20230209_C359213_45_359213.Opn.Pdf

CourtMichigan Court of Appeals
DecidedFebruary 9, 2023
Docket20230209
StatusUnpublished

This text of 20230209_C359213_45_359213.Opn.Pdf (20230209_C359213_45_359213.Opn.Pdf) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
20230209_C359213_45_359213.Opn.Pdf, (Mich. Ct. App. 2023).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

LEGACY CUSTOM BUILDERS, INC., FOR PUBLICATION February 9, 2023 Plaintiff-Appellant, 9:15 a.m.

v No. 359213 Oakland Circuit Court SALLY A NOERR ROGERS, LC No. 2021-187535-CH

Defendant-Appellee.

Before: LETICA, P.J., and SERVITTO and HOOD, JJ.

HOOD, J.

Plaintiff, Legacy Custom Builders, Inc. (Legacy), appeals as of right the trial court’s order granting summary disposition and compelling arbitration in favor of defendant, Sally A. Noerr Rogers (Rogers). The trial court correctly enforced a valid agreement to arbitrate, but it should have stayed proceedings pending arbitration instead of dismissing the case. We, therefore, affirm in part, reverse in part, and remand for proceedings consistent with this opinion.

I. BACKGROUND

This case arises out of a contract dispute over the construction of a home on a vacant residential property in White Lake, Michigan. Rogers is the owner of the property. Legacy is a home construction company.

In July 2020, Rogers contracted with Legacy to build a house on her vacant land. Relevant to this appeal, the contract contained an arbitration provision. Under Article XVI, entitled “Disputes,” the contract provided that Legacy and Rogers resolve any dispute through arbitration. In its relevant part, Article XVI stated:

Any dispute between Builder and Purchaser about this Contract, including the interpretation of this Contract and adequacy of performance of this Contract, shall be resolved by arbitration before a single arbitrator who is mutually acceptable to Builder and Purchaser. . . . The decision of the arbitrator on any dispute shall be final and binding on the parties and enforceable in any court of appropriate jurisdiction. In any arbitration proceeding under this Article subject to the award

-1- of the arbitrator, each party shall pay its own expenses, [and] an equal share of the fees and expenses of the arbitrator. The arbitrator shall have the power to award recovery of costs and fees (including reasonable attorney fees, administrative fees, and arbitrator’s costs and fees) among the parties as the arbitrator determines to be equitable under the circumstances.

In January 2021, the parties had a dispute. Legacy claimed that Rogers failed to pay invoices and failed to make selections and decisions related to work on the project. Rogers disputed invoices, asked for documentation supporting Legacy’s invoices, and appears to have sought an accounting to determine how Legacy used money on the project. Through their attorneys, each party accused the other of breaching the contract. Legacy threatened to file a construction lien, and Rogers indicated she was seeking to invoke the arbitration clause of the parties’ agreement. On January 12, 2021, Legacy furnished its last labor or supplies on the project.

On February 4, 2021, Legacy recorded a claim of lien related to Rogers’s property and later served a copy of the claim of lien on Rogers’s attorney. The claim of lien indicated that Legacy had received $548,653.46 related to the construction project, but claimed a lien for $177,905.83, plus interest, costs, and attorneys fees under the contract. The claim of lien indicated that this did not include $232,432.17 “of the contract which was not completed due to the termination of [the] contract.”

On April 20, 2021, Legacy filed a complaint suing Rogers. The complaint raised five claims: (1) breach of contract; (2) promissory estoppel; (3) quantum meruit; (4) declaratory relief; and (5) foreclosure of the construction lien. It alleged Rogers breached the parties’ contract when she failed to respond to inquiries regarding the construction project and failed to pay various invoices. Based on Rogers’s alleged failure to pay Legacy, it also sought foreclosure of the construction lien it recorded against Rogers’s property.

In June 2021, in lieu of an answer, Rogers moved for summary disposition of Legacy’s complaint under MCR 2.116(C)(7) and (D)(2), and sought to compel arbitration. Rogers argued that summary disposition was appropriate because the parties’ contract included an arbitration provision that required the parties to arbitrate “any” dispute arising under the contract between Legacy and Rogers. Rogers asserted that if Legacy continued to refuse to comply with arbitration and continued litigation, Legacy could be held to have waived its right to arbitration. Rogers also sought fees and costs under the contract for Legacy’s purported failure to comply with the arbitration agreement.

