5500 Coastal Highway Ltd. Partnership v. Electrical Equipment Co.

505 A.2d 533, 305 Md. 532, 1986 Md. LEXIS 198
CourtCourt of Appeals of Maryland
DecidedMarch 7, 1986
Docket100, 101, September Term, 1985
StatusPublished
Cited by4 cases

This text of 505 A.2d 533 (5500 Coastal Highway Ltd. Partnership v. Electrical Equipment Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
5500 Coastal Highway Ltd. Partnership v. Electrical Equipment Co., 505 A.2d 533, 305 Md. 532, 1986 Md. LEXIS 198 (Md. 1986).

Opinion

SMITH, Judge.

In this case we shall hold that suppliers of materials to a modular home builder in Delaware are entitled to mechanics’ liens on a building constructed of those modules in Ocean City, Maryland.

Electrical Equipment Company, Inc., and Noland Company each filed mechanics’ lien claims in Worcester County against 5500 Coastal Highway Limited Partnership and its *534 building known as Tiffanie By The Sea Condominium. The cases were consolidated for the purpose of decision in the Circuit Court for Worcester County. The trial judge in each case directed the establishment of a lien. 5500 Coastal Highway Limited Partnership appealed to the Court of Special Appeals in each case. On our own motion we directed that writs of certiorari be issued prior to argument in the intermediate appellate court in order that we might address the important public question here presented. We ordered that the two cases be argued the same day. We consolidate the cases for the purpose of our opinion.

Appellant takes no issue on appeal with the findings of fact of the trial judge. Accordingly, we set forth the facts as found by the trial judge:

“In each case, the owner of property in Ocean City, Maryland, the Defendant entered into a contract with a modular home builder in Delaware, Virginia Homes, for Virginia Homes to build and deliver to Defendant’s Maryland building site modular units which were then to be stacked one on top of another and therefore to be incorporated into a condominium (or multi-unit) project known and advertised as ‘Tiffanie By The Sea’. Upon the creation of the contract, Virginia Homes (not a party to the instant cases and allegedly in a state of bankruptcy) then contracted with materialmen to supply materials for the construction of the ‘Tiffanie’ modules at the Virginia Homes Delaware plant. The Plaintiffs in these cases were two of such materialmen. ... Electrical Equipment Company, allegedly supplied electrical equipment which was incorporated in the units. ... Noland Company, allegedly supplied plumbing, etc., equipment which was incorporated into the modules.
“In each case most, if not all, of the Plaintiff's invoices to Virginia Homes had indicated on their face that the materials were being supplied for the specific project ‘Tiffanie By The Sea’. Additionally, there was uncontradicted testimony that the ‘Tiffanie By The Sea’ project was the only modular project being constructed in the *535 Virginia Homes Delaware plant at the time during which the materials were delivered. ... Electrical Equipment Company, Inc., presented evidence that they visited the Delaware plant and observed the ‘Tiffanie’ modules being constructed from material that included Electrical’s materials shipped for the ‘Tiffanie’ project. They further testified that they visited the modules at ‘Tiffanie By The Sea’ after they had been delivered to the Ocean City, Maryland site and had seen the material they sold to Virginia Homes for the ‘Tiffanie’ project actually in the ‘Tiffanie’ units at the Maryland construction site.
“... Noland Company presented evidence that its employee and agent, a Mr. Willen, testified that he was approached by Virginia Homes to give a quote on the ‘Tiffanie’ project, and that eventually Noland Company supplied materials for the ‘Tiffanie’ project to the Delaware plant of Virginia Homes for incorporation into the ‘Tiffanie’ modules. He testified that on his visits to the Delaware plant of Virginia Homes he observed the material shipped by Noland Company actually being incorporated into the modules. He testified that as the modules came off the assembly line they were on wheels and towed or driven directly to the construction site in Maryland. He testified that he had visited the Maryland construction site and verified that some of the units that he had seen built in the Delaware plant were actually on the site of ‘Tiffanie By The Sea’. On cross-examination he revealed that he had followed three (3) units (two of which he had been through while they were on the Delaware assembly line) from Virginia Homes’ plant to the ‘Tiffanie By The Sea’ project in Ocean City.”

The judge concluded:

“Accordingly, the Court holds that where there is a prior contract between a modular home manufacturer, (whose factory is in or out of state), and an owner of Maryland real property, to which and on which the modules are to be delivered and erected, and the manufacturer produces the modules pursuant to the contract with *536 the owner and where the materialmen furnish materials pursuant to specific quotes on the project and invoices them to the project, said materialmen have the right to claim a lien under the statute. In the event however, that such a manufacturer produces modules for stock purposes and later sells modules under contracts made after the modules are constructed a materialman’s lien would not lie against the real property of such subsequent purchaser.”

Some idea of what took place here may be gleaned from the testimony of a witness for Noland who said:

“I actually saw, on several occasions, on two different occasions that I know of, I saw the units actually being lifted off of the trailers that have come from Georgetown [, Delaware,] and lifted and being put on the concrete pads on the job site.”

Maryland Code (1974) § 9-102, Real Property Article, provides in pertinent part relative to mechanics’ liens:

“(a) Buildings. Every building erected ... is subject to establishment of a lien in accordance with this subtitle for the' payment of all debts, without regard to the amount, contracted for work done for or about the building and for materials furnished for or about the building, including the drilling and installation of wells to supply water, the construction or installation of any swimming pool, the sodding, seeding or planting in or about the premises of any shrubs, trees, plants, flowers or nursery products, and the grading, filling, landscaping, and paving of the premises.”

The lien exists purely by virtue of statute. Himmighoefer v. Medallion Industries, Inc., 302 Md. 270, 278, 487 A.2d 282, 286 (1985); Freeform Pools v. Strawbridge, 228 Md. 297, 301, 179 A.2d 683, 685 (1962). It follows, therefore, that there can be no lien for anything which does not fall within the statutory provision. This Court has no power to extend the mechanic’s lien law to cases beyond its obvious design and plain requirements. Caton Ridge v. *537 Bonnett, 245 Md. 268, 272, 225 A.2d 853, 855 (1967). Despite these restrictions, however, the statute is to be construed in favor of those for whom it was enacted. Caton Ridge, 245 Md. at 272, 225 A.2d at 855.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: Walker and Walker
248 A.3d 981 (Court of Appeals of Maryland, 2021)
Jacksonville MacHine and Repair, Inc. v. Kent Sand and Gravel, LLC
923 A.2d 1023 (Court of Special Appeals of Maryland, 2007)
Westpointe Plaza II Ltd. Partnership v. Kalkreuth Roofing & Sheet Metal, Inc.
675 A.2d 571 (Court of Special Appeals of Maryland, 1996)
Atlantic Sea-Con, Ltd. v. Robert Dann Co.
582 A.2d 981 (Court of Appeals of Maryland, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
505 A.2d 533, 305 Md. 532, 1986 Md. LEXIS 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/5500-coastal-highway-ltd-partnership-v-electrical-equipment-co-md-1986.