5640 ST. CLAUDE, LLC * NO. 2023-CA-0659
VERSUS * COURT OF APPEAL
DURR HEAVY * FOURTH CIRCUIT CONSTRUCTION, LLC AND THE CITY OF NEW ORLEANS * STATE OF LOUISIANA
*******
APPEAL FROM CIVIL DISTRICT COURT, ORLEANS PARISH NO. 2019-02554, DIVISION “F-14” Honorable Jennifer M. Medley ****** JUDGE SANDRA CABRINA JENKINS ****** (Court composed of Judge Daniel L. Dysart, Judge Sandra Cabrina Jenkins, Judge Dale N. Atkins)
Luis Etienne Balart Jarred G. Trauth Christopher K. Ulfers Sara B. Kuebel JONES WALKER LLP 201 St. Charles Avenue, 48th Floor New Orleans, LA 70170
COUNSEL FOR DEFENDANT/APPELLEE
Renee Goudeau Corwin M. St. Raymond Deisha LaGarde Donesia D. Turner CITY ATTORNEY CITY OF NEW ORLEANS 1300 Perdido St., 5E03 New Orleans, LA 70112
COUNSEL FOR DEFENDANT/APPELLANT
AMENDED IN PART; AFFIRMED AS AMENDED; ANSWER TO APPEAL DENIED MAY 10, 2024 SCJ DLD DNA
The City of New Orleans (the “City”) appeals the July 5, 2023 judgment of
the trial court, finding the City ninety percent at fault, and Durr Heavy
Construction, LLC (“Durr”) ten percent at fault for plaintiff, 5640 St. Claude,
LLC’s (“St. Claude”) damages. For the following reasons, we affirm the trial
court’s allocation of fault.
FACTS AND PROCEDURAL HISTORY
This action involves the demolition of property located at 5640 St. Claude
Avenue in New Orleans, Louisiana (“St. Claude Property”). The property at issue
was acquired by St. Claude through its principal, John Spencer (“Mr. Spencer”), at
a Sheriff’s sale in June 2017. The property was determined to be in imminent
danger of collapse and the City issued a notice of emergency demolition. The City
contracted with Durr Heavy Contruction, LLC (“Durr”) to conduct the demolition.
Mr. Spencer became aware of the notice of emergency demolition and
emailed Chad Dyer (“Mr. Dyer”), the director of code enforcement for the City,
1 notifying of the steps taken to renovate the property. Mr. Dyer informed Mr.
Spencer that demolition of the property ceased and requested a timeline for the
renovations.
The following is a chronological timeline of the pre-incident events:
• On April 10, 2018, Winston Reid (“Mr. Reid”, the deputy director of code enforcement emailed Durr’s project manager, John R. Ovella (“Mr. Ovella”), advising that the property should be in the “Do Not Demolish” category for emergency demolition.
• On April 17, 2018, St. Claude submitted an application for a structural renovation permit.
• Deborah Champagne (“Ms. Champagne”) replaced Mr. Ovella as the project manager.
• In May of 2018, a meeting was held between the City and Durr.
• On May 9, 2018, Ms. Champagne emailed Mr. Reid a list of properties for demolition. The St. Claude property was on the list indicating that a demolition permit was issued.
• On May 9, 2018, Mr. Reid responded to Ms. Champagne’s email stating that he would take a look at the list.
• On June 5, 2018, Ms. Champagne emailed Mr. Reid advising that Durr had permits for six properties scheduled for demolition, including the St. Claude property. She further asked that he advise her whether there were any hold ups on any of the properties she listed.
• On June 27, 2018, Mr. Reid texted Pay Layus (“Mr. Layus”), Durr’s on-site project manager, requesting confirmation of the location Durr was working that day. Mr. Layus responded “5640 [S]t. Claude,” the property at issue.
• The property was demolished on June 27, 2018.
