12 Gauge Construction, LLC v. Aron R. Thompson and Nicole R. Thompson

United States Bankruptcy Court, W.D. Wisconsin·Decided September 11, 2026·No. 3-23-00008·Unknown

Opinion

= a hy THIS ORDER IS SIGNED AND ENTERED. = a ~— Dated: September 11, 2026 7). Mm ie a Pe dy i ny a > “®Diaaion of 8

Hon. Rachel M. Blise United States Bankruptcy Judge UNITED STATES BANKRUPTCY COURT FOR THE WESTERN DISTRICT OF WISCONSIN In re: Case No. 22-11921-rmb Aron R. Thompson and Nicole R. Thompson, Chapter 7 Debtors. 12 Gauge Construction, LLC, Plaintiff, Adversary No. 23-00008-rmb v. Aron R. Thompson and Nicole R. Thompson, Defendants.

POST-TRIAL DECISION

Aron Thompson owned a construction company called Thompson Exteriors, LLC through which he provided mostly carpentry services. After Thompson Exteriors contracted with 12 Gauge Construction, LLC to provide rough carpentry for a 141-unit apartment building in Wausau, Wisconsin, Aron’s wife Nicole Thompson became more involved in the business. The project had problems from

the beginning, and 12 Gauge ultimately terminated the contract with Thompson Exteriors. 12 Gauge now contends that the Thompsons are both liable under Wisconsin’s theft by contractor statute and seeks to have the resulting debt

declared nondischargeable. Based on the evidence presented at trial, the Court concludes that both Thompsons are liable to 12 Gauge for theft by contractor and that the debt is nondischargeable under 11 U.S.C. § 523(a)(4). JURISDICTION The Court has jurisdiction over this adversary proceeding pursuant to 28 U.S.C. § 1334 and the order of reference from the district court pursuant to 28 U.S.C. § 157(a). See General Order No. 161 (W.D. Wis. June 12, 1984) (available at

https://www.wiwd.uscourts.gov/administrative-orders) (last visited September 10, 2026). Determination of the dischargeability of a debt is a core proceeding under 28 U.S.C. § 157(b)(2)(I). To the extent the determination of dischargeability requires consideration of issues impacted by the Supreme Court’s decision in Stern v. Marshall, 564 U.S. 462 (2011), the parties have consented to the bankruptcy court’s final adjudication of these issues. See Dkt. No. 15, ¶ 17; Dkt. No. 16, ¶ 17; see also

Fed. R. Bankr. P. 7008, 7012. This decision constitutes the Court’s findings of fact and conclusions of law pursuant to Bankruptcy Rule 7052 and Rule 52 of the Federal Rules of Civil Procedure. FINDINGS OF FACT The Parties and the Bantr Project Contract Aron Thompson formed Thompson Exteriors, LLC (“TE”) in 2019. Aron is the sole member of the LLC and responsible for all operations of the LLC. Before that, he worked for several construction companies for approximately 10 years, during which time he gained experience with many aspects of construction, with a focus on carpentry. When he formed TE, Aron started doing mostly residential construction

work, and he obtained a dwelling contractor license in March 2021. To obtain that license, he took a course and an exam that included information about Wisconsin’s theft by contractor laws. On March 15, 2021, Aron was criminally charged with theft by contractor under Wis. Stat. § 943.20(3)(a). Ex. 139. A lumber yard filed a lien on the owner’s property because TE did not timely pay the bill. Aron says the charge related to a

dispute over supplies he ordered that were not delivered. Aron retained counsel, and the matter was resolved through a deferred prosecution agreement. Aron’s wife, Nicole Thompson, was aware of Aron’s legal troubles and the basis for the charges against him, in part because Nicole provided the retainer to Aron’s defense counsel. See Ex. 31 at 5. Nicole testified that after Aron was criminally charged she was aware of Wisconsin’s theft by contractor law, she was aware that project funds could be used only for project expenses, and she was aware that there could

be significant consequences for failing to account for project funds. 2/11/2025 Tr. at 60:11-64:22. 12 Gauge Construction, LLC is a construction company owned by James Worthington and Dale Hudack. 12 Gauge generally functions as a general contractor, managing construction projects and hiring subcontractors to do most of the work. The company is based in Madison but manages projects throughout Wisconsin. In August 2021, 12 Gauge contracted with Bantr on Elm LLC to build a 141-

