges and resulting in an increase, rather than a decrease, in the exposure to falls.

The Secretary of Labor then petitioned for discretionary review by the full Commission and such review was directed on November 12, 1976. The Commission reinstated the violation under subitem (a) and found that petitioner had neither established a "greater hazard" defense nor a defense of impossibility. There was a dissenting opinion. Petitioner now appeals this determination.

The test by which we view the Commission's findings of fact and inferences is whether such findings were based upon substantial evidence. Danco Construction Company v. OSHRC, 586 F.2d 1243, 1246 (8th Cir. 1978). After a thorough review of the record, we cannot say that substantial evidence supports the Commission's determination.

The Commission would require petitioner to build a guardrail along the 171-foot edge of a building under construction although the reason for the employees working on this third level is to erect an exterior wall which will serve as the functional equivalent of the standard guardrail. The Commission would penalize petitioner for failing to provide this guardrail despite the evidence presented, as pointed out by the dissent, that 1) the wall will take less time to build than the time required to construct and take down the guardrail; 2) the employees who put up and disassemble the guardrail will also be exposed to fall hazards hazards for which other additional safety devices must be devised or erected; and 3) the erected guardrail would provide meager protection, since it cannot be braced from the third floor interior without preventing construction of the wall and, lacking such bracing, will be able to withstand little outward force.

While we are mindful of the broad scope and remedial purposes of the Occupational Safety and Health Review Act, we are of the opinion that some modicum of reasonableness and common sense is implied. There is a point at which the impracticality of the requirement voids its effectiveness and that point has been reached when to erect an entire wall, a project said to take approximately two hours, petitioner must begin an endless spiral of tasks consisting of abatement activities which necessitate further protective devices, i. e., guardrail to erect wall, scaffold to erect guardrail, safety devices to erect scaffold, etc. We agree with the dissent that some demarcation line must be drawn between that which is genuinely aimed at the promotion of safety and health and that which, while directed at such aims, is so imprudent as to be unreasonable.

On appeal, the Secretary argues that in order to plead the "greater hazard" defense, petitioner must show: 1) that the hazards of compliance are greater than the hazards of noncompliance, 2) that alternative means of protecting employees are unavailable; and 3) that a variance application under section 6(d) of the Act would be inappropriate. Such criteria and proof as structured by the Commission have been recently recognized by the Third and Ninth Circuits. See Noblecraft Industries, Inc. v. Secretary of Labor, 614 F.2d 199 (9th Cir. 1980) and General Electrical Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
627 F.2d 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/8-osh-casbna-1785-1980-oshd-cch-p-24702-h-s-holtze-ca8-1980.