Legacy responded arguing that enforcing the arbitration agreement would prevent it from complying with the one-year limitation period for recording and foreclosing on a lien even if it was successful. It further argued that the arbitrator did not have authority to determine an interest in land. Finally, it argued that Rogers was required to identify her claims prior to arbitration and that Legacy was not required to arbitrate unknown issues. Legacy also sought sanctions, arguing that Rogers’s motion and request for sanctions was frivolous and intended to delay and harass Legacy.

-2- On September 22, 2021, the trial court entered an order granting Rogers’s motion for summary disposition and compelling arbitration. The trial court dispensed with oral argument and found that the contract “clearly directs ‘any’ dispute arising out of the contract be arbitrated.” Accordingly, the trial court granted Rogers’s motion for summary disposition under MCR 2.116(C)(7) and ordered arbitration.

Legacy moved for reconsideration. In addition to previously raised arguments, Legacy argued that, instead of dismissing its lien foreclosure claim, the trial court should have stayed that portion of the lawsuit and “allowed it to pick back up after” there was an arbitration award. This appears to have been Legacy’s first explicit request for the court to stay proceedings. Although Legacy claims to have offered Rogers’s counsel to stay proceedings, it did not file a motion to stay proceedings pending arbitration, and it did not request a stay as alternative relief in its response to Rogers’s motion for summary disposition. The trial court denied the motion for reconsideration. This appeal followed.

II. STANDARDS OF REVIEW

This Court reviews de novo a trial court’s decision on a motion for summary disposition. Tinsley v Yatooma, 333 Mich App 257, 261; 964 NW2d 45 (2020). In RDM Holdings, Ltd v Continental Plastics Co, 281 Mich App 678, 687; 762 NW2d 529 (2008), this Court articulated the rules governing dispositive motions filed under MCR 2.116(C)(7):

Under MCR 2.116(C)(7) . . . , this Court must consider not only the pleadings, but also any affidavits, depositions, admissions, or other documentary evidence filed or submitted by the parties. The contents of the complaint must be accepted as true unless contradicted by the documentary evidence. This Court must consider the documentary evidence in a light most favorable to the nonmoving party. If there is no factual dispute, whether a plaintiff’s claim is barred under a principle set forth in MCR 2.116(C)(7) is a question of law for the court to decide. If a factual dispute exists, however, summary disposition is not appropriate. [Citations omitted.]

Summary disposition is proper under MCR 2.116(C)(7) when a claim is barred because of “an agreement to arbitrate . . . .” See Tinsley, 333 Mich App at 261, citing Altobelli v Hartmann, 499 Mich 284, 294-295; 884 NW2d 537 (2016) (stating the same). “Whether a claim is subject to arbitration is also reviewed de novo, as is the construction of contractual language.” Id. (citation omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James v. Logee
388 N.W.2d 294 (Michigan Court of Appeals, 1986)
Fromm v. Meemic Insurance
690 N.W.2d 528 (Michigan Court of Appeals, 2005)
City of Ferndale v. Florence Cement Co.
712 N.W.2d 522 (Michigan Court of Appeals, 2006)
Rdm Holdings, Ltd v. Continental Plastics Co
762 N.W.2d 529 (Michigan Court of Appeals, 2008)
Mair v. Consumers Power Co.
348 N.W.2d 256 (Michigan Supreme Court, 1984)
Fed. Kemper Ins. Co. v. AM. BANKERS INS. CO. OF FL.
357 N.W.2d 834 (Michigan Court of Appeals, 1984)
Garrett v. Washington
886 N.W.2d 762 (Michigan Court of Appeals, 2016)
Altobelli v. Hartmann
884 N.W.2d 537 (Michigan Supreme Court, 2016)
Ronnisch Construction Group, Inc v. Lofts on the Nine, LLC
886 N.W.2d 113 (Michigan Supreme Court, 2016)
the Meisner Law Group v. Weston Downs Condominium Association
909 N.W.2d 890 (Michigan Court of Appeals, 2017)
Varga v. Heritage Hospital
362 N.W.2d 282 (Michigan Court of Appeals, 1984)
Kaftan v. Kaftan
300 Mich. App. 661 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
20230209_C359213_45_359213.Opn.Pdf, Counsel Stack Legal Research, https://law.counselstack.com/opinion/20230209_c359213_45_359213opnpdf-michctapp-2023.