In March 2019, St. Claude filed a petition for damages against Durr and the
City. St. Claude alleged that Durr, operating as the contractor for the City,
wrongfully demolished its property. A bench trial was held on March 28, 2023. On
2 July 5, 2023, the trial court signed a judgment in favor of St. Claude and against
the City and Durr, allocating ninety percent fault to the City and ten percent fault
to Durr. The judgment awarded St. Claude $29,000.00 for loss of value of
property, ordering $26,100.00 be paid by the City and $2,900.00 be paid by Durr.
The judgment further awarded St. Claude $34,410.00 for loss of monetary
investment in the development of the property, ordering $30,969.00 be paid by the
City and $3,441.00 be paid by Durr. The City filed a motion for suspensive appeal.
This appeal follows.
DISCUSSION
Preliminary Note
We first address the trial court’s clerical error in the July 5, 2023 judgment.
The judgment in pertinent part:
IT IS FURTHER ORDERED, ADJUDGED, AND DECREED that Judgment be entered in favor of Plaintiff, 5640 St. Claude, LLC, and against Defendants, Durr Heavy Construction, LLC, and the City of New Orleans, in which Plaintiff, 5640 St. Claude, LLC’s, Petition for Damages, is hereby GRANTED and Plaintiff, 5640 St. Claude, LLC, is entitled to an award of TWENTY- NINE THOUSAND DOLLARS AND ZERO CENTS ($29,000.00) for loss of value of property.
IT IS FURTHER ORDERED, ADJUDGED, AND DECREED that the amount of thirty-four thousand and four-hundred and ten dollars is to be reduced by Defendant, the City of New Orleans’s appropriation of fault of NINETY (90) PERCENT, and thus Plaintiff, 5640 St. Claude, LLC, is awarded TWENTY-SIX THOUSAND ONE HUNDRED DOLLARS AND ZERO CENTS ($26,100.00), with judicial interest from date of demand, costs to be assessed separately on either party’s motion to tax costs.
IT IS FURTHER ORDERED, ADJUDGED, AND DECREED that the amount of thirty-four thousand and four-hundred and ten dollars is to be reduced by Defendant, Durr Heavy Construction, LLC’s appropriation of fault of TEN (10) PERCENT,
3 and thus Plaintiff, 5640 St. Claude, LLC, is awarded TWO- THOUSAND NINE-HUNDRED DOLLARS AND ZERO CENTS ($2,900.00), with judicial interest from date of demand, costs to be assessed separately on either party’s motion to tax costs.
(emphasis in original) (italics added).
The trial court awarded St. Claude $29,000.00 for loss of value to property,
however, in its allocation of fault, wrote “thirty-four thousand and four-hundred
and ten dollars” instead of “twenty-nine thousand dollars and zero cents.” The
calculations within the judgment reflect that $29,000.00 is the appropriation of
fault assigned to the defendants.
Louisiana Code of Civil Procedure Article 1951 allows the trial court to
amend clerical errors in its judgment.1 Nonetheless, “the court of appeal may
correct clerical errors in the judgment of a trial court.” Succession of Rachal, 2021-
0621, p. 5 (La. App. 4 Cir. 6/8/22) 342 So.3d 1012, 1017-18 (citing Moss v. Moss,
2005-455, p. 5 (La. App. 3 Cir. 11/2/05), 916 So.2d 455, 458). Accordingly, we
amend the July 5, 2023 judgment allocating the percentage of fault and damages
for 5640 St. Claude, to reflect the amount of twenty-nine thousand dollars and zero
cents ($29,000.00).
Allocation of Fault by the Trial Court
In its sole assignment of error, the City asserts that the trial court erred in the
allocation of fault between the two defendants by allocating ten percent fault to
Durr and ninety percent fault to the City.
1 Louisiana Code of Civil Procedure Article 1951 provides in pertinent part that “[o]n motion of
the court or any party, a final judgment may be amended at any time to alter the phraseology of the judgment or to correct deficiencies in the decretal language or errors of calculation.”
