2300 Pennsylvania Avenue, LLC v. Harkins Builders, Inc.

513 F. App'x 273
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 4, 2013
Docket12-1346
StatusUnpublished

This text of 513 F. App'x 273 (2300 Pennsylvania Avenue, LLC v. Harkins Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
2300 Pennsylvania Avenue, LLC v. Harkins Builders, Inc., 513 F. App'x 273 (4th Cir. 2013).

Opinion

Affirmed by unpublished PER CURIAM opinion.

Unpublished opinions are not binding precedent in this circuit.

PER CURIAM:

2300 Pennsylvania Avenue, LLC, brought this action against Harkins Builders, Inc., alleging breach of contract, fraud, and negligence arising out of a contract for the construction of a building project in Washington, D.C. The district court granted summary judgment to 2800 as to Har-kins’ liability for liquidated damages. Following a bench trial, the court entered judgment for 2800, in the total amount of $3,922,189 in damages. Harkins appeals, raising several arguments. We affirm.

I.

In August 2008, 2300, as owner and developer, and Harkins, as general contractor, entered into a written contract for the construction of a mixed-use apartment and retail building project in Washington, D.C. The contract consisted of several documents, including AIA Document A101-1997, the “Standard Form of Agreement Between Owner and Contractor,” AIA Document A201-1997, the “General Conditions of the Contract for Construction,” and “Modifications issued after execution of’ the A101-1997, which include the various numbered Change Orders.

A.

Relevant to this appeal, the contract requires windows meeting the performance requirements of an “HC-70 window,” a high-performance window. In December 2009, Harkins discovered some of the windows leaked. After initial remediation efforts failed, Harkins learned that a manufacturing defect caused the leaks. Between December 2009 and October 2010, Harkins and its subcontractors undertook at least five remediation efforts on the windows, testing after each remediation. These efforts involved drilling holes, injecting foam compound and seam sealer, applying new sealant and caulking, and installing redesigned sashes. On August 2, 2010, 2300 retained a testing agency that tested 24 window openings. Two openings failed but were remediated and tested with successful results that same day. At least as late as December 2010, the project architect observed some window leaks.

Also in December 2009, Harkins observed approximately twenty leaks in the garage walls. The leaks appeared at approximately the same height and in “pretty consistent intervals.” Harkins’ sub-contractor, Prospect Waterproofing Co., said that “capillary action” caused the uniform leaks in the walls and denied responsibility. Harkins accepted responsibility for the leaks; Prospect conducted the repairs. Despite several rounds of repairs, which included injecting cement and chemical grout in the leaking areas, the project architect continued to observe leaks in late 2010 and spring 2011. The architect noted that the leak heights correlated to the approximate horizontal boundary between the two waterproofing systems. In light of the “pattern created by the water penetration,” the architect also determined that “the waterproofing in the garage was either damaged or not installed properly,” *275 due to “poor quality waterproofing, improper installation, or postinstallation damage.”

The contract requires Harkins to achieve “Substantial Completion” of the entire building by April 25, 2010. Under the contract, the architect’s “Certificate of Substantial Completion shall establish the date of Substantial Completion.”

The architect’s certification must be made “in accordance with Section 9.8,” which provides that the architect will determine that the building is substantially complete when it “is sufficiently complete in accordance with the Contract Documents so that [2300] can occupy or utilize the [building] for its intended use.” Substantial completion is to be determined building-wide, rather than on a unit-by-unit basis. Under the contract, Harkins is liable for liquidated damages if it did not achieve substantial completion by April 25, 2010.

The D.C. Department of Consumer and Regulatory Affairs issued a Certificate of Occupancy on February 25, 2010, and tenants began moving into units two days later. A month later, on March 30, Har-kins requested payment of a $150,000 “Substantial Completion Incentive Bonus” established by Change Order 9, which modified the liquidated damages and bonus provisions of the contract. In Change Order 91 dated April 23, 2010, the architect approved and 2300 agreed to pay Har-kins a $150,000 bonus, which was called a “Certificate of Occupancy Bonus.”

By letter dated July 13, 2010, Harkins requested that the architect issue the Certificate of Substantial Completion. On September 23, 2010, the architect issued the certificate, which set August 2, 2010 as the Date of Substantial Completion. The architect attached to the certificate a “punch list” of tasks that Harkins was to complete before final payment would issue. On October 5, 2010, Harkins advised 2300 that it would not execute the Certificate unless the Date of Substantial Completion was changed to April 25, 2010, and the punch list removed. 2300 did not do this but did execute the certificate on October 7, 2010.

B.

On November 19, 2010, 2300 filed a five-count complaint against Harkins in the United States District Court for the Eastern District of Virginia. In its complaint, 2300 alleged that Harkins breached its express and implied obligations to 2300 by furnishing deficient windows and damaged garage waterproofing, and by failing to properly construct and install the roof, adhere to specified building dimensions required by federal law, timely complete the work, and submit required documentation to 2300. 2300 further alleged that Harkins failed to act in good faith and deal fairly with 2300, and breached its express and implied warranties under the contract. Finally, 2300 alleged that Harkins negligently “breached its duty to exercise reasonable care and competence by performing substandard and defective work.”

Harkins answered the complaint and asserted a counterclaim for breach of contract, alleging that 2300 had withheld the $510,000 contract balance even though Harkins “fully and properly fulfilled all of its obligations under the contract.” In March 2011, after being granted leave to do so, 2300 filed an amended complaint, adding a fraud count, which Harkins answered.

Shortly thereafter, upon the close of discovery, each party moved for partial summary judgment. The court granted summary judgment to 2300 as to liability on its liquidated damages claim, finding Harkins had failed to achieve substantial comple *276 tion under the contract prior to August 2, 2010. The court denied the parties’ remaining motions for summary judgment. After a bench trial, the court issued a memorandum opinion and order for judgment to 2800, finding that Harkins had breached the contract with respect to the windows and waterproofing. The court further found that 2300 failed to demonstrate by a preponderance of the evidence that the roof did not meet contract specifications, but in light of the parties’ agreement, found 2800 entitled to compensation to relocate the roof condenser. The court awarded 2300 damages in the amount of $3,922,189, which included $2,683,962 for window replacement, $210,000 for waterproofing repair and maintenance, $3,500 to relocate the roof condenser, $637,200 in liquidated damages, and $387,527 in associated fees and costs. As to 2300’s fraud and negligence claims, the court awarded judgment to Harkins.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Noel v. Artson
641 F.3d 580 (Fourth Circuit, 2011)
1010 Potomac Associates v. Grocery Manufacturers of America, Inc.
485 A.2d 199 (District of Columbia Court of Appeals, 1984)
Affordable Elegance Travel, Inc. v. Worldspan, L.P.
774 A.2d 320 (District of Columbia Court of Appeals, 2001)
Holland v. Hannan
456 A.2d 807 (District of Columbia Court of Appeals, 1983)
NEST AND TOTAH VENTURE, LLC v. Deutsch
31 A.3d 1211 (District of Columbia Court of Appeals, 2011)
Gasperini v. Center for Humanities, Inc.
518 U.S. 415 (Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
513 F. App'x 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/2300-pennsylvania-avenue-llc-v-harkins-builders-inc-ca4-2013.