24 HR AIR SERVICE, INC. v. HOSANNA COMMUNITY BAPTIST CHURCH, INC.

CourtDistrict Court of Appeal of Florida
DecidedJune 9, 2021
Docket21-0061
StatusPublished

This text of 24 HR AIR SERVICE, INC. v. HOSANNA COMMUNITY BAPTIST CHURCH, INC. (24 HR AIR SERVICE, INC. v. HOSANNA COMMUNITY BAPTIST CHURCH, INC.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
24 HR AIR SERVICE, INC. v. HOSANNA COMMUNITY BAPTIST CHURCH, INC., (Fla. Ct. App. 2021).

Opinion

Third District Court of Appeal State of Florida

Opinion filed June 9, 2021. Not final until disposition of timely filed motion for rehearing.

________________

No. 3D21-61 Lower Tribunal Nos. 16-20107 CC and 19-264AP ________________

24 Hr Air Service, Inc., Appellant,

vs.

Hosanna Community Baptist Church, Inc., Appellee.

An Appeal from the County Court for Miami-Dade County, Christina Marie DiRaimondo, Judge.

Law Office of Alexander Alvarez, and Alexander Alvarez and Anamari C. Del Rio, for appellant.

Pierre Simon, and Faudlin Pierre (Fort Lauderdale), for appellee.

Before LOGUE, LINDSEY, and GORDO, JJ.

LOGUE, J. 24 Hr Air Service, Inc. (“Contractor”), appeals from the county court’s

entry of final judgment in favor of Hosanna Community Baptist Church, Inc.

following a bench trial. We affirm the county court’s judgment that the

Contractor anticipatorily breached the service agreement between the

parties. However, we reverse the damage award because the court applied

an improper measure of damages by awarding the Church the cost for

installation of a new air conditioning unit, rather than the cost of repairing the

existing unit as contemplated by the parties in the service agreement.

This dispute arises from a service contract between the parties

involving repairs to a smoke detector and air conditioning unit. The

Contractor, a licensed air conditioning company, agreed to repair the smoke

detector and AC unit in the Church’s building. The Church agreed to pay

$765.00 for the smoke detector repair and $922.30 for the AC unit repair.

After the Contractor’s employees entered the church’s attic to start the

repairs, they realized that the wooden platform they were standing on was

caving in and ran before part of the ceiling collapsed. After the ceiling

structure was repaired by the Church, the Contractor refused to return and

complete the agreed repairs to the smoke detector and AC unit for safety

reasons. The Church sued the Contractor for refusing to complete the

agreed repairs.

2 At the bench trial, Reverend Charles Dinkins testified on behalf of the

Church. He confirmed that the Church had contacted the Contractor to repair

the smoke detector and AC unit, that the repairs were never completed, and

that the Church was willing and able to pay the agreed upon price after

completion of the repairs.

Reverend Dinkins also testified regarding the amounts paid by the

Church to complete the repairs to the smoke detector ($1,400.00) and the

AC unit ($9,998.00). His testimony also revealed that the repair cost for the

smoke detector was absorbed in the Church’s annual security bill.

Additionally, the repair cost for the AC unit included inspections from two

service companies that suggested replacement of the AC unit.

Michael Dunn, corporate representative of the Contractor, testified that

the Contractor refused to go back to perform the agreed repairs “because of

safety reasons,” and that he had requested proof of the ceiling repairs from

the Church, which were never provided.1

1 We note the trial court’s findings of fact incorrectly states the Contractor “never requested . . . proof that the ceiling was repaired in a workmanlike condition.” This fact, however, is undisputed as evidenced by Mr. Dunn’s testimony at trial: QUESTION: And then the Church contacts you to repair, to come back and complete the job, correct? ANSWER: Yes. QUESTION: And you said you wanted information that the ceiling was conformed to workman-like, correct?