4 Louisiana Civil Code Article 2323 governs comparative fault and directs in
pertinent part that “[i]n any action for damages where a person suffers injury,
death, or loss, the degree or percentage of fault of all persons causing or
Free access — add to your briefcase to read the full text and ask questions with AI
5640 ST. CLAUDE, LLC * NO. 2023-CA-0659
VERSUS * COURT OF APPEAL
DURR HEAVY * FOURTH CIRCUIT CONSTRUCTION, LLC AND THE CITY OF NEW ORLEANS * STATE OF LOUISIANA
*******
APPEAL FROM CIVIL DISTRICT COURT, ORLEANS PARISH NO. 2019-02554, DIVISION “F-14” Honorable Jennifer M. Medley ****** JUDGE SANDRA CABRINA JENKINS ****** (Court composed of Judge Daniel L. Dysart, Judge Sandra Cabrina Jenkins, Judge Dale N. Atkins)
Luis Etienne Balart Jarred G. Trauth Christopher K. Ulfers Sara B. Kuebel JONES WALKER LLP 201 St. Charles Avenue, 48th Floor New Orleans, LA 70170
COUNSEL FOR DEFENDANT/APPELLEE
Renee Goudeau Corwin M. St. Raymond Deisha LaGarde Donesia D. Turner CITY ATTORNEY CITY OF NEW ORLEANS 1300 Perdido St., 5E03 New Orleans, LA 70112
COUNSEL FOR DEFENDANT/APPELLANT
AMENDED IN PART; AFFIRMED AS AMENDED; ANSWER TO APPEAL DENIED MAY 10, 2024 SCJ DLD DNA
The City of New Orleans (the “City”) appeals the July 5, 2023 judgment of
the trial court, finding the City ninety percent at fault, and Durr Heavy
Construction, LLC (“Durr”) ten percent at fault for plaintiff, 5640 St. Claude,
LLC’s (“St. Claude”) damages. For the following reasons, we affirm the trial
court’s allocation of fault.
FACTS AND PROCEDURAL HISTORY
This action involves the demolition of property located at 5640 St. Claude
Avenue in New Orleans, Louisiana (“St. Claude Property”). The property at issue
was acquired by St. Claude through its principal, John Spencer (“Mr. Spencer”), at
a Sheriff’s sale in June 2017. The property was determined to be in imminent
danger of collapse and the City issued a notice of emergency demolition. The City
contracted with Durr Heavy Contruction, LLC (“Durr”) to conduct the demolition.
Mr. Spencer became aware of the notice of emergency demolition and
emailed Chad Dyer (“Mr. Dyer”), the director of code enforcement for the City,
1 notifying of the steps taken to renovate the property. Mr. Dyer informed Mr.
Spencer that demolition of the property ceased and requested a timeline for the
renovations.
The following is a chronological timeline of the pre-incident events:
• On April 10, 2018, Winston Reid (“Mr. Reid”, the deputy director of code enforcement emailed Durr’s project manager, John R. Ovella (“Mr. Ovella”), advising that the property should be in the “Do Not Demolish” category for emergency demolition.
• On April 17, 2018, St. Claude submitted an application for a structural renovation permit.
• Deborah Champagne (“Ms. Champagne”) replaced Mr. Ovella as the project manager.
• In May of 2018, a meeting was held between the City and Durr.
• On May 9, 2018, Ms. Champagne emailed Mr. Reid a list of properties for demolition. The St. Claude property was on the list indicating that a demolition permit was issued.
• On May 9, 2018, Mr. Reid responded to Ms. Champagne’s email stating that he would take a look at the list.
• On June 5, 2018, Ms. Champagne emailed Mr. Reid advising that Durr had permits for six properties scheduled for demolition, including the St. Claude property. She further asked that he advise her whether there were any hold ups on any of the properties she listed.
• On June 27, 2018, Mr. Reid texted Pay Layus (“Mr. Layus”), Durr’s on-site project manager, requesting confirmation of the location Durr was working that day. Mr. Layus responded “5640 [S]t. Claude,” the property at issue.
• The property was demolished on June 27, 2018.
