103 Investors I, LP v. Square D Company

372 F.3d 1213, 64 Fed. R. Serv. 670, 2004 U.S. App. LEXIS 12439, 2004 WL 1399111
CourtCourt of Appeals for the Tenth Circuit
DecidedJune 23, 2004
Docket02-3345
StatusPublished
Cited by15 cases

This text of 372 F.3d 1213 (103 Investors I, LP v. Square D Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
103 Investors I, LP v. Square D Company, 372 F.3d 1213, 64 Fed. R. Serv. 670, 2004 U.S. App. LEXIS 12439, 2004 WL 1399111 (10th Cir. 2004).

Opinion

LUCERO, Circuit Judge.

At the heart of this appeal is a dispute over the admissibility of expert testimony in relation to the cause of a fire that occurred in the building of 103 Investors I, L.P. (“Investors”) on March 1, 2001. Square D Company (“Square D”), which manufactures electrical equipment, manufactured the building’s busways. Investors alleges that those busways caused the fire and seeks to introduce expert testimony toward the goal'of demonstrating that allegation.

Late in the discovery process, Investors attempted to add an additional party or, in the alternative, voluntarily dismiss the suit without prejudice. The district court denied both motions, and we AFFIRM on both issues. Having denied those motions, the district court granted summary judgment to Square D on the ground that Investors lacked admissible expert testimony that would demonstrate a manufacturing defect was present in the busways. Specifically, it found that Investors’ initial expert reports were inadmissible under Daubert v. Merrell Dow Pharmaceuticals, Inc., 509 U.S. 579, 113 S.Ct. 2786, 125 L.Ed.2d 469 (1993), and that its subsequent report was untimely. We conclude that the district court’s refusal to consider Investors’ subsequent expert report was an abuse of discretion; accordingly, we REVERSE and REMAND for proceedings consistent with this opinion.

I

On March 1, 2001, a fire occurred in the electrical room on the second floor of Investors’ office building. In the walls ran “busways,” which are systems of four insulated aluminum bars in aluminum casing that run from the basement to the top floor and distribute electricity to various floors. Square D manufactured the bus-ways, while another company installed them in 1978. During the months following the fire, Investors retained Carl Martin and Bryon Sherman as experts to investigate possible causes. Based on their analyses, Investors ultimately attributed the cause of the fire to a malfunction of the busways. Accordingly, it brought an action against Square D in state court on September 19, 2001, asserting theories of strict liability and negligence based on design defects, manufacturing defects, and failure to warn. Square D removed the case to federal court on October 18, 2001.

A detailed description of the discovery process is necessary to provide an understanding of the context of the present appeal. After conducting a scheduling conference, the district court issued a Scheduling Order on December 7, 2001. Among other things, the Scheduling Order set the following dates by which certain motions had to be filed and portions of discovery had to be completed: (1) Investors’ submission of expert reports by January 10, 2002; (2) Square D’s expert submissions by February 11, 2002; (3) any rebuttal expert reports by February 25, 2002; (4) motions to join additional parties by February 15, 2002; (5) potentially dispositive motions by May 3, 2002; and (6) all discovery completed by April 8, 2002.

These dates all changed, at the initial request of Square D and ultimately with the agreement of Investors. On April 4, 2002, the district court issued an Amended *1215 Scheduling Order, which set out the following revised dates: (1) Investors’ submission of expert reports by April 1, 2002; (2) Square D’s expert submissions by May 15, 2002; (3) any rebuttal expert reports by June 1, 2002; (4) motions to join additional parties by May 1, 2002; (5) potentially dispositive motions by June 3, 2002; and (6) all discovery completed by July 5, 2002.

Investors initially submitted two expert reports, one prepared on February 18, 2002, jointly by Martin and Sherman and the other prepared on March 25, 2002, by Martin. Under the Amended Scheduling Report, Investors’ reports were timely, and Square D had over a month remaining to file its expert reports. Square D instead filed for another extension. On May 20, 2002, the district court granted Square D’s motion to extend the deadline for its expert filings to June 14, 2002. Notably, the district court’s order changed none of the other dates. Thus, all dates other than the date on which Square D’s expert reports were due remained governed by the April 4 Amended Scheduling Order.

On June 3, 2002 (the due date for dis-positive motions under the Amended Scheduling Order), Square D moved for summary judgment, alleging that Investors lacked any admissible expert testimony or other evidence to establish liability. In accordance with the most recent time extension that it had received, on June 14, 2002, Square D filed its expert witness report. In response to Square D’s June 3 motion for summary judgment, on June 25, 2002, Investors filed an extensive motion requesting the following: (1) leave to amend the scheduling order; (2) leave to amend its complaint to join an additional party defendant; and (3) in the alternative, voluntary dismissal of its complaint without prejudice. On July 11, 2002, Investors submitted a third expert report, in which it attempts to rebut Square D’s expert report.

In a Memorandum and Order of September 2, 2002, the district court denied Investors’ procedural motions and granted summary judgment to Square D. In so doing, the district court refused to consider Investors’ July 11, 2002, expert report, explaining that it was untimely and that it espoused a “totally new theory of negligence.” 103 Investors I, L.P. v. Square D Company, 222 F.Supp.2d 1263, 1274 n. 10 (D.Kan.2002). Investors appealed, asserting inter alia the following claims of district court error: (1) the exclusion of the July 11, 2002 expert report; (2) the decision to grant Square D’s Daubert and summary judgment motions; (3) the refusal to allow Investors to amend its pleadings and add a party; and (4) the refusal to allow Investors to voluntarily dismiss its suit against Square D.

II

We allow a district court substantial latitude in its management of the discovery process, particularly in the context of our review of a decision to sanction the parties before it. Summers v. Missouri Pac. R.R. Sys., 132 F.3d 599, 604 (10th Cir.1997). Our standard of review is abuse of discretion. 1 Id.

The analytical process of the district court instructs our consideration of its decision to grant summary judgment to Square D. In granting summary judgment to Square D, the district court reasoned as follows, each decision depending on the one preceding it: (1) it refused to consider Investors’ July 11 expert report on the *1216 basis of its untimeliness; (2) citing its unwillingness to consider that report, it granted Square D’s Daubert motion; and (3) there being no expert testimony remaining, it granted Square D’s motion for summary judgment. That is to say, the court’s summary judgment grant was dependent on its decision to grant the Dau-bert motion, and the decision to grant the Daubert motion was similarly dependent on the court’s refusal to consider Investors’ rebuttal expert report.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rios v. Ramage
D. Kansas, 2021
Certain Underwriters v. Cameron Intl Corp.
951 F.3d 248 (Fifth Circuit, 2020)
Tyree v. Boston Scientific Corp.
54 F. Supp. 3d 501 (S.D. West Virginia, 2014)
Dale K. Barker Co., P.C. v. Sumrall
541 F. App'x 810 (Tenth Circuit, 2013)
Warden v. Exempla, Inc.
2012 CO 74 (Supreme Court of Colorado, 2012)
Rimbert v. Eli Lilly and Co.
647 F.3d 1247 (Tenth Circuit, 2011)
103 Investors I, LP v. Square D Company
470 F.3d 985 (Tenth Circuit, 2006)
Shulas v. Estabrook
895 A.2d 1234 (New Jersey Superior Court App Division, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
372 F.3d 1213, 64 Fed. R. Serv. 670, 2004 U.S. App. LEXIS 12439, 2004 WL 1399111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/103-investors-i-lp-v-square-d-company-ca10-2004.