328 Barry Avenue, LLC,Appellant v. Nolan Properties Group, LLC, and third party v. Carciofini Company, third party Marvin Windows, Inc., third party Minuti-Ogle Co., Inc., third party R.T.L Construction, Inc., third party Respondent,Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party

Supreme Court of Minnesota·Decided November 25, 2015·No. A14-724·Published

Opinion

STATE OF MINNESOTA

IN SUPREME COURT

A14-0724

Court of Appeals Gildea, C.J.

Took no part, Hudson, J.

328 Barry Avenue, LLC,

Appellant,

vs. Filed: November 25, 2015 Office of Appellate Courts Nolan Properties Group, LLC, defendant and third party plaintiff,

Respondent,

vs.

Carciofini Company, third party defendant,

Respondent,

Marvin Windows, Inc., third party defendant,

Respondent,

Minuti-Ogle Co., Inc., third party defendant,

Respondent,

R.T.L Construction, Inc., third party defendant,

Respondent,

Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party defendant,

Respondent.

J. Robert Keena, Joseph M. Barnett, Hellmuth & Johnson, PLLC, Edina, Minnesota, for appellant.

Bradley D. Fisher, Fisher, Bren & Sheridan, LLP, Minneapolis, Minnesota, for respondent Nolan Properties Group, LLC.

Cara C. Passaro, Murphy & Passaro, PA, Mendota Heights, Minnesota, for respondent Carciofini Company.

Michael E. Obermueller, Winthrop & Weinstine, P.A., Minneapolis, Minnesota, for respondent Marvin Windows, Inc.

Justin P. Short, Kerry C. Raymond, Best & Flanagan LLP, Minneapolis, Minnesota, for respondent Minuti-Ogle Co., Inc.

Neal J. Robinson, Coon Rapids, Minnesota, for respondent R.T.L. Construction, Inc.

SYLLABUS

1. Under the plain language of Minn. Stat. § 541.051, subd. 1 (2014), the statute of limitations for claims of defective construction can begin to run before substantial completion of the construction.

2. The building owner’s assertion that a leak had been remedied, when taken in the context of an ongoing construction project and the absence of record evidence of ongoing water problems, created a genuine issue of material fact as to when the injury was discovered under Minn. Stat. § 541.051, subd. 1.

Affirmed in part, reversed in part, and remanded.

OPINION

GILDEA, Chief Justice.

The questions presented in this case concern the interpretation and application of the 2-year statute of limitations in Minn. Stat. § 541.051, subd. 1(a) (2014), which applies to actions “arising out of the defective and unsafe condition of an improvement to real property.” Appellant 328 Barry Avenue, LLC (328 LLC) used respondent Nolan Properties Group, LLC (NPG) as the general contractor for the construction of a building. The building had problems with water intrusion. 328 LLC brought an action claiming that NPG’s actions as general contractor were negligent. The district court dismissed the action as untimely under Minn. Stat. § 541.051, subd. 1(a). The court of appeals affirmed. Although we agree with the court of appeals that the plain language of Minn. Stat. § 541.051, subd. 1 does not require that construction be substantially complete to start the running of the statute of limitations, we reverse in part and remand because we conclude that there is a genuine issue of material fact as to when 328 LLC discovered its injury.

In 2008, construction began on a three-story commercial building located in Wayzata, Minnesota. The building site belonged to 328 Barry Avenue, LLC, a company solely owned by John Nolan. 328 LLC selected NPG, another company solely owned by

Nolan, to serve as the general contractor during construction of the building. 1 According to 328 LLC, NPG’s duties as general contractor included hiring and supervising subcontractors and selecting construction materials. NPG did not personally perform any of the construction work, but claims that it was qualified to select, hire, and supervise subcontractors and ensure that the subcontractors’ work was completed according to the contract documents. NPG did not have a written contract with 328 LLC, but NPG did enter into written contracts with the subcontractors on the project, including respondents Carciofini Company, Marvin Windows, Inc., Minuti-Ogle Co., Inc., and R.T.L Construction, Inc.

In October 2009, during what Nolan referred to as the “punch list” phase of construction, NPG contacted Minuti-Ogle Co. (MOC), the stucco contractor. NPG asked MOC about a leak around an east elevation window, indicating that there was “some water” on the property. A representative from MOC visited the property and, after observing “soaking wet” insulation and water “coming out by the window,” told NPG, “I think you’ve got a window issue.” A few days later, NPG again contacted MOC regarding leakage at the same location. At NPG’s request, the same MOC representative returned to the property and applied small amounts of silicone sealant to the window corners, although he warned NPG that he feared that absence of sealant was not the issue.