In March 2019, St. Claude filed a petition for damages against Durr and the
City. St. Claude alleged that Durr, operating as the contractor for the City,
wrongfully demolished its property. A bench trial was held on March 28, 2023. On
2 July 5, 2023, the trial court signed a judgment in favor of St. Claude and against
the City and Durr, allocating ninety percent fault to the City and ten percent fault
to Durr. The judgment awarded St. Claude $29,000.00 for loss of value of
property, ordering $26,100.00 be paid by the City and $2,900.00 be paid by Durr.
The judgment further awarded St. Claude $34,410.00 for loss of monetary
investment in the development of the property, ordering $30,969.00 be paid by the
City and $3,441.00 be paid by Durr. The City filed a motion for suspensive appeal.
This appeal follows.
DISCUSSION
Preliminary Note
We first address the trial court’s clerical error in the July 5, 2023 judgment.
The judgment in pertinent part:
IT IS FURTHER ORDERED, ADJUDGED, AND DECREED that Judgment be entered in favor of Plaintiff, 5640 St. Claude, LLC, and against Defendants, Durr Heavy Construction, LLC, and the City of New Orleans, in which Plaintiff, 5640 St. Claude, LLC’s, Petition for Damages, is hereby GRANTED and Plaintiff, 5640 St. Claude, LLC, is entitled to an award of TWENTY- NINE THOUSAND DOLLARS AND ZERO CENTS ($29,000.00) for loss of value of property.
IT IS FURTHER ORDERED, ADJUDGED, AND DECREED that the amount of thirty-four thousand and four-hundred and ten dollars is to be reduced by Defendant, the City of New Orleans’s appropriation of fault of NINETY (90) PERCENT, and thus Plaintiff, 5640 St. Claude, LLC, is awarded TWENTY-SIX THOUSAND ONE HUNDRED DOLLARS AND ZERO CENTS ($26,100.00), with judicial interest from date of demand, costs to be assessed separately on either party’s motion to tax costs.
IT IS FURTHER ORDERED, ADJUDGED, AND DECREED that the amount of thirty-four thousand and four-hundred and ten dollars is to be reduced by Defendant, Durr Heavy Construction, LLC’s appropriation of fault of TEN (10) PERCENT,
3 and thus Plaintiff, 5640 St. Claude, LLC, is awarded TWO- THOUSAND NINE-HUNDRED DOLLARS AND ZERO CENTS ($2,900.00), with judicial interest from date of demand, costs to be assessed separately on either party’s motion to tax costs.
(emphasis in original) (italics added).
The trial court awarded St. Claude $29,000.00 for loss of value to property,
however, in its allocation of fault, wrote “thirty-four thousand and four-hundred
and ten dollars” instead of “twenty-nine thousand dollars and zero cents.” The
calculations within the judgment reflect that $29,000.00 is the appropriation of
fault assigned to the defendants.
Louisiana Code of Civil Procedure Article 1951 allows the trial court to
amend clerical errors in its judgment.1 Nonetheless, “the court of appeal may
correct clerical errors in the judgment of a trial court.” Succession of Rachal, 2021-
0621, p. 5 (La. App. 4 Cir. 6/8/22) 342 So.3d 1012, 1017-18 (citing Moss v. Moss,
2005-455, p. 5 (La. App. 3 Cir. 11/2/05), 916 So.2d 455, 458). Accordingly, we
amend the July 5, 2023 judgment allocating the percentage of fault and damages
for 5640 St. Claude, to reflect the amount of twenty-nine thousand dollars and zero
cents ($29,000.00).
Allocation of Fault by the Trial Court
In its sole assignment of error, the City asserts that the trial court erred in the
allocation of fault between the two defendants by allocating ten percent fault to
Durr and ninety percent fault to the City.
1 Louisiana Code of Civil Procedure Article 1951 provides in pertinent part that “[o]n motion of
the court or any party, a final judgment may be amended at any time to alter the phraseology of the judgment or to correct deficiencies in the decretal language or errors of calculation.”
