11 Essex St. Corp. v. Tower Ins. Co. of N.Y.

2017 NY Slip Op 6709, 153 A.D.3d 1190, 63 N.Y.S.3d 13
CourtAppellate Division of the Supreme Court of the State of New York
DecidedSeptember 28, 2017
Docket600176/04 -110019/04 101984/05 590172/06 590479/06 590879/06 590972/06 4156 4155
StatusPublished
Cited by4 cases

This text of 2017 NY Slip Op 6709 (11 Essex St. Corp. v. Tower Ins. Co. of N.Y.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
11 Essex St. Corp. v. Tower Ins. Co. of N.Y., 2017 NY Slip Op 6709, 153 A.D.3d 1190, 63 N.Y.S.3d 13 (N.Y. Ct. App. 2017).

Opinion

Order, Supreme Court, New York County (Geoffrey D. Wright, J.), entered August 27, 2015, which granted defendant DeSimone Consulting Engineers’ (DCE) motion for a directed verdict dismissing all claims and cross claims against it, unanimously affirmed, without costs. Order, same court and Justice, entered October 13, 2015, which granted defendant Berzak Gold, P.C.’s (Berzak) motion for a directed verdict dismissing the complaint as against it, unanimously reversed, on the law, without costs, the motion denied, and the matter remanded for a new trial. Amended order, same court and Justice, entered April 28, 2016, which granted Berzak’s motion for a directed verdict dismissing defendant Jeffrey M. Brown Associates, Inc.’s (JMB) cross claims and granted JMB’s motion for a directed verdict dismissing the claims for gross negligence and punitive damages against it, unanimously modified, on the law, to deny JMB’s motion and to deny Berzak’s motion as to its breach of contract, contribution and common-law indemnification claims, and otherwise affirmed, without costs.

These appeals arise out of a months-long trial that ultimately *1191 resulted in a mistrial. Over a two-month period, plaintiff, the owner of a five-story walk-up apartment building, called 11 witnesses, including an expert who testified over the course of seven days through two rounds of direct and two rounds of cross-examination. The issue in the case was whether defendants were liable for the damage to plaintiff’s building caused when construction on a neighboring site resulted in the alleged shifting of plaintiff’s building’s foundation. Plaintiff asserted that the underpinning installed to prevent such movement was inadequate. JMB was the general contractor retained by defendant 7 Essex Street, LLC, the owner of three lots next to plaintiff’s property, to demolish the buildings on the lots and construct a 10-story condominium building in their place. 7 Essex also retained an architect, and the architect hired defendant DCE to perform the structural design for the new building. Berzak was retained by JMB as a consultant to design an underpinning system.

After plaintiff’s expert, Nathaniel Smith, had been subjected to re-cross-examination, and plaintiff’s counsel reserved the right to call Smith back for re-redirect, DCE and Berzak announced their intentions to move for a directed verdict. The court stated that it would entertain written submissions. Plaintiff objected, arguing that the end of Smith’s testimony was still extant, and that it still had remaining witnesses to call, including an additional expert for whom plaintiff had produced a CPLR 3101 (d) exchange. Further, plaintiff had not yet completed his examination of Berzak’s witness, Stuart Gold.

In support of its motion, DCE argued that plaintiff had not made out a prima facie case because Smith, plaintiff’s own expert, had testified unequivocally that DCE was not liable. That was because the only connection between DCE and the underpinning was a Statement of Technical Responsibility (TR-1) executed by DCE and filed by it with the Department of Buildings (DOB). The TR-1 represented that DCE would perform controlled inspections of the underpinning. However, DCE pointed to testimony from Smith that in such a scenario the party can only have liability if it actually filed underpinning plans, which DCE indisputably did not. DCE further argued that, in any event, and as acknowledged by Smith, it did not receive 72-hour written notice of commencement of the underpinning work. It also noted that, pursuant to former Administrative Code of the City of New York § 27-195, a party responsible for performing controlled inspections must be given such notice before its obligation is triggered.

*1192 In support of its motion for a directed verdict, Berzak argued that the court had already found that Smith was not qualified to opine about whether, by the professional standards in place in 2002, when the underpinning work had been performed, its plan was appropriate. That was because, by Smith’s own admission, he was working in Massachusetts at the time and was not familiar with the particulars of New York engineering practice. For that reason, Berzak asserted, plaintiff could not make out a prima facie case against it. Berzak further argued that the underpinning was performed according to a plan it had designed for preliminary purposes only, and which it had not signed or sealed, much less obtained DOB approval for. Accordingly, it had no expectation that JMB would instruct its underpinning contractor to work off the plan. To the extent plaintiff was also seeking to hold Berzak liable based on a TR-1 it signed indicating that it would perform controlled supervision of the underpinning, it noted that it signed its TR-1 after the damage to plaintiff’s building had already occurred. Similar to DCE, it also asserted that it did not receive the requisite 72-hour notice.

In opposition to the motions of both DCE and Berzak, plaintiff argued that they were premature. This was because, as noted above, plaintiff’s counsel had not yet completed the examination of Smith, nor had he been given an opportunity to call a second structural engineering expert. Further, plaintiff, relying on an earlier decision by Supreme Court that found an issue of fact whether DCE had responsibility for the underpinning by virtue of the TR-1, argued that the trial court was required to allow that issue to reach the jury. JMB opposed the DCE and Berzak motions as well. JMB also argued that the motions were premature, since it had not yet had an opportunity to question Gold, Berzak’s witness, nor had it had an opportunity to call its own expert witness to prove DCE’s and Berzak’s liability. JMB also pointed to trial testimony that Gold had already given, as well as deposition testimony from an engineer employed by Berzak, which it argued demonstrated that there were factual issues regarding Berzak’s liability that should have gone to the jury. JMB attached an affidavit from its designated expert explaining how he would have testified concerning Berzak’s behavior, which he opined departed from the appropriate standard of care.

In separate orders, the court granted both directed verdict motions. With respect to DCE, the court stated that “[p]laintiff points to no exhibits, in evidence already, or upcoming, that demonstrate [DCE’s] involvement with underpinning.” It *1193 disregarded the earlier ruling that there was an issue of fact concerning the TR-1, finding that it became irrelevant once the trial commenced. With respect to Berzak, the court pointed to Smith’s admitted lack of familiarity with the standards for underpinning design in New York City in 2002, such that plaintiff could not make out a prima facie case. The court further noted that JMB’s expert exchange, furnished three years earlier, addressed plaintiff’s behavior only, and not Berzak’s. Therefore, the court held, it would be prejudicial to Berzak to permit JMB to supplement the disclosure at such a late date.

On the same day the court issued its order directing a verdict in favor of Berzak, it orally declared a mistrial, based on the inability of several jurors to continue. Also on that day, JMB moved for a directed verdict dismissing the gross negligence and punitive damages claims asserted against it by plaintiff. It argued that the evidence showed, at best, ordinary negligence. In opposition, plaintiff argued, again, that the motion was premature because it had not rested its case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Padilla v. Absolute Realty Inc.
2021 NY Slip Op 03416 (Appellate Division of the Supreme Court of New York, 2021)
Cromedy v. City of New York
2019 NY Slip Op 7527 (Appellate Division of the Supreme Court of New York, 2019)
Matter of Pastor
2017 NY Slip Op 6729 (Appellate Division of the Supreme Court of New York, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 NY Slip Op 6709, 153 A.D.3d 1190, 63 N.Y.S.3d 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/11-essex-st-corp-v-tower-ins-co-of-ny-nyappdiv-2017.