On October 30, 2 weeks after his previous visit, the MOC representative received an email from NPG asking him to return to the property because water was again entering

1 The parties make no argument regarding the corporate formalities of Nolan’s companies, and therefore issues about any identity of interest between 328 LLC and NPG are not before us.

around the same window. In early November 2009, the MOC representative and two representatives of NPG performed a garden-hose “spray test” to determine the location of the leak. The test revealed water “slowly seep[ing] in on the right side of the [same] window.” Although MOC testified that it performed no work during this visit to repair or correct the issue, and NPG produced no specific evidence that NPG or any subcontractor attempted to repair the leak, the record does not reflect that there were any water leaks around the window or in other parts of the building between November 2009 and August 2010. Nolan, testifying on behalf of NPG, stated that “whatever [the subcontractors] did, they addressed [the leak] to [NPG’s] satisfaction because I didn’t hear anything, I didn’t see anything . . . and we paid everybody. That issue was solved and done.” Nolan testified that 328 LLC observed no leaks or water intrusion damage from November 2009 until August 2010.

The City of Wayzata issued a certificate of occupancy for the building in January 2010, although parts of the building were still unfinished. The parties agree, however, that construction was substantially complete by May 2010 when 328 LLC began to occupy the building for commercial purposes.

In August 2010, 328 LLC noticed water on the floor of the building. NPG again contacted the MOC representative who had observed the window leak in 2009, stating that “[t]his problem with water leaking around the windows needs to be solved.” Upon arrival at the property, the MOC representative noticed “water in the same spot” as the previous fall, and, as he said he did earlier, suggested that NPG “get [the] window tested.”

Throughout 2011 and 2012, NPG and 328 LLC hired a number of experts to investigate the extent and cause of the water damage to the building. A report released in June 2011 documented window leaks at multiple east and west elevation locations, the presence of “unspecified” building materials, and installation of materials contrary to project specifications. Invasive cuts into the stucco wall-covering revealed saturated sheathing and tar paper, as well as wet wood framing around the windows. An additional company hired by NPG to inspect the property in May and June of 2012 found heightened moisture levels in test sites around windows, stucco breaking away from beams, gaps around deck supports, and unsealed window joints.

Based on these reports, 328 LLC brought suit against NPG on June 14, 2012, alleging failure to exercise reasonable care in performing its duties as general contractor, including the negligent supervision of subcontractors and the negligent selection of building materials. NPG filed a third-party complaint against the respondent subcontractors for contribution and indemnity.

Free access — add to your briefcase to read the full text and ask questions with AI

328 Barry Avenue, LLC,Appellant v. Nolan Properties Group, LLC, and third party v. Carciofini Company, third party Marvin Windows, Inc., third party Minuti-Ogle Co., Inc., third party R.T.L Construction, Inc., third party Respondent,Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party, (Mich. 2015).

328 Barry Avenue, LLC,Appellant v. Nolan Properties Group, LLC, and third party v. Carciofini Company, third party Marvin Windows, Inc., third party Minuti-Ogle Co., Inc., third party R.T.L Construction, Inc., third party Respondent,Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party (328 Barry Avenue, LLC,Appellant v. Nolan Properties Group, LLC, and third party v. Carciofini Company, third party Marvin Windows, Inc., third party Minuti-Ogle Co., Inc., third party R.T.L Construction, Inc., third party Respondent,Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lietz v. Northern States Power Co.
718 N.W.2d 865 (Supreme Court of Minnesota, 2006)
In Re Stadsvold
754 N.W.2d 323 (Supreme Court of Minnesota, 2008)
In Re UnitedHealth Group Inc. Shareholder Derivative Litigation
754 N.W.2d 544 (Supreme Court of Minnesota, 2008)
DLH, Inc. v. Russ
566 N.W.2d 60 (Supreme Court of Minnesota, 1997)
Appletree Square 1 Ltd. Partnership v. W.R. Grace & Co.
815 F. Supp. 1266 (D. Minnesota, 1993)
Day Masonry v. Independent School District 347
781 N.W.2d 321 (Supreme Court of Minnesota, 2010)
Molloy v. Meier
679 N.W.2d 711 (Supreme Court of Minnesota, 2004)
Vlahos v. R&I Construction of Bloomington, Inc.
676 N.W.2d 672 (Supreme Court of Minnesota, 2004)
City of Willmar v. Short-Elliott-Hendrickson, Inc.
475 N.W.2d 73 (Supreme Court of Minnesota, 1991)
Jackson v. Mortgage Electronic Registration Systems, Inc.
770 N.W.2d 487 (Supreme Court of Minnesota, 2009)
Nord v. Herreid
305 N.W.2d 337 (Supreme Court of Minnesota, 1981)
Citizens State Bank Norwood Young America v. Gordon Brown
849 N.W.2d 55 (Supreme Court of Minnesota, 2014)
Seagate Technology, LLC v. Western Digital Corporation, Sining Mao
854 N.W.2d 750 (Supreme Court of Minnesota, 2014)
Great River Energy v. David D. Swedzinski
860 N.W.2d 362 (Supreme Court of Minnesota, 2015)
County of Dakota v. Cameron
839 N.W.2d 700 (Supreme Court of Minnesota, 2013)