4 Louisiana Civil Code Article 2323 governs comparative fault and directs in
pertinent part that “[i]n any action for damages where a person suffers injury,
death, or loss, the degree or percentage of fault of all persons causing or
contributing to the injury, death, or loss shall be determined.” La. C.C. art.
2323(A). “A trial court’s allocation of fault is a question of fact.” Preston v.
Certain Underwriters at Lloyd’s London, 2023-0277, p. 2 (La. App. 4 Cir. 1/22/24)
381 So.3d. 827, 831 (citing Amos v. Taylor, 51,595, p. 3 (La. App. 2 Cir. 9/27/17),
244 So.3d 749, 752).
“The trier of fact is owed great deference in its allocation of fault.” Goldsby
v. Blocker Through Dep’t of Transp. & Dev., 51,584, p. 5 (La. App. 2 Cir.
9/27/17), 244 So.3d 703, 710 (citing Clement v. Frey, 1995-1119, (La. 01/16/96),
666 So.2d 607). The trial court’s factual finding are reviewed under the manifest
error/clearly wrong standard of review. Gordon v. Gordon, 2016-0008, p. 3, (La.
App. 4 Cir. 6/8/2016) 195 So.3d 687, 688. If a conflict in the testimony exist,
“reasonable evaluations of credibility and reasonable inferences of fact should not
be disturbed upon review, even though the appellate court may feel that its own
evaluations and inferences are as reasonable.” Sewell v. Sewerage & Water Bd. of
New Orleans, 2019-0268, p. 4 (La. App. 4 Cir. 1/20/21), 313 So.3d 333, 339
(quoting Rosell v. ESCO, 549 So.2d 840, 844 (La. 1989)). On the other hand,
“[w]here there are two permissible views of the evidence, the factfinder’s choice
between them cannot be manifestly erroneous or clearly wrong.” Id. Therefore,
“the issue to be resolved by the appellate court is not whether the trier of fact was
5 right or wrong, but whether the factfinder’s conclusion was reasonable.” Id. at pp.
4-5 (quoting Stobart v. State through Dep’t of Transp. and Dev., 617 So.2d 880,
882 (La. 1993)). In considering the nature of each party’s conduct, this Court has
found: Some of the factors that may influence the degree of fault assigned are: 1) whether the conduct resulted from inadvertence or involved an awareness of the danger; 2) how great a risk was created by the conduct; 3) the significance of what was sought by the conduct; 4) the capacities of the actor, whether superior or inferior; and 5) any extenuating circumstances which might require the actor to proceed in haste, without proper thought.
Wilson v. Veolia Transp. Servs., Inc., 2015-0998, p. 4 (La. App. 4 Cir. 4/13/16),
192 So.3d 245, 248 (citing Gray v. Louisiana Downs, 585 So.2d 1238, 1242 (La.
App. 2 Cir.1991)).
The City contends that the evidence established that the property was
wrongfully demolished based upon Durr’s disregard for the City’s explicit
instructions not to demolish the property and Durr’s lack of communication and
transition between project managers. The City further argues that Durr was
instructed to not demolish the property unless formal notice in writing was given.
Durr counters that during a meeting held on May 9, 2018, Hillary Carrere,
the City’s demolition coordinator, provided Durr with a handwritten list of
properties to be demolished and the property at issue was included on the list. Durr
argues that it advised the City on three separate occasions that it was proceeding
with demolition of the property as instructed in the May 9, 2018 meeting. Durr
further argues it should be free from fault based on the City not rescinding the
imminent danger of collapse notice.
6 At trial, Robert Wooderson (“Mr. Wooderson”), the corporate
representative of Durr, testified that Durr was notified by the City to place the
subject property on the “Do Not Demolish” category. Mr. Wooderson confirmed
that once the City notified Durr of the status change, either Ms. Champagne or Mr.
Ovella was responsible for ensuring that the change was noted. Mr. Wooderson
submitted that Durr tracked the properties assigned for demolition with a
spreadsheet and Ms. Champagne worked off the same spreadsheet as her
predecessor, Mr. Ovella. However, Ms. Champagne testified that she did not work
off of the same spreadsheet as Mr. Ovella and none of his lists were transitioned to
her.