unit apartment complex (the “Bantr Project” or the “Project”). Ex. 1. The Bantr Project was on a tight deadline, and construction needed to begin almost immediately. In planning the Project and retaining subcontractors, 12 Gauge determined that it would need to hire a contractor to do the rough carpentry (framing) work. The initial plan was to use a company Hudack and Worthington referred to as Eagle Framing, because 12 Gauge had worked with the company on

other projects and had been very satisfied with their work. 12 Gauge needed the rough carpentry subcontractor to begin work in January 2022 as soon as the foundation was poured. The Eagle Framing crew was occupied on other projects during that time, so 12 Gauge needed to work with a different framing subcontractor that could start in January. Around the same time 12 Gauge was looking for a rough carpentry subcontractor for the Bantr Project, 12 Gauge was working on another project with

Aron and TE in Madison, Wisconsin that the parties referred to as the “MBS Project.” The contract between 12 Gauge and TE for that project was $180,600; with change orders the payments to TE totaled $261,258. Exs. 126-127. 12 Gauge was satisfied with TE’s work on the MBS Project, so Hudack and Worthington approached Aron about TE working on the Bantr Project. The Bantr Project would be by far the largest project that TE had ever worked on. Aron met with Worthington in early January 2022 to discuss the Bantr Project. During the meeting, Aron told Worthington that he “could get 20-plus guys to go up [to Wausau].” 2/11/2025 Tr. at 204:12-17. Worthington was satisfied with

his conversation with Aron, and on January 7, 2022, 12 Gauge sent a draft contract to Aron to review. Ex. 47. When Aron made the statement to Worthington, Aron knew that TE did not have 20 employees or crew members available to work on the project and that he would need to find the necessary laborers. Aron did not tell Worthington this because Aron believed he could easily find about 10 crew members to hire as employees of TE and that he could obtain 10 crew members from All

Seasons Drywall, a company that provides laborers for construction projects. 2/11/2025 Tr. at 205:3-10. On January 13, 2022, Aron had another meeting, this time with both Worthington and Hudack, to discuss the architectural plans, logistics for the Project, and the schedule. The Bantr Project had three sections—a north wing, a west wing, and a center portion. TE would begin work on the north wing while the foundation was poured for the center and the west wing. Each wing was

Free access — add to your briefcase to read the full text and ask questions with AI

12 Gauge Construction, LLC v. Aron R. Thompson and Nicole R. Thompson, (Wis. 2026).

12 Gauge Construction, LLC v. Aron R. Thompson and Nicole R. Thompson (12 Gauge Construction, LLC v. Aron R. Thompson and Nicole R. Thompson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ojeda v. Goldberg
599 F.3d 712 (Seventh Circuit, 2010)
Grogan v. Garner
498 U.S. 279 (Supreme Court, 1991)
Field v. Mans
516 U.S. 59 (Supreme Court, 1995)
Cohen v. De La Cruz
523 U.S. 213 (Supreme Court, 1998)
Reeves v. Davis
638 F.3d 549 (Seventh Circuit, 2011)
Stern v. Marshall
131 S. Ct. 2594 (Supreme Court, 2011)
Bullock v. BankChampaign, N. A.
133 S. Ct. 1754 (Supreme Court, 2013)
KBS CONSTR. v. McCULLOUGH PLUMBING
2010 WI App 19 (Court of Appeals of Wisconsin, 2009)
State v. Sobkowiak
496 N.W.2d 620 (Court of Appeals of Wisconsin, 1992)
Capital City Sheet Metal, Inc. v. Voytovich
578 N.W.2d 643 (Court of Appeals of Wisconsin, 1998)
Capen Wholesale, Inc. v. Probst
509 N.W.2d 120 (Court of Appeals of Wisconsin, 1993)
Ritchie v. Clappier
326 N.W.2d 131 (Court of Appeals of Wisconsin, 1982)
State v. Keyes
2008 WI 54 (Wisconsin Supreme Court, 2008)
State v. Blaisdell
270 N.W.2d 69 (Wisconsin Supreme Court, 1978)
Ollerman v. O'Rourke Co., Inc.
288 N.W.2d 95 (Wisconsin Supreme Court, 1980)
Tri-Tech Corp. of America v. Americomp Services, Inc.
2002 WI 88 (Wisconsin Supreme Court, 2002)
Nunnery v. Rountree (In Re Rountree)
330 B.R. 166 (E.D. Virginia, 2004)