3 The trial court entered final judgment in favor of the Church and

awarded damages totaling $9,710.70 based on the difference between the

agreed cost of repairs and the cost to complete the repairs paid by the

Church. The Contractor now appeals.

a. Anticipatory Breach

“In reviewing a final judgment rendered from a non-jury trial, the trial

court’s findings of fact are clothed with a presumption of correctness. We

apply a clear error standard to the findings of fact, and a finding will not be

disturbed unless it is totally unsupported by competent and substantial

evidence, it is clearly against the weight of the evidence, or it was induced

by an erroneous view of the law.” La Ley Sports Complex at the City of

Homestead, LLC v. City of Homestead, 255 So. 3d 468, 469 (Fla. 3d DCA

2018) (citations omitted). Moreover, the final judgment may be affirmed for

reasons other than those articulated by the trial court. See Dade Cnty. Sch.

Bd. v. Radio Station WQBA, 731 So. 2d 638, 644–45 (Fla. 1999) (explaining

under “tipsy coachman” rule, when a trial court reaches the right result but

ANSWER: Yes. * * * QUESTION: Did you request the church to provide you with proof that the repairs had been done? ANSWER: Yes. QUESTION: And did they provide that? ANSWER: No.

4 for the wrong reasons, an appellate court may uphold the result if there is

any basis to support the judgment in the record).

There is competent substantial evidence in the record to support a

claim for anticipatory breach against the Contractor. “A prospective breach

of contract occurs when there is absolute repudiation by one of the parties

prior to the time when his performance is due under the terms of the contract.

Such a repudiation may be evidenced by words or voluntary acts but the

refusal must be distinct, unequivocal, and absolute.” Mori v. Matsushita Elec.

Corp. of America, 380 So. 2d 461, 463 (Fla. 3d DCA 1980). Moreover,

repudiation can be shown where one party makes additional demands not

included in the initial agreement:

The law is clear that where one party to the contract arbitrarily demands performance not required by the contract and couples this demand with a refusal to further perform unless the demand is met, the party has anticipatorily repudiated the contract, which anticipatory repudiation relieves the non-breaching party of its duty to further perform and creates in it an immediate cause of action for breach of contract.

Twenty-Four Collection, Inc. v. M. Weinbaum Constr., Inc., 427 So. 2d 1110,

1111 (Fla. 3d DCA 1983) (internal citations omitted).

The Contractor’s request that the Church provide safety assurances of

the ceiling repairs constitutes an additional demand that was not agreed to

5 by the parties under the service contract.2 Despite the Contractor’s argument

that it never abandoned the job, its demand for safety assurances coupled

with its refusal to complete the agreed repairs until such assurances were

provided was an anticipatory breach of the contract. See id. at 1111–12 (“A

requirement of actual breach as a prerequisite for anticipatory breach would

totally nullify the doctrine of anticipatory breach.”).

Therefore, the trial court correctly entered final judgment for the Church

on its claim for anticipatory breach as there is competent substantial

evidence to support the judgment.

b. Damages

“A trial court’s determination as to the method of calculating damages

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rector v. Larson's Marine, Inc.
479 So. 2d 783 (District Court of Appeal of Florida, 1985)
Koplowitz v. Girard
658 So. 2d 1183 (District Court of Appeal of Florida, 1995)
Taylor v. Lee
884 So. 2d 222 (District Court of Appeal of Florida, 2004)
Mori v. MATSUSHITA ELEC. CORP., ETC.
380 So. 2d 461 (District Court of Appeal of Florida, 1980)
Dade Cty. Sch. Bd. v. Radio Station WQBA
731 So. 2d 638 (Supreme Court of Florida, 1999)
Twenty-Four Collection, Inc. v. M. Weinbaum Construction, Inc.
427 So. 2d 1110 (District Court of Appeal of Florida, 1983)
Campbell v. Rawls
381 So. 2d 744 (District Court of Appeal of Florida, 1980)
Tubby's Customs, Inc. v. Euler
225 So. 3d 405 (District Court of Appeal of Florida, 2017)
Katz Deli of Aventura, Inc. v. Waterways Plaza, LLC
183 So. 3d 374 (District Court of Appeal of Florida, 2013)
La Ley Sports Complex at the City of Homestead, LLC v. City of Homestead
255 So. 3d 468 (District Court of Appeal of Florida, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
24 HR AIR SERVICE, INC. v. HOSANNA COMMUNITY BAPTIST CHURCH, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/24-hr-air-service-inc-v-hosanna-community-baptist-church-inc-fladistctapp-2021.