Ms. Champagne also testified that she attended the May 9, 2018 meeting and
Mr. Carrere provided a handwritten list of properties in which she instructed to
demolish. Ms. Champagne confirmed that Durr no longer had a copy of the
handwritten list. Ms. Champagne testified that she emailed Mr. Reid a list of
nineteen properties that Durr was proceeding to demolish, and she expected the
City to cross-check the properties listed to inform her of any property that should
not be included in the demolition. Ms. Champagne confirmed that the City did not
email a formal notice to demolish the subject property, and Durr has not previously
demolished a property based on a handwritten list.
Mr. Reid testified that his April 10, 2018 email to Mr. Ovella was an official
notice to suspend all operations to demolish the property. He also testified that the
May 9, 2018 meeting was primarily for budget, billing, invoicing, and the
7 outstanding terms of costs. Mr. Reid provided that he did not recall responding to
Ms. Champagne’s email inquiring whether there were any issues with the
properties she listed for demolition. Mr. Reid testified that Mr. Carrere kept his
own list of “Do Not Demolish” properties. He also confirmed that the City has
never used a handwritten list to order demolition of properties, and did not
authorize Durr with a handwritten list to demolish the subject property.
Durr’s Allocation of Fault
First, we address whether the trial court’s allocation of fault to Durr was
manifestly erroneous. The City contends that Durr should be allocated a greater
percentage of fault as the evidence shows that the property was wrongfully
demolished based upon Durr’s disregard for the City’s instructions not to demolish
the property and Durr’s lack of transition between project managers to properly
manage its records.
During the transitional phase of Durr’s project managers, the spreadsheets
and lists were not transferred to Ms. Champagne. Thus, if Mr. Ovella did in fact
place the property on a “Do Not Demolish” list as instructed by the City, Ms.
Champagne had no knowledge of it. While it is undisputed that Durr did not have a
solidified system of managing properties in which demolition was postponed, there
were numerous instances where Durr took steps to confirm that the property was to
be demolished. In addition, Durr never received a notice from the City rescinding
the notice of emergency demolition. Accordingly, we find the trial court was not
manifestly erroneous in allocating ten percent fault to Durr.
8 The City’s Allocation of Fault
Next, we address the City’s allocation of fault. The City issued a notice of
emergency demolition of St. Claude’s property and subsequently contracted with
Durr for the demolition. Upon instructing Durr to place the property on the “Do
Not Demolish” list, the City bore a greater responsibility for maintaining and
verifying properties placed on hold for demolition. The City was also responsible
for rescinding the imminent danger of collapse and notice of emergency
demolition.
The City’s demolition coordinator and deputy director of code enforcement
kept separate “Do Not Demolish” lists. Further, when Ms. Champagne emailed Mr.
Reid a list of properties that were scheduled to be demolished, Mr. Reid failed to
respond that the property at issue should not be on the list for demolition. Mr. Reid
also failed to inform Durr that the property should not be demolished after receipt
of the June 27, 2018 text message from Durr’s on-site project manager that Durr
was at the St. Claude property.
In light of the particular facts of the case and the record before us, we find
that the trial court was not manifestly erroneous in assigning ninety percent fault to
the City.
Answer to Appeal
Durr filed an Answer to Appeal requesting that the judgement be modified
to allocate one hundred percent fault to the City. Based on our finding that
9 the trial court did not err in its allocation of fault, we deny Durr’s Answer to
Appeal.
DECREE
For the foregoing reasons, we make a clerical amendment to that portion of
the July 5, 2023 judgment allocating the percentage of fault and damages for 5640
St. Claude, to reflect the amount of twenty-nine thousand dollars and zero cents
($29,000.00). The judgment is affirmed in all other respects.
AMENDED IN PART; AFFIRMED AS AMENDED; ANSWER TO APPEAL DENIED